Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
57
Completed
43
In Progress
58
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
PRE.EP.1000 |
Identify Program Directives, Initiatives, and Expectations - Precon/Estimating | Precon- Early Precon | Complete | 05/20/24 | 07/08/24 | 47.5 | 0.0 |
|
0.0 |
PRE.EP.1020 |
Precon Kick Off (Target Value, Risk, Schedule) | Precon- Early Precon | Complete | 07/11/24 | 07/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1040 |
Initial PWO Document Creation (GC) | Precon- Early Precon | Complete | 07/29/24 | 08/16/24 | 6.2 | 0.0 |
|
0.0 |
PRE.EP.1060 |
GC PWO Exhibits Received | Precon- Early Precon | Complete | 07/29/24 | 07/29/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1080 |
PWO Meta Legal Review Send Draft | Precon- Early Precon | Complete | 08/16/24 | 10/18/24 | 5.0 | 0.0 |
|
0.0 |
PRE.BNS.1000 |
Baseline 1 Development | Precon - Budget & Schedule | Complete | 09/02/24 | 10/11/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1020 |
Develop Baseline 1 Budget & Schedule | Precon - Budget & Schedule | Complete | 09/02/24 | 10/10/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1040 |
Baseline 1 Issuance | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1060 |
Establish Baseline 1 | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1000 |
Issue Bid Package List with Subcontractors & Meta Approval | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1020 |
Initial Procurement Plan Approved | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1080 |
Meta Review & Comment - Baseline 1 | Precon - Budget & Schedule | Complete | 10/14/24 | 11/01/24 | 18.8 | 0.0 |
|
0.0 |
DES.PRS.1000 |
Development of PRS | PRS | Complete | 10/16/24 | 05/26/25 | 46.2 | 0.0 |
|
0.0 |
PRE.EP.1100 |
Revised PWO Document Submission (GC) | Precon- Early Precon | Complete | 10/21/24 | 11/04/24 | 6.2 | 0.0 |
|
0.0 |
ICM.G.0001.2 |
RPL09 Commencement Date | IMS P0 Milestones | Complete | 11/01/24 | 11/01/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1120 |
PWO Meta Legal Review | Precon- Early Precon | Complete | 11/05/24 | 12/03/24 | 18.8 | 0.0 |
|
0.0 |
PRE.EP.1140 |
PWO Signed | Precon- Early Precon | Complete | 12/04/24 | 12/04/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1120 |
Site BIM Coordination Package [Civil & Struct. Foundation] | Early Packages | Complete | 01/03/25 | 03/31/25 | 75.0 | 0.0 |
|
0.0 |
PRE.BNS.1100 |
Finalize GC/GRs for BL 2 (DPR to Meta) | Precon - Budget & Schedule | Complete | 01/13/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1120 |
Site Logistics Create and Approval for BL 2 | BL2 | Complete | 01/13/25 | 08/28/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1140 |
Develop Project Review Set - Baseline 2 Estimate & Schedule | BL2 | Complete | 01/13/25 | 08/28/25 | 25.0 | 0.0 |
|
0.0 |
DES.EP.1040 |
Design Kick Off ( with Product Development Design Package) | Early Packages | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL09.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL09.SKN.E.01010 |
RPL09.SKIN.East - Install IMP Insulated Metal Panels System - WBS Summary - OBSOLETE | Obsolete | Active | 03/03/25 | 10/17/28 | 1231.2 | 787.5 |
|
0.0 |
DES.PRS.1020 |
Project Review Set (PRS) | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1040 |
PRS Issuance | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1060 |
PRS Review Cycle | PRS | Complete | 05/27/25 | 07/18/25 | 30.0 | 0.0 |
|
0.0 |
DES.PRS.1080 |
PRS Page Turn | PRS | Complete | 05/27/25 | 06/11/25 | 8.8 | 0.0 |
|
0.0 |
PRE.BNS.1160 |
Preliminary Baseline 2 Development (Progress update only DD-6.22.25) | BL2 | Complete | 05/27/25 | 08/04/25 | 30.0 | 0.0 |
|
0.0 |
PRE.BNS.1170 |
Baseline 2 Development | BL2 | Complete | 05/27/25 | 08/04/25 | 30.0 | 0.0 |
|
0.0 |
RPL.PD.D.PX110.XR |
PRS Set - RPL-0 - Complete | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1100 |
IFP Design Lock | PRS | Complete | 07/18/25 | 07/18/25 | 0.0 | 0.0 |
|
0.0 |
DES.IFP.1000 |
Building Permit Package - 100% IFP Development | IFP | Complete | 07/21/25 | 08/11/25 | 13.8 | 0.0 |
|
0.0 |
RPL08.OFCI.6620 |
OFE Delivery ROJ: PTX-FWM (CUP) | (OFCI) - RPL09 - PTX | Active | 07/25/25 | 11/16/26 | 1.2 | 190.0 |
|
222.5 |
RPL09.OFCI.2020 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHB) - 12 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 548.8 | 186.2 |
|
251.2 |
RPL09.OFCI.2030 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHA) - 12 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 561.2 | 186.2 |
|
262.5 |
RPL09.OFCI.2240 |
OFE Delivery ROJ: 3MW Generator (DHD/DHC) - 2 | (OFCI) - RPL09 - Generators | Active | 07/25/25 | 05/18/27 | 562.5 | 345.0 |
|
261.2 |
RPL09.OFCI.2260 |
OFE Delivery ROJ: 3MW Generator (DHA/DHB) - 1 | (OFCI) - RPL09 - Generators | Active | 07/25/25 | 04/06/27 | 552.5 | 307.5 |
|
148.8 |
RPL09.OFCI.2300 |
OFE Delivery ROJ: GSB (DHD/DHC) - 2 | (OFCI) - RPL09 - Generator Switchboard GSB | Active | 07/25/25 | 05/18/27 | 1.2 | 345.0 |
|
261.2 |
RPL09.OFCI.2320 |
OFE Delivery ROJ: GSB (DHA/DHB) - 1 | (OFCI) - RPL09 - Generator Switchboard GSB | Active | 07/25/25 | 04/06/27 | 553.8 | 307.5 |
|
148.8 |
RPL09.OFCI.2830 |
OFE Delivery ROJ: UPS - Core UPS (DHB) - 12 | (OFCI) - RPL09 - UPS | Active | 07/25/25 | 04/26/27 | 548.8 | 325.0 |
|
112.5 |
RPL09.OFCI.3070 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHD) - 12 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 660.0 | 186.2 |
|
401.2 |
RPL09.OFCI.3090 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHC) - 12 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 697.5 | 186.2 |
|
408.8 |
RPL09.OFCI.3110 |
OFE Delivery ROJ: UPS - Core UPS (DHA) - 12 | (OFCI) - RPL09 - UPS | Active | 07/25/25 | 05/17/27 | 561.2 | 343.8 |
|
105.0 |
RPL09.OFCI.3130 |
OFE Delivery ROJ: UPS - Core UPS (DHD) - 10 | (OFCI) - RPL09 - UPS | Active | 07/25/25 | 07/12/27 | 660.0 | 391.2 |
|
196.2 |
RPL09.OFCI.3150 |
OFE Delivery ROJ: UPS - Core UPS (DHC) - 10 | (OFCI) - RPL09 - UPS | Active | 07/25/25 | 08/02/27 | 697.5 | 410.0 |
|
185.0 |
RPL09.OFCI.3190 |
OFE Delivery ROJ: UPS - Control Power UPS (EC) - **?? | (OFCI) - RPL09 - UPS | Active | 07/25/25 | 06/04/27 | 561.2 | 360.0 |
|
265.0 |
RPL09.OFCI.3210 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHB) - 4 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 04/26/27 | 1.2 | 325.0 |
|
112.5 |
RPL09.OFCI.3230 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHA) - 4 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 05/17/27 | 1.2 | 343.8 |
|
105.0 |
RPL09.OFCI.3250 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHD) - 4 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 07/12/27 | 660.0 | 391.2 |
|
196.2 |
RPL09.OFCI.3270 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHC) - 4 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 08/02/27 | 697.5 | 410.0 |
|
185.0 |
RPL09.OFCI.3290 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHB) - 1 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 521.2 | 186.2 |
|
242.5 |
RPL09.OFCI.3310 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHA) - 1 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 566.2 | 186.2 |
|
245.0 |
RPL09.OFCI.3330 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHD) - 1 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 663.8 | 186.2 |
|
347.5 |
RPL09.OFCI.3350 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHC) - 1 | (OFCI) - RPL09 - PLC Panels | Active | 07/25/25 | 11/10/26 | 676.2 | 186.2 |
|
355.0 |
RPL09.OFCI.6640 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 11/16/26 | 1.2 | 190.0 |
|
191.2 |
RPL09.OFCI.6660 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 11/16/26 | 407.5 | 190.0 |
|
191.2 |
RPL09.OFCI.6680 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/09/26 | 426.2 | 208.8 |
|
191.2 |
RPL09.OFCI.6720 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/09/26 | 426.2 | 208.8 |
|
191.2 |
RPL09.OFCI.6760 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/31/26 | 445.0 | 227.5 |
|
326.2 |
RPL09.OFCI.6780 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/31/26 | 445.0 | 227.5 |
|
326.2 |
RPL09.OFCI.6785 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 11/16/26 | 407.5 | 190.0 |
|
191.2 |
RPL09.OFCI.6790 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 11/16/26 | 407.5 | 190.0 |
|
191.2 |
RPL09.OFCI.6795 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/09/26 | 426.2 | 208.8 |
|
191.2 |
RPL09.OFCI.6805 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/09/26 | 426.2 | 208.8 |
|
191.2 |
RPL09.OFCI.6815 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/31/26 | 445.0 | 227.5 |
|
326.2 |
RPL09.OFCI.6820 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 pcs | (OFCI) - RPL09 - Dry Coolers | Active | 07/25/25 | 12/31/26 | 445.0 | 227.5 |
|
326.2 |
RPL09.OFE.1050 |
OFE Delivery ROJ: MV Skid (DHB) - 12 (ROJ03.08.27) (RVCD04.12.27) | (MOFE) - RPL09 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 04/12/27 | 1.2 | 312.5 |
|
83.8 |
RPL09.OFE.1060 |
OFE Delivery ROJ: MV Skid (DHA) - 12 (ROJ03.30.27) (RVCD04.19.27) | (MOFE) - RPL09 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 04/19/27 | 527.5 | 318.8 |
|
96.2 |
RPL09.OFE.1080 |
OFE Delivery ROJ: MV Skid (DHD) - 10 (ROJ04.20.27) (RVCD04.26.27) | (MOFE) - RPL09 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 04/26/27 | 536.2 | 325.0 |
|
222.5 |
RPL09.OFE.1100 |
OFE Delivery ROJ: MV Skid (DHC) - 10 (ROJ05.06.27) (RVCD05.10.27) | (MOFE) - RPL09 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 05/10/27 | 572.5 | 337.5 |
|
226.2 |
RPL09.OFE.1110 |
OFE Delivery ROJ: GS.MDF (DHB) - 1 (ROJ03.01.27) (RVCD03.04.27) | (MOFE) - RPL09 - GS.MDF Module (Facnet) | Active | 07/25/25 | 03/04/27 | 1.2 | 280.0 |
|
161.2 |
RPL09.OFE.1140 |
OFE Delivery ROJ: GS.IDF Hut - Exterior (CUP) - 3 qty (GS.IDFXX01,02,03) (ROJ11.16.27) (RVCD12.16.27) | (MOFE) - RPL09 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 12/16/26 | 406.2 | 215.0 |
|
188.8 |
RPL09.OFE.1150 |
OFE Delivery ROJ: GS.IDF Hut - Exterior (South Yard*) - 1qty (GS.IDFXX04) (ROJ02.24.27) (RVCD01.06.27) | (MOFE) - RPL09 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 01/06/27 | 1.2 | 231.2 |
|
355.0 |
RPL09.OFE.1200 |
OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF9B2) - 1 qty (ROJ02.24.27) (RVCD04.07.27) | (MOFE) - RPL09 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 04/07/27 | 487.5 | 308.8 |
|
173.8 |