Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
4 entries
Clear
4 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the daily logs from May 27 to June 1, 2026, highlighting ongoing issues with equipment installation and grounding requirements across multiple areas. The main focus is on the completion of site walks and the identification of missing components necessary for compliance. ## By Area / Equipment - **NCB RPL10** - Completed site walk with Supers and DPR. - Discussed cable tray system pathways and fire alarm locations. - Noted need to shift APs to meet minimum distance from fire alarms. - RFI submitted regarding rack direction; awaiting response. - Ensured end caps are placed before cable pulling. - **GSEF1** - Missing overhead support for crossover. - Ladder rack on west wall lacks grounding and bonding. - Missing unit strut caps and ground bar. - **CMDF1/2** - Vertical ladder rack missing. - Racks lack grounding and bonding. - Overhead ladder rack missing bonding and ground bar. - **GSEF2** - Extra vertical ladder rack under tier 2 noted. - Overhead support missing for crossover runway. - Missing caps on unistrut and grounding/bonding between tiers. ## Issues / Open Items - RFI regarding rack direction at CMDF not answered (2026-05-27). - Missing overhead support and grounding components in GSEF1 (2026-06-01). - Vertical ladder racks and grounding/bonding issues noted in CMDF1/2 and GSEF2 (2026-06-01). ## Progress / Completed - Completed site walk and discussions regarding FOK specifics and cable pathways (2026-05-27). - Documented notes and site photos for GSCMDF FOK (2026-05-27). ## People Mentioned - Caleb Bourghs - Timeon P.
Monday, June 01, 2026
Timeon P. GSEF2 · logged 06/01/2026 10:27 AM CT
Extra vertical ladder rack under tier 2 Overhead support missing for crossover runway. Missing caps on unistrut Tier 1 to tier 2 grounding and bonding missing
Timeon P. CMDF1/2 · logged 06/01/2026 10:20 AM CT
Vertical ladder rack missing. Racks missing grounding and bonding Overhead ladder rack missing bonding Missing ground bar Unistrut caps missing
Timeon P. GSEF1 · logged 06/01/2026 10:15 AM CT
EF one is missing the overhead support for the crossover. Ladder rack on the west wall missing the grounding and bonding. we're also missing the unit strut caps. Ladder rack support on the west wall. Vertical ladder rack on west wall under tier 2 not needed Missing ground bar. Tier 1 to 2 grounding and bonding missing.
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets