## Overview This summary covers the daily logs from April 28 to June 10, 2026, focusing on the ongoing inspections and issues related to OC (Optical Cable) installations across various areas. Key themes include pre-installation assessments, issue identification, and coordination among teams to ensure compliance with specifications. ## By Area / Equipment - **RPL10.CMDF 1/2** - Pre-installation walkthrough completed; one issue documented (Issue #5174) (2026-04-28). - Ground bar needed to complete GSEF 1/2 (2026-05-11). - Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (2026-06-10). - **GSIDFNX05** - Issues identified: MOFE Door (Issue #6395), Labeling Conflict (Issue #6393) (2026-04-30). - Fiber dressing in 432 can and 1u unican fiber enclosure not up to standard; Clear Core called back for corrections (2026-04-30). - **CMDF1** - Concrete hole documented (Issue #6394); location for VCM noted (2026-04-30). - Vertical ladder rack locations blocked by EPMS/BAS conduit (Issue #6391) (2026-04-30). - Concrete slabs need sanding and labeling before splicing can start (2026-06-10). - **CMDF2** - Racks placed correctly according to prints (2026-04-30). - Issues with VCMs being too close to the wall for door clearance; ongoing adjustments (2026-05-18). - Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (2026-06-10). - **GSMDF1/GSMDF2** - Both areas require 2x spill outs and have networking constraints. - Missing devices and power cords noted; FIM not updated (2026-06-10). ## Issues / Open Items - Issue #5174 documented regarding CMDF 1/2 (2026-04-28). - Issue #6395: MOFE Door at GSIDFNX05 (2026-04-30). - Issue #6393: Labeling Conflict at GSIDFNX05 (2026-04-30). - Issue #6394: Concrete hole in CMDF1 (2026-04-30). - Issue #6391: Blocked vertical ladder rack locations in CMDF2 (2026-04-30). - Ground bar needed for GSEF 1/2 (2026-05-11). - Clearance issues with VCMs in CMDF2 (2026-05-18). - Awaiting 1 OC for bonding and grounding in CMDF1 and CMDF2 (2026-06-10). - Missing devices and power cords in GSMDF1/GSMDF2 (2026-06-10). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed (2026-04-28). - Measurements verified for CMDF2 VCMs; all met requirements (2026-04-30). - Daily QA meetings held to discuss workflows and upcoming tasks (2026-05-06, 2026-05-13). - Completed L1s and updated QA tracker for accurate tracking (2026-05-18). - Site walk completed with GC, PM, and Supers for RPL10 EF2 (2026-05-18). - Tiger Meeting conducted discussing GC handovers and cable pathways (2026-05-27). ## People Mentioned - Timeon P. - Caleb Bourghs - Perry Brocato - Super Chance - Meta - DPR - Samuel
Wednesday, June 10, 2026
Timeon P. RPL10 · logged 06/10/2026 02:47 PM CT
GSEF1: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES) Dress all OSP cables to the respective OSE. (Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) GSEF2: OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES) Dress all OSP cables to the respective OSE.(Mortenson/IES) Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson) Possibly paint the slab. (Mortenson) CMDF1: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) CMDF2: Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES) Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson) GSMDF1: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS) GSMDF2: 2x Spill outs needed Networking Constraints Missing 10 devices for corpnet and 24 power cords (IBOS) Waiting 110 of fact net devices and optics (IBOS) FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Wednesday, May 27, 2026
Caleb Bourghs NCB RPL10 · logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK. Notes from walk: Qa GC MDF WALK CABLE PATHWAY FOR NORTH WALL LOCATION EPMS LOCATION? FIBER WILL BE ON TOP OF TRANSITIONS FOK CABLE SYSTEM PATHWAYS FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC Mdf2, same issue with ap location next to fire alarm. Extending ap piping to be way from alarm Swap rack direction rfi CMDF? NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX E 1 25% WHEN ROW 5 IS ANCHORED NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED Front o base 84 1/2, back to back 77 1/2 ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE! Place end caps while material is on ground. EGsidf2 - fe needs to arrange Box for outside wap Exterior cans are hung, need close out with qa Get fok for external, send to chance CMDF 2 - FACEPLATES FOR SOUTH WALL CMDF1 - vertical ladder rack for south wall after cement sets
Monday, May 18, 2026
Caleb Bourghs NCB RPL10 · logged 05/18/2026 04:01 PM CT
Completed walk and measurements with QA Team for RPL10 EF2. Received notice from DPR about GSCMDF VCMs are too close to the wall to open rack doors for full clearance. Verified our teams are working on it. Returned after lunch to verify clearance, there is enough room for doors to open comfortably. Verified they are still trying to make more room for opening VCM doors. Did RPL10 EF2 site walk with GC, PM, and Supers. Verified our team is bringing all material through RPL10 Gate 2 (Front right gate if your facing rpl10 from trailer city). Completed L1s and edited older L1s adding name and quantity. Updated qa tracker to match L1 forms.
Wednesday, May 13, 2026
Caleb Bourghs NCB RPL10 · logged 05/14/2026 07:13 AM CT
Daily QA meeting to discuss walk, upcoming FOK, and standards. Had meeting with Meta, DPR, and other GCs to discuss upcoming walks, alignment, and new procedures for hand offs. Walked field with Meta to update issues. Helped Timeon complete FOK with field photos. Completed L1s to Qa tracker for accurate tracking.
Monday, May 11, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2 · logged 05/12/2026 07:12 AM CT
Conducted a field walk of GSEF 1/2 and CMDF 1/2. Ground bar is needed to complete GSEF 1/2. Samuel wants a FOK of the GSEF done by lunch Wednesday.
Wednesday, May 06, 2026
Caleb Bourghs NCB · logged 05/07/2026 06:03 AM CT
Created L1 checklist for 45 different shipments to the warehouse. Met with Meta, DPR, and other GCs for 11am to discuss upcoming weekly Wednesday walks with needed personnel to better align our scheduling and progress. Qa Team meeting discussing IES QA/QC Workflow Process.
Friday, May 01, 2026
Perry brocato · logged 05/01/2026 09:51 AM CT
We were at the warehouse and we counted and inspected 554 2 post,12 4 post and 11 VCM.
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).