GSIDFNX12

EXTERNAL
L1 – OFCI Verification
No delivery forms yet. Click "Add Form" to start tracking.
L2 – Infrastructure
0%
Was 03/23/2026
Was 03/27/2026
50%
Target: 04/15/2026
100%
Target: 04/17/2026
L3 – ISP
0%
Was 04/28/2026
Was 05/11/2026
25%
Target: 05/14/2026
50%
Target: 05/18/2026
75%
Target: 05/20/2026
100%
Target: 05/22/2026
L3 – OSP
0%
25%
Target: 04/25/2026
50%
Target: 04/29/2026
75%
Target: 05/04/2026
100%
Target: 05/08/2026
L4 – Network
0%
50%
Target: 05/12/2026
100%
Target: 05/13/2026
L5 – Punchlist
0%
Set start & finish dates to see milestone schedule.