GSIDFNX10

EXTERNAL
L1 – OFCI Verification
No delivery forms yet. Click "Add Form" to start tracking.
L2 – Infrastructure
0%
Was 06/11/2026
Was 06/17/2026
50%
Target: 06/10/2026
100%
Target: 06/12/2026
L3 – ISP
0%
Was 07/10/2026
Was 07/14/2026
50%
Target: 07/08/2026
100%
Target: 07/09/2026
L3 – OSP
0%
25%
Target: 06/22/2026
50%
Target: 06/26/2026
75%
Target: 07/01/2026
100%
Target: 07/06/2026
L4 – Network
0%
50%
Target: 07/08/2026
100%
Target: 07/09/2026
L5 – Punchlist
0%
Set start & finish dates to see milestone schedule.