## Overview This briefing covers the period from April 30, 2026, to June 10, 2026. The main themes include ongoing inspections and measurements for equipment placement, issues with labeling and cable management, and preparations for upcoming work orders (FOK). ## By Area / Equipment - **GSIDFNX05** - Racks placed according to prints; measurements taken for anchoring. - Issues reported: - Issue #6395: MOFE Door - Issue #6393: Labeling Conflict - Fiber clippings left on the floor; dressing in fiber enclosures not up to standard. - **RPL** - Verified new material at Warehouse and Mortenson Tent; arranged crew for material pickup. - **NCB RPL10** - Discussed specifications and upcoming FOK during QA Team meeting. - Completed site walk with Supers and DPR; noted cable pathways and fire alarm proximity issues. - RFI submitted regarding rack direction swap; awaiting response. - **GSEF1 & GSEF2** - OSE labels need clarity on path requirements. - OSP cables need dressing to respective OSE. - Concrete slabs require sanding and labeling before splicing. - **CMDF1 & CMDF2** - Awaiting OC for rack bonding and grounding; in transit. - Concrete slabs need sanding and labeling. - **GSMDF1 & GSMDF2** - 2x spill outs needed; networking constraints identified. - Missing devices and power cords; FIM not updated, incomplete portmap for fiber or copper. ## Issues / Open Items - Fiber dressing not up to standard; Clear Core called back (2026-04-30). - RFI regarding rack direction swap; no answer yet (2026-05-27). - Awaiting OC for rack bonding and grounding for CMDF1 and CMDF2 (2026-06-10). - FIM not updated; incomplete portmap for fiber or copper for GSMDF1 and GSMDF2 (2026-06-10). ## Progress / Completed - Racks at GSIDFNX05 landed according to prints (2026-04-30). - New material verified and picked up at Mortenson Tent (2026-05-05). - Completed site walk and discussions for GSCMDF1 FOK (2026-05-27). ## People Mentioned - Timeon P. - Caleb Bourghs - Super Chance - Richard - Mortenson - IES - IBOS
Wednesday, June 10, 2026
Timeon P. RPL10 · logged 06/10/2026 02:47 PM CT
GSEF1: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES) Dress all OSP cables to the respective OSE. (Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) GSEF2: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Dress all OSP cables to the respective OSE.(Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) CMDF1: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) CMDF2: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) GSMDF1: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS) GSMDF2: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets
Tuesday, May 05, 2026
Caleb Bourghs RPL · logged 05/06/2026 07:07 AM CT
Verified new material at Warehouse. Completed L1s and verified through OOR. Verified material at Mortenson Tent, arranged our crew to pick it up to bring to Tent 1.
Thursday, April 30, 2026
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.