Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
9 entries
Clear
9 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the period from April 30 to June 10, 2026, focusing on the inspections and progress related to the EF1 area and associated equipment. Key themes include ongoing adjustments to rack positioning, the need for additional supports and grounding, and preparations for upcoming walks and final inspections. ## By Area / Equipment - **GSEF 1/2** - Temporary splices of two 192 fibers completed in IDFNX5 (04/30). - Ground bar needed to complete GSEF 1/2 (05/11). - OSE labels colored per path; clarity needed on label requirements (06/10). - Dress all OSP cables to respective OSE (06/10). - Concrete slabs need sanding and labeling before splicing can start (06/10). - **CMDF 1/2** - Ladder rack supports spaced incorrectly; issue being corrected (05/07). - Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (06/10). - Concrete slabs need sanding and labeling before splicing can start (06/10). - **EF1** - Rack positioning confirmed; racks shifted 4 inches to avoid column bolts (05/21). - Missing overhead support for crossover and grounding/bonding on west wall (06/01). - Missing unit strut caps and ground bar (06/01). - **GSMDF 1/2** - 2x spill outs needed; networking constraints present (06/10). - Missing 10 devices for corpnet and 24 power cords (IBOS) (06/10). - Waiting on 110 fact net devices and optics (IBOS) (06/10). - FIM not updated; incomplete portmap for fiber or copper (ENS) (06/10). ## Issues / Open Items - Horizontal ladder runway in CMDFs needs to move 5" from walls (04/30). - RFI's in GSEF1/2 need resolution before closing the room (05/07). - Grounding and bonding missing in EF1 (06/01). - Clarity needed on OSE label requirements (06/10). - Concrete slabs need sanding and labeling before splicing can start (06/10). ## Progress / Completed - Completed field walk in GSEF 1/2 and CMDF 1/2 (04/30). - Verified splicing, cable management, and routing; cleared issue #6394 in CMDF1 (05/07). - Created checklist with FE team to prepare for the 100% walk (05/07). - Started GSEF1 FOK with Timeon (05/11). - Completed L1s for multiple equipment tags (05/12). ## People Mentioned - Timeon P. - Caleb Bourghs - Samuel - Joe (PM) - DPR QA team - Clear Core (fiber splicing) - Mortenson (OSP cable dressing) - IES (labeling and concrete work) - ENS (FIM updates)
Wednesday, June 10, 2026
Timeon P. RPL10 · logged 06/10/2026 02:47 PM CT
GSEF1: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES) Dress all OSP cables to the respective OSE. (Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) GSEF2: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Dress all OSP cables to the respective OSE.(Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) CMDF1: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) CMDF2: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) GSMDF1: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS) GSMDF2: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Monday, June 01, 2026
Timeon P. GSEF1 · logged 06/01/2026 10:15 AM CT
EF one is missing the overhead support for the crossover. Ladder rack on the west wall missing the grounding and bonding. we're also missing the unit strut caps. Ladder rack support on the west wall. Vertical ladder rack on west wall under tier 2 not needed Missing ground bar. Tier 1 to 2 grounding and bonding missing.
Thursday, May 21, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, EF · logged 05/21/2026 03:33 PM CT
Confirmed rack positioning in EF1. Operations began to anchor the racks into place after shifting the racks over 4 inches to avoid hitting the bolts on the nearby columns. Conducted a field walk with the superintendents and FE's. Walked the GSEFs and reviewed the plan on supporting the crossovers with Unistrut.
Tuesday, May 12, 2026
Caleb Bourghs NCB RPL10 · logged 05/13/2026 07:19 AM CT
Daily QA meeting to discuss walk, upcoming FOK, and standards. Met with FE team for GSEF1 & 2 walk to verify checklist. Took remaining photos and made updates to FOK. Completed L1s for: CB-FE-HT-384MCM-034 CB-FE-HT-096MCM-048 CB-FE-HT-288MCM-086 CB-FE-HT-096MCM-101 CB-FE-HT-096MCM-059 CB-FE-HT-096MCM-052 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-025 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-346 CB-FE-HT-192MCM-222 CB-FE-HT-096MCM-095 CB-FE-HT-096MCM-091 CB-FE-HT-096MCM-071 CB-FE-HT-096MCM-089 CB-FE-HT-096MCM-102 CB-FE-HT-096MCM-078 CB-FE-HT-096MCM-121 CB-FE-HT-096MCM-127 CB-FE-ET-384MCFMCM-103 CB-FE-HT-096MCM-082 CB-FE-HT-096MCM-051 CB-FE-HT-096MCM-076 CB-FE-HT-192MCM-064 CB-FE-ET-384MCFMCM-119 CB-FE-ET-384MCFMCM-285 CB-FE-ET-384MCFMCM-194 CB-FE-HT-096MCM-188 CB-FE-HT-192MCM-067 CB-FE-HT-096MCM-408 CB-FE-HT-096MCM-315 CB-FE-ET-384MCFMCM-305 CB-FE-ET-384MCFMCM-257 CB-FE-HT-096MCM-400 CB-FE-ET-384MCFMCM-200 CB-FE-ET-384MCFMCM-298 CB-FE-ET-384MCFMCM-151 CB-FE-ET-384MCFMCM-179
Monday, May 11, 2026
Caleb Bourghs NCB RPL10 · logged 05/12/2026 10:45 AM CT
Daily QA Team meeting to discuss FOK, L1, Warehouse storing, and IES team alignments for scheduling. Met with PM, Joe, and QA Team to discuss FOK requirements. Verified steps for FOK completion across Teams. Created L1s, started GSEF1 FOK with Timeon, and walked RPL10. Took photos for FOK and verified progress according to specs. Met with DPR QA team in the field to verify progress. Notated changes and upcoming phases. Had evening meeting with QA Team going over Warehouse Audit and future expectations.
Timeon P. RPL10 GSEF 1/2, CMDF 1/2 · logged 05/12/2026 07:12 AM CT
Conducted a field walk of GSEF 1/2 and CMDF 1/2. Ground bar is needed to complete GSEF 1/2. Samuel wants a FOK of the GSEF done by lunch Wednesday.
Thursday, May 07, 2026
Caleb Bourghs NCB, RPL10 · logged 05/07/2026 04:54 PM CT
Daily align with QA Team discussing upcoming walks and FOKs. Went over specs per FOK and upcoming walks in GSEF1, GSEF2, CMDF 1, CMDF 2. Met with our FE team at RPL10 and completed a walk through for each room. Verified spacing in between ladder racks support and worked with FE team to have it corrected. Verified splicing, cable management, and routing. Verified cleared issue #6394 in CMDF1. Created checklist with FE team to prepare for the 100% walk.
Timeon P. RPL10.CMDF1, GSEF1/2 · logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue. Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.
Thursday, April 30, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.