## Overview
The entries from May 21 to May 27, 2026, detail ongoing installation and inspection activities related to rack positioning and cable pathways. Key themes include adjustments to avoid interference with bolts and preparations for upcoming site walks and installations.
## By Area / Equipment
- **RPL10 GSEF 1/2, CMDF 1/2, EF**
- Confirmed rack positioning in EF1; racks shifted 4 inches to avoid hitting nearby column bolts.
- Operations began anchoring racks into place.
- **NCB RPL10**
- Discussed specifications and preparations for upcoming FOK.
- Initiated L2 FOK for GSCMDF1.
- Conducted a site walk with superintendents and DPR, focusing on cable tray pathways and fire alarm placements.
## Issues / Open Items
- RFI regarding rack direction swap for CMDF pending response (May 27).
- Need to verify all rows are even and matching measurements before placing last 2 bolts (May 27).
- Ensure all end caps are placed before starting cable pulls (May 27).
- Need to arrange box for outside WAP at EGsidf2 (May 27).
- Close out required with QA for hung exterior cans (May 27).
## Progress / Completed
- Completed Tiger Meeting discussing GC handovers and cable tray system pathways (May 27).
- Completed site walk and documented notes and photos for GSCMDF FOK (May 27).
- 25% completion noted when Row 5 is anchored (May 27).
## People Mentioned
- Timeon P.
- Caleb Bourghs
- Superintendents
- DPR
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, May 21, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, EF
· logged 05/21/2026 03:33 PM CT
Confirmed rack positioning in EF1. Operations began to anchor the racks into place after shifting the racks over 4 inches to avoid hitting the bolts on the nearby columns.
Conducted a field walk with the superintendents and FE's. Walked the GSEFs and reviewed the plan on supporting the crossovers with Unistrut.