Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
5 entries
Clear
5 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the period from April 30 to May 21, 2026, focusing on the ongoing inspections and adjustments in the GSEF 1/2 and CMDF 1/2 areas. Key themes include the need for modifications to ladder rack supports, completion of temporary splices, and preparations for final inspections. ## By Area / Equipment - **GSEF 1/2** - Temporary splices of two 192 fibers completed by Clear Core (04/30). - Ground bar needed to complete GSEF 1/2 (05/11). - Confirmed rack positioning; operations began to anchor racks after adjustments (05/21). - **CMDF 1/2** - Horizontal ladder runway needs to move 5" from walls for fiber routing (04/30). - Ladder rack supports spaced incorrectly; field team notified for correction (05/07). - Reviewed plan for supporting crossovers with Unistrut during field walk (05/21). - **IDFNX5** - Temporary 2 post rack photos taken for splices (04/30). ## Issues / Open Items - RFI's pending resolution before closing GSEF 1/2 (05/07). - Need for a ground bar in GSEF 1/2 (05/11). - Ladder rack support spacing issue to be corrected (05/07). ## Progress / Completed - Field walk completed with FE team in GSEF 1/2, CMDF 1/2, and IDFNX5 (04/30). - L1s completed for various equipment tags (05/12). - Rack positioning confirmed in EF1; anchoring operations initiated (05/21). ## People Mentioned - Timeon P. - Caleb Bourghs - SFE Paul - FE team
Thursday, May 21, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, EF · logged 05/21/2026 03:33 PM CT
Confirmed rack positioning in EF1. Operations began to anchor the racks into place after shifting the racks over 4 inches to avoid hitting the bolts on the nearby columns. Conducted a field walk with the superintendents and FE's. Walked the GSEFs and reviewed the plan on supporting the crossovers with Unistrut.
Tuesday, May 12, 2026
Caleb Bourghs NCB RPL10 · logged 05/13/2026 07:19 AM CT
Daily QA meeting to discuss walk, upcoming FOK, and standards. Met with FE team for GSEF1 & 2 walk to verify checklist. Took remaining photos and made updates to FOK. Completed L1s for: CB-FE-HT-384MCM-034 CB-FE-HT-096MCM-048 CB-FE-HT-288MCM-086 CB-FE-HT-096MCM-101 CB-FE-HT-096MCM-059 CB-FE-HT-096MCM-052 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-025 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-346 CB-FE-HT-192MCM-222 CB-FE-HT-096MCM-095 CB-FE-HT-096MCM-091 CB-FE-HT-096MCM-071 CB-FE-HT-096MCM-089 CB-FE-HT-096MCM-102 CB-FE-HT-096MCM-078 CB-FE-HT-096MCM-121 CB-FE-HT-096MCM-127 CB-FE-ET-384MCFMCM-103 CB-FE-HT-096MCM-082 CB-FE-HT-096MCM-051 CB-FE-HT-096MCM-076 CB-FE-HT-192MCM-064 CB-FE-ET-384MCFMCM-119 CB-FE-ET-384MCFMCM-285 CB-FE-ET-384MCFMCM-194 CB-FE-HT-096MCM-188 CB-FE-HT-192MCM-067 CB-FE-HT-096MCM-408 CB-FE-HT-096MCM-315 CB-FE-ET-384MCFMCM-305 CB-FE-ET-384MCFMCM-257 CB-FE-HT-096MCM-400 CB-FE-ET-384MCFMCM-200 CB-FE-ET-384MCFMCM-298 CB-FE-ET-384MCFMCM-151 CB-FE-ET-384MCFMCM-179
Monday, May 11, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2 · logged 05/12/2026 07:12 AM CT
Conducted a field walk of GSEF 1/2 and CMDF 1/2. Ground bar is needed to complete GSEF 1/2. Samuel wants a FOK of the GSEF done by lunch Wednesday.
Thursday, May 07, 2026
Timeon P. RPL10.CMDF1, GSEF1/2 · logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue. Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.
Thursday, April 30, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.