Building Report
Generated 06/17/2026 03:13 AM
Building Report — 06/17/2026
RPL10 ACC Checklists 0/335   |   KPA Milestones 25% 2/62, 50% 7/190, 75% 1/62, 100% 0/190
  • Insp10CMDF1 (L2 – Infrastructure): 1/0 ground cable needed
  • Insp10CMDF2 (L2 – Infrastructure): 1/0 ground cable needed
  • Insp10GSEF1 (L2 – Infrastructure): 24" triangle bracket needed RFI #DPR-NW-01258 OSE Label colors
  • Insp10GSEF2 (L2 – Infrastructure): 18" triangle bracket needed RFI #DPR-NW-01258 OSE Label colors
  • Insp10GSMDF1 (L2 – Infrastructure): 2 spill outs needed
  • Insp10GSMDF2 (L2 – Infrastructure): 2 spill outs needed
RPL9 ACC Checklists 0/180   |   KPA Milestones 25% 0/33, 50% 0/67, 75% 0/33, 100% 0/67
RPL8 ACC Checklists 0/160   |   KPA Milestones 25% 0/27, 50% 0/55, 75% 0/27, 100% 0/55
RPL7 ACC Checklists 0/160   |   KPA Milestones 25% 0/27, 50% 0/56, 75% 0/27, 100% 0/56
RPL6 ACC Checklists 0/160   |   KPA Milestones 25% 0/29, 50% 0/58, 75% 0/29, 100% 0/58
EXTERNAL ACC Checklists 0/50   |   KPA Milestones 25% 0/0, 50% 0/0, 75% 0/0, 100% 0/0