Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
6 entries
Clear
6 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This summary covers the daily logs from April 30 to June 10, 2026, focusing on the CMDF2 area. Key themes include ongoing inspections, issue identification, and corrective actions related to equipment placement, labeling, and splicing specifications. ## By Area / Equipment - **CMDF2** - Racks placed according to prints; measurements verified (04-30). - Issues identified: vertical ladder rack locations blocked by EPMS/BAS conduit (04-30). - Bonding for vertical ladder racks to tier 1 completed; continuity for overhead ladder rack noted (06-08). - Awaiting one OC to complete rack bonding and grounding; ordered and in transit (06-10). - Concrete slabs need sanding and labeling before splicing can start (06-10). ## Issues / Open Items - Issue #6395: MOFE Door (04-30). - Issue #6393: Labeling Conflict (04-30). - Issue #6394: Concrete hole on East Wall in CMDF1 (04-30). - Issue #6391: Ladder rack locations blocked by conduit (04-30). - RFI regarding rack direction swap in CMDF2; no answer yet (05-27). - Clarity needed on OSE label requirements for multiple paths (06-10). ## Progress / Completed - Racks in CMDF2 verified and measurements met standards (04-30). - Splicing in IDFNX5 verified; issues reported to Super Intendant (04-30). - Checklist created with FE team for 100% walk preparation (05-07). - Bonding for vertical ladder racks completed (06-08). ## People Mentioned - Timeon P. - Caleb Bourghs - Super Chance - Richard
Wednesday, June 10, 2026
Timeon P. RPL10 · logged 06/10/2026 02:47 PM CT
GSEF1: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES) Dress all OSP cables to the respective OSE. (Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) GSEF2: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Dress all OSP cables to the respective OSE.(Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) CMDF1: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) CMDF2: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) GSMDF1: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS) GSMDF2: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Monday, June 08, 2026
Timeon P. CMDF2 · logged 06/08/2026 09:55 AM CT
Label racks Finished bonding for vertical ladder racks to tier 1 Bonding for racks and finish continuity for overhead ladder rack, bonding does not touch all runway
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, May 07, 2026
Caleb Bourghs NCB, RPL10 · logged 05/07/2026 04:54 PM CT
Daily align with QA Team discussing upcoming walks and FOKs. Went over specs per FOK and upcoming walks in GSEF1, GSEF2, CMDF 1, CMDF 2. Met with our FE team at RPL10 and completed a walk through for each room. Verified spacing in between ladder racks support and worked with FE team to have it corrected. Verified splicing, cable management, and routing. Verified cleared issue #6394 in CMDF1. Created checklist with FE team to prepare for the 100% walk.
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.