Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
3 entries
Clear
3 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the period from April 28 to May 7, 2026, focusing on the pre-installation walkthroughs and inspections of the CMDF 1/2 and related areas. Key themes include identifying issues related to structural integrity and equipment placement, as well as ongoing coordination among team members. ## By Area / Equipment - **RPL10.CMDF 1/2** - Pre-installation walkthrough completed (4/28). - Issue #5174 documented regarding room measurements. - 50% walk conducted in CMDF1; ladder rack supports found improperly spaced (5/7). - **RPL10.CMDF1** - Issue #6394: Hole in East Wall identified (4/30). - **RPL10.CMDF2** - Issue #6391: Blocked ladder rack locations due to EPMS/BAS conduit (4/30). - **RPL10.IDFNX5** - Verified splicing; findings reported for necessary changes (4/30). - **RPL10.GSEF1/2** - Preparation for 100% walk initiated (5/7). ## Issues / Open Items - Issue #5174: Room measurement discrepancy (4/28). - Issue #6394: Concrete hole in CMDF1 (4/30). - Issue #6391: Blocked ladder rack locations in CMDF2 (4/30). - Ladder rack supports in CMDF1 spaced incorrectly (5/7). - RFI's pending resolution in GSEF1/2 before room closure (5/7). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed (4/28). - Daily specs and site updates coordinated with QA team (4/30). - Verified specs and measurements for CMDF2 VCMs met requirements (4/30). ## People Mentioned - Timeon P. - Caleb Bourghs - Chance (Superintendent)
Thursday, May 07, 2026
Timeon P. RPL10.CMDF1, GSEF1/2 · logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue. Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).