Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.2 entries
Tags:
CMDF2 2
GSIDFNX05 2
ALARM 1
ALL 1
ANCHORED 1
AND 1
ANSWER 1
AP 1
ARE 1
BEFORE 1
BEING 1
BOLTS 1
BOX 1
CABLE 1
CAPS 1
CLOSE 1
CMDF 1
CMDF1 1
DISTANCE 1
DPR 1
ELECTRICAL 1
EMI/SPEC 1
END 1
ENSURE 1
Wednesday, May 27, 2026
Caleb Bourghs
NCB RPL10
· logged 05/27/2026 03:57 PM CT
Qa Team meeting discussing Specifications, upcoming FOK, FOK specifics with photo information, and site walk preparations. Started L2 FOK for GSCMDF1. Completed Tiger Meeting going over GC handovers, cable tray system pathways, and bridges for cable pulling. Completed a site walk with our Supers and DPR. Took notes on all discussed and saved in Teams. Took site photos to complete GSCMDF FOK.
Notes from walk:
Qa GC MDF WALK
CABLE PATHWAY FOR NORTH WALL LOCATION
EPMS LOCATION?
FIBER WILL BE ON TOP OF TRANSITIONS
FOK CABLE SYSTEM PATHWAYS
FIRE ALARM MIDDLE LANE, NEED TO SHIFT AP TO MEET MIN DISTANCE EMI/SPEC
Mdf2, same issue with ap location next to fire alarm.
Extending ap piping to be way from alarm
Swap rack direction rfi CMDF?
NO ANSWER ON RFI YET. POTENTIAL ISSUE BEING CLOSE TO ELECTRICAL BOX
E 1
25% WHEN ROW 5 IS ANCHORED
NEED TO VERIFY ALL ROWS ARE EVEN AND MATCHING MEASUREMENTS BEFORE LAST 2 BOLTS ARE PLACED
Front o base 84 1/2, back to back 77 1/2
ENSURE ALL END CAPS ARE PLACED BEFORE STARTING TO PULL CABLE!
Place end caps while material is on ground.
EGsidf2 - fe needs to arrange Box for outside wap
Exterior cans are hung, need close out with qa
Get fok for external, send to chance
CMDF 2 - FACEPLATES FOR SOUTH WALL
CMDF1 - vertical ladder rack for south wall after cement sets
Thursday, April 30, 2026
Timeon P.
GSIDFNX05
· logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints.
Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below:
Issue #6395 GSIDFNX05 MOFE Door
Issue #6393 GSIDFNX05 Labeling Conflict
Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels
Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.