Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
Tags:
CMDF1 1
CMDF2 1
ENS 1
FIM 1
GSEF1 1
GSEF2 1
GSMDF1 1
GSMDF2 1
IBOS 1
IES 1
OC 1
OSE 1
OSP 1
RPL10 1
## Overview
This log covers the activities and findings from June 10, 2026, focusing on labeling requirements, equipment installation, and outstanding material needs across various areas. Key themes include the need for clarity on labeling, completion of rack bonding, and updates to the FIM.
## By Area / Equipment
- **GSEF1:**
- OSE labels colored per path; clarification needed on label requirements (IES).
- Horizontal ladder rack on the West wall requires a 24-inch triangle bracket and needs to move to 8" from the wall (IES).
- Dress all OSP cables to respective OSE (Mortenson/IES).
- Concrete slabs need sanding and labeling with placards before splicing can start (Mortenson).
- Possibly paint the slab (Mortenson).
- **GSEF2:**
- OSE labels colored per path; clarification needed on label requirements (IES).
- Dress all OSP cables to respective OSE (Mortenson/IES).
- Concrete slabs need sanding and labeling with placards before splicing can start (Mortenson).
- Possibly paint the slab (Mortenson).
- **CMDF1:**
- Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (IES).
- Concrete slabs need sanding and labeling before splicing can start; possibly paint the slab (Mortenson).
- **CMDF2:**
- Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (IES).
- Concrete slabs need sanding and labeling before splicing can start; possibly paint the slab (Mortenson).
- **GSMDF1:**
- 2x spill outs needed.
- Networking constraints present.
- Missing 10 devices for corpnet and 24 power cords (IBOS).
- Waiting on 110 fact net devices and optics (IBOS).
- FIM is not updated; no complete portmap for fiber or copper (ENS).
- **GSMDF2:**
- 2x spill outs needed.
- Networking constraints present.
- Missing 10 devices for corpnet and 24 power cords (IBOS).
- Waiting on 110 fact net devices and optics (IBOS).
- FIM is not updated; no complete portmap for fiber or copper (ENS).
## Issues / Open Items
- Clarification needed on OSE label requirements (June 10).
- Horizontal ladder rack adjustment required (June 10).
- Completion of rack bonding and grounding pending OC delivery (June 10).
- Concrete slabs need sanding and labeling before splicing can start (June 10).
- FIM not updated; incomplete portmap for fiber or copper (June 10).
## Progress / Completed
- None reported.
## People Mentioned
- Timeon P.
- Mortenson
- IES
- IBOS
- ENS
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)