Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
52
Completed
48
In Progress
54
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
PRE.EP.1000 Identify Program Directives, Initiatives, and Expectations - Precon/Estimating Precon- Early Precon Complete 05/20/24 07/08/24 47.5 0.0
100%
0.0
PRE.EP.1020 Precon Kick Off (Target Value, Risk, Schedule) Precon- Early Precon Complete 07/11/24 07/11/24 0.0 0.0
100%
0.0
PRE.EP.1040 Initial PWO Document Creation (GC) Precon- Early Precon Complete 07/29/24 08/16/24 6.2 0.0
100%
0.0
PRE.EP.1060 GC PWO Exhibits Received Precon- Early Precon Complete 07/29/24 07/29/24 0.0 0.0
100%
0.0
PRE.EP.1080 PWO Meta Legal Review Send Draft Precon- Early Precon Complete 08/16/24 10/18/24 5.0 0.0
100%
0.0
PRE.BNS.1000 Baseline 1 Development Precon - Budget & Schedule Complete 09/02/24 10/11/24 35.0 0.0
100%
0.0
PRE.BNS.1020 Develop Baseline 1 Budget & Schedule Precon - Budget & Schedule Complete 09/02/24 10/10/24 35.0 0.0
100%
0.0
PRE.BNS.1040 Baseline 1 Issuance Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1060 Establish Baseline 1 Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1000 Issue Bid Package List with Subcontractors & Meta Approval Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1020 Initial Procurement Plan Approved Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1080 Meta Review & Comment - Baseline 1 Precon - Budget & Schedule Complete 10/14/24 11/01/24 18.8 0.0
100%
0.0
DES.PRS.1000 Development of PRS PRS Complete 10/16/24 05/26/25 46.2 0.0
100%
0.0
PRE.EP.1100 Revised PWO Document Submission (GC) Precon- Early Precon Complete 10/21/24 11/04/24 6.2 0.0
100%
0.0
ICM.G.0001.2 RPL06 Commencement Date IMS P0 Milestones Complete 11/01/24 11/01/24 0.0 0.0
100%
0.0
PRE.EP.1120 PWO Meta Legal Review Precon- Early Precon Complete 11/05/24 12/03/24 18.8 0.0
100%
0.0
PRE.EP.1140 PWO Signed Precon- Early Precon Complete 12/04/24 12/04/24 0.0 0.0
100%
0.0
DES.EP.1120 Site BIM Coordination Package [Civil & Struct. Foundation] Early Packages Complete 01/03/25 03/31/25 75.0 0.0
100%
0.0
PRE.BNS.1100 Finalize GC/GRs for BL 2 (DPR to Meta) Precon - Budget & Schedule Complete 01/13/25 07/28/25 0.0 0.0
100%
0.0
PRE.BNS.1120 Site Logistics Create and Approval for BL 2 BL2 Complete 01/13/25 09/19/25 5.0 0.0
100%
0.0
PRE.BNS.1140 Develop Project Review Set - Baseline 2 Estimate & Schedule BL2 Complete 01/13/25 08/28/25 25.0 0.0
100%
0.0
RPL06.CFCI.6510 Fabricate / Deliver - Roof Drain (Scupper & Downspots) (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Active 02/21/25 05/15/26 25.0 31.2
0%
278.8
DES.EP.1040 Design Kick Off ( with Product Development Design Package) Early Packages Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
RPL06.PRED PRED Obsolete Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
DES.PRS.1020 Project Review Set (PRS) PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1040 PRS Issuance PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1060 PRS Review Cycle PRS Complete 05/27/25 07/18/25 30.0 0.0
100%
0.0
DES.PRS.1080 PRS Page Turn PRS Complete 05/27/25 06/11/25 8.8 0.0
100%
0.0
PRE.BNS.1160 Preliminary Baseline 2 Development (Progress update only DD-6.22.25) BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
PRE.BNS.1170 Baseline 2 Development BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
RPL.PD.D.PX110.XR PRS Set - RPL-0 - Complete PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1100 IFP Design Lock PRS Complete 07/18/25 07/18/25 0.0 0.0
100%
0.0
RPL06.OFCI.2020 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHB) - 12 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.2030 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHA) - 12 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.2240 OFE Delivery ROJ: 3MW Generator (DHD/DHC) - 2 (VC08.19.26) (OFCI) - RPL06 - Generators Active 07/25/25 08/19/26 331.2 113.8
0%
148.8
RPL06.OFCI.2260 OFE Delivery ROJ: 3MW Generator (DHA/DHB) - 1 (VC08.05.26) (OFCI) - RPL06 - Generators Active 07/25/25 08/05/26 322.5 101.2
0%
57.5
RPL06.OFCI.2300 OFE Delivery ROJ: GSB (DHD/DHC) - 2 (ROJ08.12.26) (OFCI) - RPL06 - Generator Switchboard GSB Complete 07/25/25 01/16/26 326.2 0.0
100%
0.0
RPL06.OFCI.2320 OFE Delivery ROJ: GSB (DHA/DHB) - 1 (ROJ06.23.26) (OFCI) - RPL06 - Generator Switchboard GSB Complete 07/25/25 01/16/26 322.5 0.0
100%
0.0
RPL06.OFCI.2830 OFE Delivery ROJ: UPS - Core UPS (DHB) - 12 (OFCI) - RPL06 - UPS Active 07/25/25 06/08/26 323.8 50.0
0%
90.0
RPL06.OFCI.3070 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHD) - 12 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.3090 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHC) - 12 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.3110 OFE Delivery ROJ: UPS - Core UPS (DHA) - 12 (OFCI) - RPL06 - UPS Active 07/25/25 06/08/26 26.2 50.0
0%
102.5
RPL06.OFCI.3130 OFE Delivery ROJ: UPS - Core UPS (DHD) - 10 (OFCI) - RPL06 - UPS Active 07/25/25 06/11/26 435.0 53.8
0%
177.5
RPL06.OFCI.3150 OFE Delivery ROJ: UPS - Core UPS (DHC) - 10 (OFCI) - RPL06 - UPS Active 07/25/25 06/11/26 472.5 53.8
0%
193.8
RPL06.OFCI.3190 OFE Delivery ROJ: UPS - Control Power UPS (EC) - (Room #3.1) (OFCI) - RPL06 - UPS Complete 07/25/25 12/30/25 26.2 0.0
100%
0.0
RPL06.OFCI.3210 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHB) - 4 (OFCI) - RPL06 - PLC Panels Active 07/25/25 06/25/26 1.2 66.2
0%
73.8
RPL06.OFCI.3230 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHA) - 4 (OFCI) - RPL06 - PLC Panels Active 07/25/25 07/14/26 1.2 81.2
0%
71.2
RPL06.OFCI.3250 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHD) - 4 (OFCI) - RPL06 - PLC Panels Active 07/25/25 10/19/26 1.2 166.2
0%
65.0
RPL06.OFCI.3270 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHC) - 4 (OFCI) - RPL06 - PLC Panels Active 07/25/25 11/02/26 1.2 178.8
0%
68.8
RPL06.OFCI.3290 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHB) - 1 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.3310 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHA) - 1 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.3330 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHD) - 1 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.3350 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHC) - 1 (OFCI) - RPL06 - PLC Panels Complete 07/25/25 10/31/25 1.2 0.0
100%
0.0
RPL06.OFCI.6620 OFE Delivery ROJ: PTX-FWM (CUP) (ROJ03.12.26) (OFCI) - RPL06 - PTX Complete 07/25/25 09/30/25 1.2 0.0
100%
0.0
RPL06.OFCI.6640 OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 pcs (ROJ03.12.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 01/14/26 163.8 0.0
100%
0.0
RPL06.OFCI.6660 OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 pcs (ROJ03.12.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 03/04/26 163.8 0.0
100%
0.0
RPL06.OFCI.6680 OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 pcs (ROJ04.02.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 03/04/26 182.5 0.0
100%
0.0
RPL06.OFCI.6720 OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 pcs (ROJ04.02.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/13/26 182.5 0.0
0%
103.8
RPL06.OFCI.6760 OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 pcs (ROJ04.24.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/24/26 201.2 12.5
0%
196.2
RPL06.OFCI.6780 OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 pcs (ROJ04.24.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/24/26 201.2 12.5
0%
196.2
RPL06.OFCI.6785 OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 pcs (ROJ03.12.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 01/14/26 163.8 0.0
100%
0.0
RPL06.OFCI.6790 OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 pcs (ROJ03.12.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 03/04/26 163.8 0.0
100%
0.0
RPL06.OFCI.6795 OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 pcs (ROJ04.02.26) (OFCI) - RPL06 - Dry Coolers Complete 07/25/25 03/04/26 182.5 0.0
100%
0.0
RPL06.OFCI.6805 OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 pcs (ROJ04.02.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/13/26 182.5 0.0
0%
103.8
RPL06.OFCI.6815 OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 pcs (ROJ04.24.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/24/26 201.2 12.5
0%
196.2
RPL06.OFCI.6820 OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 pcs (ROJ04.24.26) (OFCI) - RPL06 - Dry Coolers Active 07/25/25 04/24/26 201.2 12.5
0%
196.2
RPL06.OFE.1050 OFE Delivery ROJ: MV Skid (DHB) - 12 (ROJ05.26.26) (RVCD 07.13.26) (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 07/13/26 1.2 80.0
0%
20.0
RPL06.OFE.1060 OFE Delivery ROJ: MV Skid (DHA) - 12 (ROJ06.09.26) (RVCD 07.20.26) (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 07/20/26 296.2 86.2
0%
32.5
RPL06.OFE.1080 OFE Delivery ROJ: MV Skid (DHD) - 10 (ROJ07.15.26) (RVCD 07.24.26) (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 07/24/26 305.0 91.2
0%
115.0
RPL06.OFE.1100 OFE Delivery ROJ: MV Skid (DHC) - 10 (ROJ07.29.26) (RVCD 08.10.26) (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 08/10/26 335.0 105.0
0%
123.8
RPL06.OFE.1110 OFE Delivery ROJ: GS.MDF (DHB) - 1 (ROJ05.14.26) (RVCD 05.29.26) (MOFE) - RPL06 - GS.MDF Module (Facnet) Active 07/25/25 05/29/26 1.2 42.5
0%
102.5
RPL06.OFE.1140 OFE Delivery ROJ: GS.IDF Hut - Exterior (mCUP) - 2 qty (GSIDF6X01,02,03) (ROJ03.25.26) (RVCD 04.29.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 04/28/26 163.8 15.0
0%
95.0
RPL06.OFE.1150 OFE Delivery ROJ: GS.IDF Hut - Exterior (mCUP & South Yard*) - 2qty (GSIDF6X04) (ROJ04.29.26) (RVCD - 5.14.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 05/13/26 248.8 28.8
0%
188.8
RPL06.OFE.1200 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6B2) - 1 qty (ROJ06.24.26) (RVCD 07.01.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 07/01/26 255.0 71.2
0%
115.0
RPL06.OFE.1220 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6A2) - 1 qty (ROJ06.24.26) (RVCD 07.01.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 07/01/26 318.8 71.2
0%
115.0
RPL06.OFE.1228 OFE Delivery ROJ: FWM (CUP) - 1 (ROJ07.15.26) (MOFE) - RPL06 - Facility Water Complete 07/25/25 09/30/25 165.0 0.0
100%
0.0
RPL06.OFE.1230 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6D2) - 1 qty (ROJ07.23.26) (RVCD 08.19.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 08/19/26 1.2 113.8
0%
146.2
RPL06.OFE.1240 OFE Delivery ROJ: GS.MDF (DHA) - 1 (ROJ05.14.26) (RVCD 05.29.26) (MOFE) - RPL06 - GS.MDF Module (Facnet) Active 07/25/25 05/29/26 7.5 42.5
0%
108.8
RPL06.OFE.1250 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6C2) - 1 qty (ROJ07.23.26) (RVCD 08.19.26) (MOFE) - RPL06 - GS.IDF (Exterior and Interior) Active 07/25/25 08/19/26 1.2 113.8
0%
140.0
RPL06.OFE.1400 OFE Delivery ROJ: MES Skids CDU/MTR (DHB) - 10 (Deliver 2 per day) (ROJ05.19.26) (MOFE) - RPL06 - MES CDU/MTR Active 07/25/25 05/01/26 1.2 18.8
0%
126.2
RPL06.OFE.1420 OFE Delivery ROJ: MES Skids CDU/MTR (DHA) - 10 (Deliver 2 per day) (ROJ06.03.26) (MOFE) - RPL06 - MES CDU/MTR Active 07/25/25 06/02/26 290.0 45.0
0%
100.0
RPL06.OFE.1440 OFE Delivery ROJ: MES Skids CDU/MTR (DHD) - 8 (Deliver 2 per day) (ROJ07.09.26) (MOFE) - RPL06 - MES CDU/MTR Active 07/25/25 07/08/26 298.8 76.2
0%
118.8
RPL06.OFE.1460 OFE Delivery ROJ: MES Skids CDU/MTR (DHC) - 8 (Deliver 2 per day) (ROJ07.23.26) (MOFE) - RPL06 - MES CDU/MTR Active 07/25/25 07/22/26 328.8 88.8
0%
95.0
RPL06.OFE.2050 OFE Delivery ROJ: mCUP - mCUP1 - 1 (6 Pieces) (ROJ03.13.26) (MOFE) - RPL06 - mCUP Complete 07/25/25 03/31/26 191.2 0.0
100%
0.0
RPL06.OFE.3480 OFE Delivery ROJ: mCUP - mCUP5 - 1 (6 Pieces) (ROJ04.10.26) (MOFE) - RPL06 - mCUP Active 07/25/25 04/13/26 225.0 0.0
0%
205.0
RPL06.OFE.3490 OFE Delivery ROJ: mCUP - mCUP2 - 1 (6 Pieces) (ROJ03.20.26) (MOFE) - RPL06 - mCUP Complete 07/25/25 04/07/26 197.5 0.0
100%
0.0
RPL06.OFE.3510 OFE Delivery ROJ: mCUP - mCUP3 - 1 (6 Pieces) (ROJ03.27.26) (MOFE) - RPL06 - mCUP Active 07/25/25 04/13/26 203.8 0.0
0%
101.2
RPL06.OFE.3540 OFE Delivery ROJ: mCUP - mCUP4 - 1 (6 Pieces) (ROJ04.03.26) (MOFE) - RPL06 - mCUP Active 07/25/25 04/13/26 210.0 0.0
0%
107.5
RPL06.OFE.3560 OFE Delivery ROJ: mCUP - mCUP6 - 1 (6 Pieces) (ROJ04.17.26) (MOFE) - RPL06 - mCUP Active 07/25/25 04/17/26 231.2 6.2
0%
205.0
RPL06.OFE.5460 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHB) - 21 (ROJ06.03.26) (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 05/19/26 1.2 33.8
0%
41.2
RPL06.OFE.5470 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHA) - 21 (ROJ06.10.26) (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 06/02/26 310.0 45.0
0%
37.5
RPL06.OFE.5480 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHD) - 17 (ROJ08.12.26) (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 08/12/26 418.8 107.5
0%
76.2
RPL06.OFE.5490 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHC) - 17 (ROJ08.26.26) (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 08/26/26 431.2 120.0
0%
65.0
RPL06.OFE.6800 OFE Delivery ROJ: LV Skid (DHB) - 12 (ROJ05.18.26) (RVCD 07.06.26) (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 07/06/26 277.5 73.8
0%
-8.8
RPL06.OFE.6820 OFE Delivery ROJ: LV Skid (DHA) - 12 (ROJ06.02.26) (RVCD 07.10.26) (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 07/10/26 290.0 78.8
0%
-1.2
RPL06.OFE.6840 OFE Delivery ROJ: LV Skid (DHD) - 10 (ROJ07.08.26) (RVCD 07.16.26) (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 07/16/26 298.8 83.8
0%
81.2
RPL06.OFE.6860 OFE Delivery ROJ: LV Skid (DHC) - 10 (ROJ07.22.26) (RVCD 08.04.26) (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 08/04/26 328.8 100.0
0%
77.5
RPL06.OFE.6920 OFE Delivery ROJ: mCUP Elec Skid - mCUP1 - 1 (ROJ03.19.26) (RVCD 04.17.26) Follows MCUP (MOFE) - RPL06 - mCup Electrical Skids - Outside Active 07/25/25 04/16/26 197.5 5.0
0%
116.2
RPL06.OFE.6940 OFE Delivery ROJ: mCUP Elec Skid - mCUP5 - 1 (ROJ04.16.26) (RVCD 05.15.26) Follows MCUP (MOFE) - RPL06 - mCup Electrical Skids - Outside Active 07/25/25 05/14/26 231.2 30.0
0%
197.5
RPL06.OFE.6960 OFE Delivery ROJ: mCUP Elec Skid - mCUP2 - 1 (ROJ03.26.26) (RVCD 04.17.26) Follows MCUP (MOFE) - RPL06 - mCup Electrical Skids - Outside Active 07/25/25 04/16/26 203.8 5.0
0%
116.2