A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.5 entries
Tags:
RPL10 6
CMDF1 4
CMDF 3
GSEF1/2 3
CMDF2 2
GSEF1 2
DPR 2
GC 2
GSCMDF 2
RFI 2
NCB 2
CMDF1/2 2
GSEF 2
IDFNX5 2
ENS 1
FIM 1
GSEF2 1
GSMDF1 1
GSMDF2 1
IBOS 1
IES 1
OC 1
OSE 1
OSP 1
## Overview
This briefing covers the daily logs from April 30 to June 10, 2026, focusing on the OSE-related activities and requirements across various areas. Key themes include ongoing inspections, necessary adjustments for compliance, and the need for clarity on labeling and splicing preparations.
## By Area / Equipment
- **GSEF1:**
- OSE labels colored per path; clarity needed on labeling requirements (one label per path?) (2026-06-10).
- Horizontal ladder rack on the West wall requires a 24-inch triangle bracket and needs to move to 8" from the wall (2026-06-10).
- Dress all OSP cables to respective OSE (Mortenson/IES) (2026-06-10).
- Concrete slabs need sanding and labeling with placards before splicing can start; possibly paint the slab (Mortenson) (2026-06-10).
- **GSEF2:**
- OSE labels colored per path; clarity needed on labeling requirements (one label per path?) (2026-06-10).
- Dress all OSP cables to respective OSE (Mortenson/IES) (2026-06-10).
- Concrete slabs need sanding and labeling with placards before splicing can start; possibly paint the slab (Mortenson) (2026-06-10).
- **CMDF1:**
- Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (IES) (2026-06-10).
- Concrete slabs need sanding and labeling before splicing can start; possibly paint the slab (Mortenson) (2026-06-10).
- **CMDF2:**
- Awaiting 1 OC to complete rack bonding and grounding; ordered and in transit (IES) (2026-06-10).
- Concrete slabs need sanding and labeling before splicing can start; possibly paint the slab (Mortenson) (2026-06-10).
- **GSMDF1:**
- 2x spill outs needed; networking constraints present.
- Missing 10 devices for corpnet and 24 power cords (IBOS).
- Waiting on 110 fact net devices and optics (IBOS).
- FIM is not updated; no complete portmap for fiber or copper (ENS) (2026-06-10).
- **GSMDF2:**
- 2x spill outs needed; networking constraints present.
- Missing 10 devices for corpnet and 24 power cords (IBOS).
- Waiting on 110 fact net devices and optics (IBOS).
- FIM is not updated; no complete portmap for fiber or copper (ENS) (2026-06-10).
## Issues / Open Items
- Clarity needed on OSE labeling requirements (one label per path?) (2026-06-10).
- Horizontal ladder rack adjustments required in GSEF1 (2026-06-10).
- Concrete slabs need sanding and labeling before splicing can start across multiple areas (2026-06-10).
- Missing devices and power cords for GSMDF1 and GSMDF2 (2026-06-10).
- FIM not updated; incomplete portmap for fiber or copper (2026-06-10).
## Progress / Completed
- Temporary splices of two 192 fibers in IDFNX5 completed by Clear Core (2026-04-30).
- Field walk completed with FE team through GSEF's 1/2, CMDF 1/2, and IDFNX5 (2026-04-30).
- 50% walk in CMDF1 conducted; issues with ladder rack supports identified and being corrected (2026-05-07).
- Site walk with QA Team for RPL10 EF2 completed, and material handling procedures verified (2026-05-18).
- QA team meeting held to discuss specifications and upcoming FOK (2026-05-27).
## People Mentioned
- Timeon P.
- Caleb Bourghs
- SFE Paul
- Clear Core
- Mortenson
- IES
- IBOS
- ENS
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets
Monday, May 18, 2026
Caleb Bourghs
NCB RPL10
· logged 05/18/2026 04:01 PM CT
Completed walk and measurements with QA Team for RPL10 EF2. Received notice from DPR about GSCMDF VCMs are too close to the wall to open rack doors for full clearance. Verified our teams are working on it. Returned after lunch to verify clearance, there is enough room for doors to open comfortably. Verified they are still trying to make more room for opening VCM doors. Did RPL10 EF2 site walk with GC, PM, and Supers. Verified our team is bringing all material through RPL10 Gate 2 (Front right gate if your facing rpl10 from trailer city). Completed L1s and edited older L1s adding name and quantity. Updated qa tracker to match L1 forms.
Thursday, May 07, 2026
Timeon P.
RPL10.CMDF1, GSEF1/2
· logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue.
Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.
Thursday, April 30, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, IDFNX5
· logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5.
Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core.
SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.