Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
99
Completed
1
In Progress
99
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
PRE.EP.1000 |
Identify Program Directives, Initiatives, and Expectations - Precon/Estimating | Precon- Early Precon | Complete | 05/20/24 | 07/08/24 | 47.5 | 0.0 |
|
0.0 |
DES.EP.1000 |
Product Design Documentation (PDD) | Early Packages | Complete | 07/08/24 | 07/08/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1020 |
Completion of PDD Package and SDS Package | Early Packages | Complete | 07/08/24 | 07/08/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1040 |
Design Kick Off ( with Product Development Design Package) | Early Packages | Complete | 07/09/24 | 07/09/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1060 |
Develop Project Review Design Package | Early Packages | Complete | 07/11/24 | 08/30/24 | 50.0 | 0.0 |
|
0.0 |
JCL.C.1340 |
RPL10 - Cost Risk LOE-18 Jobsite Management | Cost LOEs | Active | 07/11/24 | 08/25/28 | 0.0 | 742.5 |
|
1248.8 |
PRE.EP.1020 |
Precon Kick Off (Target Value, Risk, Schedule) | Precon- Early Precon | Complete | 07/11/24 | 07/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1040 |
Initial PWO Document Creation (GC) | Precon- Early Precon | Complete | 07/29/24 | 08/16/24 | 6.2 | 0.0 |
|
0.0 |
PRE.EP.1060 |
GC PWO Exhibits Received | Precon- Early Precon | Complete | 07/29/24 | 07/29/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1080 |
PWO Meta Legal Review Send Draft | Precon- Early Precon | Complete | 08/16/24 | 10/18/24 | 5.0 | 0.0 |
|
0.0 |
DES.EP.1080 |
Project Review Design Package Review Cycle | Early Packages | Complete | 08/30/24 | 08/30/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1100 |
Project Review Design Package (for Estimate Development) Delivered | Early Packages | Complete | 09/02/24 | 09/02/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1000 |
Baseline 1 Development | Precon - Budget & Schedule | Complete | 09/02/24 | 10/11/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1020 |
Develop Baseline 1 Budget & Schedule | Precon - Budget & Schedule | Complete | 09/02/24 | 10/10/24 | 35.0 | 0.0 |
|
0.0 |
PRE.MIR.1000 |
Electrical SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 09/04/24 | 09/04/24 | 8.8 | 0.0 |
|
0.0 |
PRE.MIR.1020 |
Mechanical SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 09/04/24 | 09/04/24 | 1.2 | 0.0 |
|
0.0 |
PRE.TPBD.1000 |
Mechanical Allocation SA Package | Trade Partner Bid Development | Complete | 09/04/24 | 09/04/24 | 35.0 | 0.0 |
|
0.0 |
PRE.TPBD.1020 |
Electrical Allocation SA Package | Trade Partner Bid Development | Complete | 09/04/24 | 09/04/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1040 |
Baseline 1 Issuance | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1060 |
Establish Baseline 1 | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1000 |
Issue Bid Package List with Subcontractors & Meta Approval | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1020 |
Initial Procurement Plan Approved | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1080 |
Meta Review & Comment - Baseline 1 | Precon - Budget & Schedule | Complete | 10/14/24 | 11/01/24 | 18.8 | 0.0 |
|
0.0 |
DES.PRS.1000 |
Development of PRS | PRS | Complete | 10/16/24 | 01/13/25 | 46.2 | 0.0 |
|
0.0 |
CX.MIL.SS |
Power Available from Substation - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.3825 |
[RPL10] TC Ready: Overhead cable tray complete [NS1] - for Redundant Pathways - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4005 |
[RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 33-40] - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4025 |
[RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 41-48] - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4085 |
[RPL10] TC Ready: Overhead cable tray complete [NS2] - for Redundant Pathways - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4165 |
[RPL10] TC Ready: Production Cabling [NS2 Rows 33-40] * Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4185 |
[RPL10] TC Ready: Production Cabling [NS2 Rows 41-48]* Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4245 |
[RPL10] TC Ready: Overhead cable tray complete [NS4] - for Redundant Pathways - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4325 |
[RPL10] TC Ready: Production Cabling [NS4 Rows 33-40] *Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4345 |
[RPL10] TC Ready: Production Cabling [NS4 Rows 41-48] *Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4405 |
[RPL10] TC Ready: Overhead cable tray complete [NS3] - for Redundant Pathways - Obsolete | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4485 |
[RPL10] TC Ready: Production Cabling [NS3 Rows 33-40] - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.4505 |
[RPL10] TC Ready: Production Cabling [NS3 Rows 41-48] - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1070 |
[NWB] Substantial Completion - NS12 & EF12 (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1070.A |
[NWB] Substantial Completion - NS12 & EF12 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1080A |
[NWB] Substantial Completion - NS43 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.8040.1A |
[NWB] FE Area Complete (ENS Ready) [NWS 1] (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.8040.2A |
[NWB] FE Area Complete (ENS Ready) [NWS 2] (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.8040.3A |
[NWB] FE Area Complete (ENS Ready) [NWS 3] (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.8040.4A |
[NWB] FE Area Complete (ENS Ready) [NWS 4] (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1405 |
Steel SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1425 |
Mechanical SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1435 |
Roofing SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1450 |
Glass & Metal Panel SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1455 |
Drywall Metal Studs SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1660 |
Ceiling - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.PRE.1680 |
Fire Protection - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.RPL10.5625 |
Area Completion - NS1 (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.RPL10.5645 |
Area Completion - NS2 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.RPL10.5665 |
Area Completion - NS4 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
ICM.RPL10.5685 |
Area Completion - NS3 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1380 |
Steel Crane #1 Movement 01 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1400 |
Steel Crane #2 Movement 01 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1420 |
Steel Crane #1 Movement 01 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1440 |
Steel Crane #2 Movement 01 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1460 |
Steel Crane #1 Movement 02 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1480 |
Steel Crane #2 Movement 02 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1500 |
Steel Crane #1 Movement 02 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1520 |
Steel Crane #2 Movement 02 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1540 |
Steel Crane #1 Movement 03 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1560 |
Steel Crane #2 Movement 03 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1580 |
Steel Crane #1 Movement 03 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1600 |
Steel Crane #2 Movement 03 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1620 |
Steel Crane #1 Movement 04 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1640 |
Steel Crane #2 Movement 04 - Start - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1660 |
Steel Crane #1 Movement 04 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
NW.1680 |
Steel Crane #2 Movement 04 - Finish - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
PRE-PP-1280 |
Concrete - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
PRE-TP-1040 |
Electrical SA - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1280 |
Architectural/Security Fencing - Final Agreement OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
PRE.INT.MRA.1100 |
Waterproofing / Caulking / Expansion Joints - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
PRE.INT.MRA.1120 |
Doors / Frames / Hardware - Meta Authorized - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3010.XR |
Radio Tower(s) Available for DAS ***OBSOLETE*** | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3770.XG |
GS pathway complete NWB to IBOS (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3780.XG |
GS pathway complete NWB to Admin (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3790.XG |
GS pathway complete NWB to GH (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3800.XG |
GS pathway complete NWB to WT (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3810.XG |
NWB to GS.IDF Pathway Complete - ADM (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3820.XG |
SUB.IDF0X1 Set (SIP) (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3830.XG |
SUB.IDF0X2 Set (SIP) (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X39X0.XG |
Production Cabling Start - RPL10 Core to RPL10 NS3 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X39X1.OR380 |
Donahoe Rd Repaving (US 80 - LA 854) (Dates to be confirmed) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X39X2.XG |
Production Cabling Start - RPL10 Core to RPL10 NS2 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X39X3.XG |
Production Cabling Start - RPL10 Core to RPL10 NS4 - OBSOLETE | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4110.XR |
Utility Connections (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4310.XR |
Water Available for Pressure Testing (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4560.XR |
RF Tower able to support campus (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4570.XR |
IBOS able to support campus (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4580.XR |
Admin able to support campus (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4590.XR |
Guard house able to support campus (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4600.XR |
Guardhouse 1 for SC Turnover of NS-1/2 (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4610.XR |
Water Treatment able to support campus (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4620.XR |
Admin SOC Fire Alarm Remote Monitoring Station (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4630.XR |
NWB to SUB.IDF0X1 Fiber Pull Complete (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4640.XR |
NWB to SUB.IDF0X2 Fiber Pull Complete (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X4650.XR |
NWB to SUB.IDF8X1 Fiber Pull Complete (OBSOLETE) | Obsolete | Complete | 10/17/24 | 10/17/24 | 0.0 | 0.0 |
|
0.0 |