Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
## Overview
On April 30, 2026, a field walk was conducted with the FE team at RPL10 GSEF 1/2, CMDF 1/2, and IDFNX5. The main focus was on the completion of temporary splices and necessary adjustments to the horizontal ladder runway for fiber routing.
## By Area / Equipment
- **RPL10 GSEF 1/2**
- Completed field walk with FE team.
- Photos taken of the temporary 2 post rack for temporary splices.
- **CMDF 1/2**
- Horizontal ladder runway needs to be moved 5" from walls for fiber routing.
- Buildout completed to spec; FE team reviewing for potential change order.
- **IDFNX5**
- Temporary splices of two 192 fibers completed by Clear Core.
## Issues / Open Items
- Need to redline changes to horizontal ladder runway after installation (2026-04-30).
- Review by FE team to determine if a change order is necessary for CMDF adjustments (2026-04-30).
## Progress / Completed
- Temporary splices in IDFNX5 completed by Clear Core (2026-04-30).
## People Mentioned
- Timeon P.
- SFE Paul
- Clear Core team
Thursday, April 30, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, IDFNX5
· logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5.
Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core.
SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.