In Progress

Area Building Inspection Type Milestones Progress Start Finish Next Milestone Status
10CMDF1 RPL10 L2 – Infrastructure 1/2
50%
04/24/2026 04/30/2026 100% – 04/30/2026 Past Due
10CMDF2 RPL10 L2 – Infrastructure 1/2
50%
04/24/2026 04/30/2026 100% – 04/30/2026 Past Due
10EF1b RPL10 L2 – Infrastructure 1/4
25%
06/22/2026 08/03/2026 50% – 07/13/2026 Upcoming
10EF1f RPL10 L2 – Infrastructure 3/4
75%
06/03/2026 06/16/2026 100% – 06/16/2026 Past Due
10GSEF1 RPL10 L2 – Infrastructure 1/2
50%
04/06/2026 04/08/2026 100% – 04/08/2026 Past Due
10GSEF2 RPL10 L2 – Infrastructure 1/2
50%
04/06/2026 04/08/2026 100% – 04/08/2026 Past Due
10GSMDF1 RPL10 L2 – Infrastructure 1/2
50%
05/04/2026 05/06/2026 100% – 05/06/2026 Past Due
10GSMDF2 RPL10 L2 – Infrastructure 1/2
50%
05/04/2026 05/06/2026 100% – 05/06/2026 Past Due

8 results