Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
6 entries
Clear
6 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the daily logs from May 7 to May 27, 2026, focusing on the QA activities and inspections at NCB, specifically RPL10. Key themes include ongoing FOK preparations, alignment meetings with various teams, and addressing clearance issues related to equipment installations. ## By Area / Equipment - **RPL10** - Conducted multiple walks with the FE team to verify spacing, cable management, and routing. - Completed L1s for various equipment tags, including CB-FE-HT-384MCM-034 and CB-FE-ET-384MCFMCM-305. - Noted clearance issues with GSCMDF VCMs and confirmed ongoing efforts to resolve them. - Initiated L2 FOK for GSCMDF1 and discussed cable pathways and fire alarm placements during site walks. - **CMDF1 & CMDF2** - Cleared issue #6394 in CMDF1. - Addressed vertical ladder rack placements in CMDF1 and faceplate installations in CMDF2. ## Issues / Open Items - Clearance issue with GSCMDF VCMs being too close to the wall (May 18). - RFI regarding rack direction swap in CMDF is pending response (May 27). - Need to verify all rows are even and matching measurements before final bolt placements (May 27). - External FOK for exterior cans needs to be sent to Chance (May 27). ## Progress / Completed - Completed a walk-through and checklist preparation for 100% walk with the FE team (May 7). - Finalized L1s for numerous equipment tags (May 12). - Updated QA tracker to match L1 forms (May 18). - Completed site walk and discussions with various teams regarding handoffs and cable pathways (May 27). ## People Mentioned - Caleb Bourghs - Joe (PM) - Meta - DPR QA Team - FE Team - GCs (General Contractors)
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets
Monday, May 18, 2026
Caleb Bourghs NCB RPL10 · logged 05/18/2026 04:01 PM CT
Completed walk and measurements with QA Team for RPL10 EF2. Received notice from DPR about GSCMDF VCMs are too close to the wall to open rack doors for full clearance. Verified our teams are working on it. Returned after lunch to verify clearance, there is enough room for doors to open comfortably. Verified they are still trying to make more room for opening VCM doors. Did RPL10 EF2 site walk with GC, PM, and Supers. Verified our team is bringing all material through RPL10 Gate 2 (Front right gate if your facing rpl10 from trailer city). Completed L1s and edited older L1s adding name and quantity. Updated qa tracker to match L1 forms.
Wednesday, May 13, 2026
Caleb Bourghs NCB RPL10 · logged 05/14/2026 07:13 AM CT
Daily QA meeting to discuss walk, upcoming FOK, and standards. Had meeting with Meta, DPR, and other GCs to discuss upcoming walks, alignment, and new procedures for hand offs. Walked field with Meta to update issues. Helped Timeon complete FOK with field photos. Completed L1s to Qa tracker for accurate tracking.
Tuesday, May 12, 2026
Caleb Bourghs NCB RPL10 · logged 05/13/2026 07:19 AM CT
Daily QA meeting to discuss walk, upcoming FOK, and standards. Met with FE team for GSEF1 & 2 walk to verify checklist. Took remaining photos and made updates to FOK. Completed L1s for: CB-FE-HT-384MCM-034 CB-FE-HT-096MCM-048 CB-FE-HT-288MCM-086 CB-FE-HT-096MCM-101 CB-FE-HT-096MCM-059 CB-FE-HT-096MCM-052 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-025 CB-FE-HT-096MCM-070 CB-FE-HT-096MCM-346 CB-FE-HT-192MCM-222 CB-FE-HT-096MCM-095 CB-FE-HT-096MCM-091 CB-FE-HT-096MCM-071 CB-FE-HT-096MCM-089 CB-FE-HT-096MCM-102 CB-FE-HT-096MCM-078 CB-FE-HT-096MCM-121 CB-FE-HT-096MCM-127 CB-FE-ET-384MCFMCM-103 CB-FE-HT-096MCM-082 CB-FE-HT-096MCM-051 CB-FE-HT-096MCM-076 CB-FE-HT-192MCM-064 CB-FE-ET-384MCFMCM-119 CB-FE-ET-384MCFMCM-285 CB-FE-ET-384MCFMCM-194 CB-FE-HT-096MCM-188 CB-FE-HT-192MCM-067 CB-FE-HT-096MCM-408 CB-FE-HT-096MCM-315 CB-FE-ET-384MCFMCM-305 CB-FE-ET-384MCFMCM-257 CB-FE-HT-096MCM-400 CB-FE-ET-384MCFMCM-200 CB-FE-ET-384MCFMCM-298 CB-FE-ET-384MCFMCM-151 CB-FE-ET-384MCFMCM-179
Monday, May 11, 2026
Caleb Bourghs NCB RPL10 · logged 05/12/2026 10:45 AM CT
Daily QA Team meeting to discuss FOK, L1, Warehouse storing, and IES team alignments for scheduling. Met with PM, Joe, and QA Team to discuss FOK requirements. Verified steps for FOK completion across Teams. Created L1s, started GSEF1 FOK with Timeon, and walked RPL10. Took photos for FOK and verified progress according to specs. Met with DPR QA team in the field to verify progress. Notated changes and upcoming phases. Had evening meeting with QA Team going over Warehouse Audit and future expectations.
Thursday, May 07, 2026
Caleb Bourghs NCB, RPL10 · logged 05/07/2026 04:54 PM CT
Daily align with QA Team discussing upcoming walks and FOKs. Went over specs per FOK and upcoming walks in GSEF1, GSEF2, CMDF 1, CMDF 2. Met with our FE team at RPL10 and completed a walk through for each room. Verified spacing in between ladder racks support and worked with FE team to have it corrected. Verified splicing, cable management, and routing. Verified cleared issue #6394 in CMDF1. Created checklist with FE team to prepare for the 100% walk.