Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.5 entries
## Overview
This briefing covers the period from April 28 to June 1, 2026, focusing on the installation and inspection activities related to CMDF 1/2 and associated areas. Key themes include ongoing inspections, identification of issues, and coordination with teams for necessary adjustments.
## By Area / Equipment
- **CMDF 1/2**
- Pre-installation walkthrough completed on April 28; one issue documented (Issue #5174).
- Horizontal ladder runway needs to be moved 5" from walls for fiber routing (April 30).
- Missing vertical ladder rack, grounding and bonding for racks, and overhead ladder rack bonding noted (June 1).
- Ground bar required to complete GSEF 1/2 (May 11).
- **GSEF 1/2**
- Field walk completed with FE team; temporary splices of two 192 fibers in IDFNX5 documented (April 30).
- Rack positioning confirmed; racks shifted 4 inches to avoid column bolts (May 21).
- **IDFNX5**
- Temporary splices completed by Clear Core (April 30).
## Issues / Open Items
- Issue #5174 documented during pre-installation walkthrough (April 28).
- Horizontal ladder runway adjustment required for CMDF 1/2 (April 30).
- Ground bar needed for GSEF 1/2 (May 11).
- Missing vertical ladder rack, grounding and bonding for racks, and overhead ladder rack bonding (June 1).
- Unistrut caps missing (June 1).
## Progress / Completed
- Pre-installation walkthrough of CMDF 1/2 completed (April 28).
- Field walk with FE team through GSEF 1/2, CMDF 1/2, and IDFNX5 completed (April 30).
- Rack positioning in EF1 confirmed; operations began to anchor racks (May 21).
## People Mentioned
- Timeon P.
- SFE Paul
- Samuel
Monday, June 01, 2026
Timeon P.
CMDF1/2
· logged 06/01/2026 10:20 AM CT
Vertical ladder rack missing.
Racks missing grounding and bonding
Overhead ladder rack missing bonding
Missing ground bar
Unistrut caps missing
Thursday, May 21, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, EF
· logged 05/21/2026 03:33 PM CT
Confirmed rack positioning in EF1. Operations began to anchor the racks into place after shifting the racks over 4 inches to avoid hitting the bolts on the nearby columns.
Conducted a field walk with the superintendents and FE's. Walked the GSEFs and reviewed the plan on supporting the crossovers with Unistrut.
Monday, May 11, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2
· logged 05/12/2026 07:12 AM CT
Conducted a field walk of GSEF 1/2 and CMDF 1/2. Ground bar is needed to complete GSEF 1/2. Samuel wants a FOK of the GSEF done by lunch Wednesday.
Thursday, April 30, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, IDFNX5
· logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5.
Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core.
SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.
Tuesday, April 28, 2026
Timeon P.
RPL10.CMDF 1/2
· logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).