Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
7 entries
Clear
7 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This summary covers the period from April 28, 2026, to June 10, 2026, focusing on the installation and inspection of various equipment and infrastructure in the RPL10 area. Key themes include ongoing issues with grounding and bonding, the need for adjustments to ladder racks, and preparations for splicing activities. ## By Area / Equipment - **RPL10.CMDF 1/2** - Pre-installation walkthrough completed; one issue documented (Issue #5174) (04-28). - Vertical ladder rack missing; racks missing grounding and bonding (06-01). - Awaiting one OC to complete rack bonding and grounding; ordered and in transit (06-10). - **RPL10 GSEF 1/2** - Field walk completed; temporary splices of two 192 fibers in IDFNX5 documented (04-30). - Missing overhead support for crossover; ladder rack on west wall missing grounding and bonding (06-01). - OSE labels need clarity on requirements; horizontal ladder rack needs adjustment (06-10). - **IDFNX5** - Temporary splices completed by Clear Core (04-30). - **GSEF2** - Extra vertical ladder rack under tier 2; overhead support missing for crossover runway (06-01). - OSE labels need clarity on requirements (06-10). - **GSMDF1/GSMDF2** - Missing devices and power cords; FIM not updated (06-10). ## Issues / Open Items - Issue #5174 documented regarding CMDF 1/2 (04-28). - Horizontal ladder runway in CMDFs needs to be moved for fiber routing (04-30). - RFI on swap rack direction for CMDF pending response (05-27). - Grounding and bonding issues across multiple racks (06-01). - Missing ground bars and unistrut caps (06-01). - Concrete slabs need sanding and labeling before splicing can start (06-10). - Networking constraints and missing devices for GSMDF1 and GSMDF2 (06-10). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed (04-28). - Field walk with FE team through GSEF 1/2, CMDF 1/2, and IDFNX5 completed (04-30). - QA team meeting held to discuss specifications and site walk preparations (05-27). ## People Mentioned - Timeon P. - Caleb Bourghs - SFE Paul - Mortenson - IES - ENS - IBOS
Wednesday, June 10, 2026
Timeon P. RPL10 · logged 06/10/2026 02:47 PM CT
GSEF1: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES) Dress all OSP cables to the respective OSE. (Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) GSEF2: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Dress all OSP cables to the respective OSE.(Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) CMDF1: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) CMDF2: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) GSMDF1: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS) GSMDF2: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Monday, June 01, 2026
Timeon P. GSEF2 · logged 06/01/2026 10:27 AM CT
Extra vertical ladder rack under tier 2 Overhead support missing for crossover runway. Missing caps on unistrut Tier 1 to tier 2 grounding and bonding missing
Timeon P. CMDF1/2 · logged 06/01/2026 10:20 AM CT
Vertical ladder rack missing. Racks missing grounding and bonding Overhead ladder rack missing bonding Missing ground bar Unistrut caps missing
Timeon P. GSEF1 · logged 06/01/2026 10:15 AM CT
EF one is missing the overhead support for the crossover. Ladder rack on the west wall missing the grounding and bonding. we're also missing the unit strut caps. Ladder rack support on the west wall. Vertical ladder rack on west wall under tier 2 not needed Missing ground bar. Tier 1 to 2 grounding and bonding missing.
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, April 30, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).