Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
6 entries
Clear
6 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the period from April 30 to May 22, 2026, focusing on inspections and coordination related to the OOR process. Key themes include ongoing issue identification, material verification, and site walkthroughs to ensure compliance with specifications. ## By Area / Equipment - **GSIDFNX05** - Racks placed correctly before anchoring (4/30). - Issues reported: - Issue #6395: MOFE Door (4/30). - Issue #6393: Labeling Conflict (4/30). - Fiber clippings and dressing issues noted; Clear Core called back for corrections (4/30). - **CMDF1** - Issue #6394: Concrete hole on East Wall (4/30). - **CMDF2** - Issue #6391: Ladder rack locations blocked by EPMS/BAS conduit (4/30). - Verified VCM measurements met requirements (4/30). - **Warehouse** - Verified all material through OOR; 554 two-post racks in good condition (5/1). - Completed L1s and verified material at Mortenson Tent (5/5). - **RPL10** - Walk and measurements completed; VCM clearance issues noted but confirmed sufficient room for door operation (5/18). - Updated QA tracker to match L1 forms (5/18). ## Issues / Open Items - Issue #6395: MOFE Door (4/30). - Issue #6393: Labeling Conflict (4/30). - Issue #6394: Concrete hole on East Wall (4/30). - Issue #6391: Ladder rack locations blocked (4/30). - Clearance issue with GSCMDF VCMs noted (5/18). ## Progress / Completed - Racks placed and verified in GSIDFNX05 (4/30). - All measurements for CMDF2 VCMs met specifications (4/30). - Verified all material at Warehouse and completed L1s (5/1). - Material verified at Mortenson Tent and arrangements made for pickup (5/5). - Updated QA tracker to match L1 forms (5/18). ## People Mentioned - Timeon P. - Caleb Bourghs - Super Chance - Richard - DPR (indirect mention)
Friday, May 22, 2026
Caleb Bourghs WAREHOUSE · logged 05/27/2026 09:51 AM CT
Created L1s, verified all deliverables on Warehouse floor. Coordinated with Logistics team to move material.
Monday, May 18, 2026
Caleb Bourghs NCB RPL10 · logged 05/18/2026 04:01 PM CT
Completed walk and measurements with QA Team for RPL10 EF2. Received notice from DPR about GSCMDF VCMs are too close to the wall to open rack doors for full clearance. Verified our teams are working on it. Returned after lunch to verify clearance, there is enough room for doors to open comfortably. Verified they are still trying to make more room for opening VCM doors. Did RPL10 EF2 site walk with GC, PM, and Supers. Verified our team is bringing all material through RPL10 Gate 2 (Front right gate if your facing rpl10 from trailer city). Completed L1s and edited older L1s adding name and quantity. Updated qa tracker to match L1 forms.
Tuesday, May 05, 2026
Caleb Bourghs RPL · logged 05/06/2026 07:07 AM CT
Verified new material at Warehouse. Completed L1s and verified through OOR. Verified material at Mortenson Tent, arranged our crew to pick it up to bring to Tent 1.
Friday, May 01, 2026
Caleb Bourghs WAREHOUSE, NCB · logged 05/01/2026 03:20 PM CT
Went through all material at Warehouse. Verify all material through OOR, receivables, and ACC website. Verified all 554 tWo post racks were fully up to specs and in good condition. Created all templates for our L1 connectivity materiaL
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.