## Overview
This briefing covers the period from May 7 to June 10, 2026, highlighting ongoing inspections and preparations for various equipment installations. Key themes include the identification of RFIs and the need for clarifications on labeling and installation requirements.
## By Area / Equipment
- **CMDF1**
- 50% walk conducted; ladder rack supports spaced incorrectly (5/7).
- Awaiting 1 OC for rack bonding and grounding; ordered and in transit (6/10).
- Concrete slabs need sanding and labeling before splicing; possible painting required (6/10).
- **CMDF2**
- Awaiting 1 OC for rack bonding and grounding; ordered and in transit (6/10).
- Concrete slabs need sanding and labeling before splicing; possible painting required (6/10).
- Faceplates for south wall needed (5/27).
- **GSEF1**
- Preparation for 100% walk; RFIs need resolution (5/7).
- OSE labels colored per path; clarity needed on labeling requirements (6/10).
- Horizontal ladder rack needs a 24-inch triangle bracket and repositioning (6/10).
- Dress all OSP cables to respective OSE (6/10).
- Concrete slabs need sanding and labeling before splicing; possible painting required (6/10).
- **GSEF2**
- OSE labels colored per path; clarity needed on labeling requirements (6/10).
- Dress all OSP cables to respective OSE (6/10).
- Concrete slabs need sanding and labeling before splicing; possible painting required (6/10).
- **GSMDF1**
- 2x spill outs needed; networking constraints noted (6/10).
- Missing 10 devices for corpnet and 24 power cords (IBOS) (6/10).
- Waiting on 110 fact net devices and optics (IBOS) (6/10).
- FIM not updated; incomplete portmap for fiber or copper (ENS) (6/10).
- **GSMDF2**
- 2x spill outs needed; networking constraints noted (6/10).
- Missing 10 devices for corpnet and 24 power cords (IBOS) (6/10).
- Waiting on 110 fact net devices and optics (IBOS) (6/10).
- FIM not updated; incomplete portmap for fiber or copper (ENS) (6/10).
## Issues / Open Items
- RFIs pending resolution for GSEF1 and CMDF1 (5/7, 5/27).
- Clarity needed on OSE labeling requirements (6/10).
- Concrete slabs need sanding and labeling before splicing can start (6/10).
- Missing devices and power cords for GSMDF1 and GSMDF2 (6/10).
- FIM not updated; incomplete portmap for fiber or copper (6/10).
## Progress / Completed
- Conducted 50% walk in CMDF1; issues identified and reported (5/7).
- Completed site walk with Supers and DPR; notes saved in Teams (5/27).
- Started L2 FOK for GSCMDF1 (5/27).
- External cans hung; need closeout with QA (5/27).
## People Mentioned
- Timeon P.
- Caleb Bourghs
- Mortenson
- IES
- IBOS
- ENS
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, May 07, 2026
Timeon P.
RPL10.CMDF1, GSEF1/2
· logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue.
Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.