Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
## Overview
On April 30, 2026, a field walk was conducted with the FE team to assess the GSEF 1/2, CMDF 1/2, and IDFNX5 areas. Key discussions focused on temporary splices and necessary adjustments to the horizontal ladder runway for fiber routing.
## By Area / Equipment
- **GSEF 1/2**
- Completed field walk with FE team.
- Photos taken of the temporary 2 post rack for splices.
- **CMDF 1/2**
- Horizontal ladder runway needs to be moved 5" from walls for fiber routing.
- Changes to be redlined post-installation per Hargis.
- **IDFNX5**
- Temporary splices of two 192 fibers completed by Clear Core.
## Issues / Open Items
- Need to confirm if the horizontal ladder runway adjustments will result in a change order (April 30, 2026).
## Progress / Completed
- Completion of temporary splices in IDFNX5 by Clear Core (April 30, 2026).
- Field walk completed with FE team through GSEF 1/2, CMDF 1/2, and IDFNX5 (April 30, 2026).
## People Mentioned
- Timeon P.
- SFE Paul
- Clear Core
- Hargis
Thursday, April 30, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, IDFNX5
· logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5.
Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core.
SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.