## Overview
The entries from May 27, 2026, detail a QA team meeting and subsequent site walk, focusing on specifications and cable pathway preparations. Key discussions included fire alarm placements and the need for adjustments to meet distance specifications.
## By Area / Equipment
- **NCB RPL10**
- Discussed specifications and upcoming FOK.
- Completed site walk with Supers and DPR.
- **GSCMDF1**
- Started L2 FOK.
- Noted cable pathway for north wall location.
- Fire alarm placement issues identified; need to shift AP to meet minimum distance EMI/spec.
- **MDF2**
- Similar AP location issue next to fire alarm; extending AP piping away from alarm.
- **CMDF**
- RFI regarding swap rack direction pending response; potential issue with proximity to electrical box.
- Faceplates for south wall noted.
- Vertical ladder rack for south wall planned after cement sets.
- **EGsidf2**
- FE needs to arrange box for outside WAP.
- **Exterior Cans**
- Hung; need closeout with QA and FOK for external.
## Issues / Open Items
- Fire alarm AP location adjustments needed to meet distance specifications (2026-05-27).
- RFI on swap rack direction pending response (2026-05-27).
- Verification required for even measurements of rows before final bolts are placed (2026-05-27).
## Progress / Completed
- Completed Tiger Meeting discussing GC handovers and cable tray system pathways (2026-05-27).
- Site photos taken to complete GSCMDF FOK (2026-05-27).
## People Mentioned
- Caleb Bourghs
- Supers
- DPR
- Chance
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets