## Overview On May 7, 2026, a 50% walk was conducted in CMDF1, revealing spacing issues with ladder rack supports. Preparations for a 100% walk in GSEF1/2 were initiated, with outstanding RFIs noted. ## By Area / Equipment - **RPL10.CMDF1** - Conducted a 50% walk. - Ladder rack supports spaced further than 6ft, contrary to specifications. - Field team notified for corrections. - **GSEF1/2** - Walked to prepare for the upcoming 100% walk. - Several RFIs pending resolution before room closure. ## Issues / Open Items - Ladder rack support spacing issue in RPL10.CMDF1 (05-07-2026). - Outstanding RFIs in GSEF1/2 needing resolution before room closure (05-07-2026). ## Progress / Completed - 50% walk completed in RPL10.CMDF1 (05-07-2026). - Preparations for 100% walk in GSEF1/2 initiated (05-07-2026). ## People Mentioned - Timeon P.
Thursday, May 07, 2026
Timeon P. RPL10.CMDF1, GSEF1/2 · logged 05/07/2026 03:53 PM CT
Conducted a 50% walk in CMDF1, found that the ladder rack supports were spaced further than 6ft, as found in the specifications. Notified the field team and they are correcting the issue. Walked GSEF1/2 to prepare for the 100% walk. There are some RFI's that need resolution before we can close the room.