This log entry from April 30, 2026, details inspections and measurements taken at GSIDFNX05, focusing on rack placements and addressing issues identified in the field.
## By Area / Equipment
- **CMDF2**:
- Measured rack placements to ensure correct locations before anchoring.
- Racks were landed according to prints.
- **GSIDFNX05**:
- Reviewed splice cassette alignment with labels.
- Noted fiber clippings left on the floor by Clear Core.
- Fiber dressing in the 432 can and 1u unican fiber enclosure was below standard.
## Issues / Open Items
- Issue #6395: GSIDFNX05 MOFE Door (reported by Super Chance on 2026-04-30).
- Issue #6393: GSIDFNX05 Labeling Conflict (reported by Super Chance on 2026-04-30).
- Fiber dressing corrections needed for the 432 can and 1u unican fiber enclosure (noted on 2026-04-30).
## Progress / Completed
- Racks at GSIDFNX05 were successfully landed according to prints (completed on 2026-04-30).
## People Mentioned
- Timeon P.
- Super Chance
- Richard
Thursday, April 30, 2026
Timeon P.
GSIDFNX05
· logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints.
Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below:
Issue #6395 GSIDFNX05 MOFE Door
Issue #6393 GSIDFNX05 Labeling Conflict
Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels
Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.