Past Due Inspections

Area Building Inspection Type Milestones Progress Start Finish Next Milestone Status
10GSEF1 RPL10 L2 – Infrastructure 1/2
50%
04/06/2026 04/08/2026 100% – 04/08/2026 Past Due
10GSEF1 RPL10 L3 – OSP 0/2
0%
04/13/2026 04/16/2026 50% – 04/15/2026 Past Due
10GSEF2 RPL10 L2 – Infrastructure 1/2
50%
04/06/2026 04/08/2026 100% – 04/08/2026 Past Due
10GSEF2 RPL10 L3 – OSP 0/2
0%
04/13/2026 04/16/2026 50% – 04/15/2026 Past Due
10GSMDF1 RPL10 L2 – Infrastructure 1/2
50%
04/13/2026 04/15/2026 100% – 04/15/2026 Past Due
10GSMDF2 RPL10 L2 – Infrastructure 1/2
50%
04/13/2026 04/15/2026 100% – 04/15/2026 Past Due
GSIDFN13 RPL10 L2 – Infrastructure 0/2
0%
03/23/2026 03/27/2026 50% – 03/25/2026 Past Due
GSIDFN23 RPL10 L2 – Infrastructure 0/2
0%
03/23/2026 03/27/2026 50% – 03/25/2026 Past Due
GSIDFN31 RPL10 L2 – Infrastructure 0/2
0%
04/13/2026 04/17/2026 50% – 04/15/2026 Past Due
GSIDFN41 RPL10 L2 – Infrastructure 0/2
0%
04/13/2026 04/17/2026 50% – 04/15/2026 Past Due
GSIDFNE1 RPL10 L2 – Infrastructure 0/2
0%
03/23/2026 03/27/2026 50% – 03/25/2026 Past Due
GSIDFNX11 EXTERNAL L2 – Infrastructure 0/2
0%
04/13/2026 04/17/2026 50% – 04/15/2026 Past Due
GSIDFNX12 EXTERNAL L2 – Infrastructure 0/2
0%
04/13/2026 04/17/2026 50% – 04/15/2026 Past Due
GSIDFNX13 EXTERNAL L2 – Infrastructure 0/2
0%
04/13/2026 04/17/2026 50% – 04/15/2026 Past Due

14 results