Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
Tags:
CMDF1 1
CMDF2 1
ENS 1
FIM 1
GSEF1 1
GSEF2 1
GSMDF1 1
GSMDF2 1
IBOS 1
IES 1
OC 1
OSE 1
OSP 1
RPL10 1
## Overview
This log covers the activities and observations made on June 10, 2026, focusing on the GSEF, CMDF, and GSMDF areas. Key themes include labeling requirements, concrete slab preparations, and missing equipment for networking.
## By Area / Equipment
- **GSEF1 & GSEF2:**
- OSE labels colored per path; clarity needed on labeling for multiple paths (IES).
- Dress all OSP cables to respective OSE (Mortenson/IES).
- Concrete slabs need sanding and labeling with placards before splicing; possible painting of slabs (Mortenson).
- Horizontal ladder rack on the West wall requires a 24-inch triangle bracket and repositioning to 8" from the wall (IES).
- **CMDF1 & CMDF2:**
- Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (IES).
- Concrete slabs need sanding and labeling before splicing; possible painting of slabs (Mortenson).
- **GSMDF1 & GSMDF2:**
- 2x spill outs needed.
- Networking constraints noted.
- Missing 10 devices for corpnet and 24 power cords (IBOS).
- Waiting on 110 fact net devices and optics (IBOS).
- FIM is not updated; incomplete portmap for fiber or copper (ENS).
## Issues / Open Items
- Clarification needed on OSE label requirements for multiple paths (June 10).
- Concrete slabs need sanding and labeling before splicing can start (June 10).
- Missing devices and power cords for networking (June 10).
- FIM not updated; incomplete portmap for fiber or copper (June 10).
## Progress / Completed
- Ordered 1 OC for rack bonding and grounding; currently in transit (June 10).
## People Mentioned
- Timeon P.
- Mortenson
- IES
- ENS
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)