Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.3 entries
Tags:
GSEF2 3
RPL10 3
CMDF1 2
CMDF2 2
GSEF1 2
ENS 1
FIM 1
GSMDF1 1
GSMDF2 1
IBOS 1
IES 1
OC 1
OSE 1
OSP 1
CMDF 1
FE 1
FOK 1
QA 1
NCB 1
Wednesday, June 10, 2026
Timeon P.
RPL10
· logged 06/10/2026 02:47 PM CT
GSEF1:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Horizontal Ladder rack on the West wall needs a 24 inch triangle bracket, and needs to move to 8" from the wall. (IES)
Dress all OSP cables to the respective OSE. (Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
GSEF2:
OSE labels colored per path. Some OSE cans will have more than one path, clarity needed on label requirements. One label per path?(IES)
Dress all OSP cables to the respective OSE.(Mortenson/IES)
Concrete slabs need to be sanded and labeled with placards before splicing can start. (Mortenson)
Possibly paint the slab. (Mortenson)
CMDF1:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
CMDF2:
Awaiting 1 OC to complete rack bonding and grounding. Ordered and in transit (IES)
Concrete slabs need to be sanded and labeled before splicing can start. Possibly paint the slab. (Mortenson)
GSMDF1:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
GSMDF2:
2x Spill outs needed
Networking Constraints
Missing 10 devices for corpnet and 24 power cords (IBOS)
Waiting 110 of fact net devices and optics (IBOS)
FIM is not updated, Do not have a complete portmap for fiber or copper (ENS)
Monday, June 01, 2026
Timeon P.
GSEF2
· logged 06/01/2026 10:27 AM CT
Extra vertical ladder rack under tier 2
Overhead support missing for crossover runway.
Missing caps on unistrut
Tier 1 to tier 2 grounding and bonding missing
Thursday, May 07, 2026
Caleb Bourghs
NCB, RPL10
· logged 05/07/2026 04:54 PM CT
Daily align with QA Team discussing upcoming walks and FOKs. Went over specs per FOK and upcoming walks in GSEF1, GSEF2, CMDF 1, CMDF 2. Met with our FE team at RPL10 and completed a walk through for each room. Verified spacing in between ladder racks support and worked with FE team to have it corrected. Verified splicing, cable management, and routing. Verified cleared issue #6394 in CMDF1. Created checklist with FE team to prepare for the 100% walk.