Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.3 entries
Tags:
RPL10 4
CMDF1 3
CMDF2 3
GSEF1 2
GSEF2 2
CMDF 2
FOK 2
NCB 2
ENS 1
FIM 1
GSMDF1 1
GSMDF2 1
IBOS 1
IES 1
OC 1
OSE 1
OSP 1
ALARM 1
ALL 1
ANCHORED 1
AND 1
ANSWER 1
AP 1
ARE 1
## Overview
This briefing covers the daily logs from May 7, May 27, and June 10, 2026, focusing on cable management, installation specifications, and ongoing issues related to cable pathways and labeling requirements.
## By Area / Equipment
- **RPL10**
- Verified spacing between ladder racks and corrected issues with the FE team (May 7).
- Discussed cable tray system pathways and bridges for cable pulling during site walks (May 27).
- Noted need for a 24-inch triangle bracket for the horizontal ladder rack on the West wall (June 10).
- **GSEF1 & GSEF2**
- OSE labels need clarity on path requirements; some cans will have multiple paths (June 10).
- All OSP cables must be dressed to the respective OSE (June 10).
- Concrete slabs require sanding and labeling before splicing can commence (June 10).
- **CMDF1**
- Cleared issue #6394; awaiting one OC to complete rack bonding and grounding (May 27, June 10).
- Concrete slabs need sanding and labeling before splicing (June 10).
- **CMDF2**
- Faceplates for the south wall are pending (May 27).
- Awaiting one OC for rack bonding and grounding; concrete slabs need sanding and labeling (June 10).
- **GSMDF1 & GSMDF2**
- Both areas require 2x spill outs and are missing devices and power cords (June 10).
- FIM is not updated; incomplete portmap for fiber or copper (June 10).
## Issues / Open Items
- RFI regarding rack direction swap in CMDF is pending response (May 27).
- Need to verify all rows are even and matching measurements before final bolts are placed (May 27).
- Clarity needed on OSE label requirements for multiple paths (June 10).
- Concrete slabs in multiple areas need sanding and labeling before splicing can start (June 10).
- Missing devices and power cords in GSMDF1 and GSMDF2 (June 10).
- FIM not updated; incomplete portmap for fiber or copper (June 10).
## Progress / Completed
- Cleared issue #6394 in CMDF1 (May 7).
- Completed a site walk with Supers and DPR, taking notes and site photos for GSCMDF FOK (May 27).
- Ordered one OC for rack bonding and grounding in CMDF1 and CMDF2 (June 10).
## People Mentioned
- Caleb Bourghs
- Timeon P.
- FE team
- Mortenson
- IES
- IBOS
- ENS
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, May 07, 2026
Caleb Bourghs
NCB, RPL10
· logged 05/07/2026 04:54 PM CT
Daily align with QA Team discussing upcoming walks and FOKs. Went over specs per FOK and upcoming walks in GSEF1, GSEF2, CMDF 1, CMDF 2. Met with our FE team at RPL10 and completed a walk through for each room. Verified spacing in between ladder racks support and worked with FE team to have it corrected. Verified splicing, cable management, and routing. Verified cleared issue #6394 in CMDF1. Created checklist with FE team to prepare for the 100% walk.