## Overview The entries from May 27, 2026, detail a QA team meeting and site walk focused on specifications and preparations for upcoming work. Key discussions included cable pathways, fire alarm placements, and ongoing RFIs. ## By Area / Equipment - **NCB RPL10** - Discussed specifications and upcoming FOK. - Completed site walk with Supers and DPR. - **GSCMDF1** - Started L2 FOK. - Noted cable system pathways and fire alarm issues. - **MDF2** - Identified AP location issue next to fire alarm. - Required extension of AP piping away from the alarm. - **CMDF** - RFI regarding rack direction pending response. - Faceplates for south wall needed in CMDF2. - Vertical ladder rack installation planned for CMDF1 after cement sets. ## Issues / Open Items - Fire alarm placement issues requiring adjustment to meet minimum distance (May 27). - RFI regarding rack direction at CMDF pending response (May 27). - Need to verify all rows are even and matching measurements before final bolt placement (May 27). - Box arrangement for outside WAP at EGsidf2 needs coordination (May 27). ## Progress / Completed - Completed Tiger Meeting discussing GC handovers and cable tray pathways (May 27). - Exterior cans hung; closeout with QA needed (May 27). - Site photos taken to complete GSCMDF FOK (May 27). ## People Mentioned - Caleb Bourghs - Supers - DPR - Chance
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets