Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
31
Completed
69
In Progress
32
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
PRE.EP.1000 Identify Program Directives, Initiatives, and Expectations - Precon/Estimating Precon- Early Precon Complete 05/20/24 07/08/24 47.5 0.0
100%
0.0
PRE.EP.1020 Precon Kick Off (Target Value, Risk, Schedule) Precon- Early Precon Complete 07/11/24 07/11/24 0.0 0.0
100%
0.0
PRE.EP.1040 Initial PWO Document Creation (GC) Precon- Early Precon Complete 07/29/24 08/16/24 6.2 0.0
100%
0.0
PRE.EP.1060 GC PWO Exhibits Received Precon- Early Precon Complete 07/29/24 07/29/24 0.0 0.0
100%
0.0
PRE.EP.1080 PWO Meta Legal Review Send Draft Precon- Early Precon Complete 08/16/24 10/18/24 5.0 0.0
100%
0.0
PRE.BNS.1000 Baseline 1 Development Precon - Budget & Schedule Complete 09/02/24 10/11/24 35.0 0.0
100%
0.0
PRE.BNS.1020 Develop Baseline 1 Budget & Schedule Precon - Budget & Schedule Complete 09/02/24 10/10/24 35.0 0.0
100%
0.0
PRE.BNS.1040 Baseline 1 Issuance Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1060 Establish Baseline 1 Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1000 Issue Bid Package List with Subcontractors & Meta Approval Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1020 Initial Procurement Plan Approved Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1080 Meta Review & Comment - Baseline 1 Precon - Budget & Schedule Complete 10/14/24 11/01/24 18.8 0.0
100%
0.0
DES.PRS.1000 Development of PRS PRS Complete 10/16/24 05/26/25 46.2 0.0
100%
0.0
PRE.EP.1100 Revised PWO Document Submission (GC) Precon- Early Precon Complete 10/21/24 11/04/24 6.2 0.0
100%
0.0
ICM.G.0001.2 RPL08 Commencement Date IMS P0 Milestones Complete 11/01/24 11/01/24 0.0 0.0
100%
0.0
PRE.EP.1120 PWO Meta Legal Review Precon- Early Precon Complete 11/05/24 12/03/24 18.8 0.0
100%
0.0
PRE.EP.1140 PWO Signed Precon- Early Precon Complete 12/04/24 12/04/24 0.0 0.0
100%
0.0
DES.EP.1120 Site BIM Coordination Package [Civil & Struct. Foundation] Early Packages Complete 01/03/25 03/31/25 75.0 0.0
100%
0.0
PRE.BNS.1100 Finalize GC/GRs for BL 2 (DPR to Meta) Precon - Budget & Schedule Complete 01/13/25 08/25/25 0.0 0.0
100%
0.0
PRE.BNS.1120 Site Logistics Create and Approval for BL 2 BL2 Complete 01/13/25 09/19/25 0.0 0.0
100%
0.0
PRE.BNS.1140 Develop Project Review Set - Baseline 2 Estimate & Schedule BL2 Complete 01/13/25 08/28/25 25.0 0.0
100%
0.0
DES.EP.1040 Design Kick Off ( with Product Development Design Package) Early Packages Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
RPL08.PRED PRED Obsolete Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
RPL08.SKN.E.01010 RPL08.SKIN.East - Install IMP Insulated Metal Panels System - WBS Summary - OBSOLETE Obsolete Active 03/03/25 07/25/28 1157.5 713.8
100%
0.0
DES.PRS.1020 Project Review Set (PRS) PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1040 PRS Issuance PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1060 PRS Review Cycle PRS Complete 05/27/25 07/18/25 30.0 0.0
100%
0.0
DES.PRS.1080 PRS Page Turn PRS Complete 05/27/25 06/11/25 8.8 0.0
100%
0.0
PRE.BNS.1160 Preliminary Baseline 2 Development (Progress update only DD-6.22.25) BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
PRE.BNS.1170 Baseline 2 Development BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
RPL.PD.D.PX110.XR PRS Set - RPL-0 - Complete PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1100 IFP Design Lock PRS Complete 07/18/25 07/18/25 0.0 0.0
100%
0.0
RPL08.OFCI.2020 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHB) - 12 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 457.5 125.0
0%
240.0
RPL08.OFCI.2030 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHA) - 12 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 470.0 125.0
0%
252.5
RPL08.OFCI.2240 OFE Delivery ROJ: 3MW Generator (DHD/DHC) - 2 (OFCI) - RPL08 - Generators Active 07/25/25 02/02/27 471.2 253.8
0%
241.2
RPL08.OFCI.2260 OFE Delivery ROJ: 3MW Generator (DHA/DHB) - 1 (OFCI) - RPL08 - Generators Active 07/25/25 12/17/26 462.5 216.2
0%
167.5
RPL08.OFCI.2300 OFE Delivery ROJ: GSB (DHD/DHC) - 2 (OFCI) - RPL08 - Generator Switchboard GSB Active 07/25/25 02/02/27 471.2 253.8
0%
241.2
RPL08.OFCI.2320 OFE Delivery ROJ: GSB (DHA/DHB) - 1 (OFCI) - RPL08 - Generator Switchboard GSB Active 07/25/25 12/17/26 462.5 216.2
0%
167.5
RPL08.OFCI.2830 OFE Delivery ROJ: UPS - Core UPS (DHB) - 12 (OFCI) - RPL08 - UPS Active 07/25/25 12/30/26 457.5 226.2
0%
138.8
RPL08.OFCI.3070 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHD) - 12 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 568.8 125.0
0%
387.5
RPL08.OFCI.3090 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHC) - 12 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 606.2 125.0
0%
396.2
RPL08.OFCI.3110 OFE Delivery ROJ: UPS - Core UPS (DHA) - 12 (OFCI) - RPL08 - UPS Active 07/25/25 01/15/27 470.0 240.0
0%
137.5
RPL08.OFCI.3130 OFE Delivery ROJ: UPS - Core UPS (DHD) - 10 (OFCI) - RPL08 - UPS Active 07/25/25 03/18/27 568.8 292.5
0%
220.0
RPL08.OFCI.3150 OFE Delivery ROJ: UPS - Core UPS (DHC) - 10 (OFCI) - RPL08 - UPS Active 07/25/25 04/05/27 606.2 306.2
0%
215.0
RPL08.OFCI.3190 OFE Delivery ROJ: UPS - Control Power UPS (EC) - **?? (OFCI) - RPL08 - UPS Active 07/25/25 02/22/27 470.0 270.0
0%
280.0
RPL08.OFCI.3210 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHB) - 4 (OFCI) - RPL08 - PLC Panels Active 07/25/25 12/30/26 457.5 226.2
0%
138.8
RPL08.OFCI.3230 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHA) - 4 (OFCI) - RPL08 - PLC Panels Active 07/25/25 01/15/27 0.0 240.0
0%
137.5
RPL08.OFCI.3250 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHD) - 4 (OFCI) - RPL08 - PLC Panels Active 07/25/25 03/18/27 568.8 292.5
0%
220.0
RPL08.OFCI.3270 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHC) - 4 (OFCI) - RPL08 - PLC Panels Active 07/25/25 04/05/27 606.2 306.2
0%
215.0
RPL08.OFCI.3290 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHB) - 1 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 436.2 125.0
0%
222.5
RPL08.OFCI.3310 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHA) - 1 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 475.0 125.0
0%
235.0
RPL08.OFCI.3330 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHD) - 1 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 572.5 125.0
0%
332.5
RPL08.OFCI.3350 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHC) - 1 (OFCI) - RPL08 - PLC Panels Active 07/25/25 09/01/26 585.0 125.0
0%
341.2
RPL08.OFCI.6620 OFE Delivery ROJ: PTX-FWM (CUP) (OFCI) - RPL08 - PTX Active 07/25/25 08/04/26 316.2 100.0
0%
237.5
RPL08.OFCI.6640 OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/04/26 317.5 100.0
0%
210.0
RPL08.OFCI.6660 OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/04/26 317.5 100.0
0%
210.0
RPL08.OFCI.6680 OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/25/26 336.2 118.8
0%
210.0
RPL08.OFCI.6720 OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/25/26 336.2 118.8
0%
210.0
RPL08.OFCI.6760 OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 09/16/26 355.0 137.5
0%
342.5
RPL08.OFCI.6780 OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 09/16/26 355.0 137.5
0%
342.5
RPL08.OFCI.6785 OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/04/26 317.5 100.0
0%
210.0
RPL08.OFCI.6790 OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/04/26 317.5 100.0
0%
210.0
RPL08.OFCI.6795 OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/25/26 336.2 118.8
0%
210.0
RPL08.OFCI.6805 OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 08/25/26 336.2 118.8
0%
210.0
RPL08.OFCI.6815 OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 09/16/26 355.0 137.5
0%
342.5
RPL08.OFCI.6820 OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 pcs (OFCI) - RPL08 - Dry Coolers Active 07/25/25 09/16/26 355.0 137.5
0%
342.5
RPL08.OFE.1050 OFE Delivery ROJ: MV Skid (DHB) - 12 (ROJ11.17.26) (RVCD12.07.26) (MOFE) - RPL08 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 12/07/26 437.5 206.2
0%
118.8
RPL08.OFE.1060 OFE Delivery ROJ: MV Skid (DHA) - 12 (ROJ12.10.26) (RVCD01.18.27) (MOFE) - RPL08 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 01/15/27 430.0 240.0
0%
103.8
RPL08.OFE.1080 OFE Delivery ROJ: MV Skid (DHD) - 10 (ROJ01.04.27) (RVCD01.25.27) (MOFE) - RPL08 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 01/25/27 443.8 246.2
0%
223.8
RPL08.OFE.1100 OFE Delivery ROJ: MV Skid (DHC) - 10 (ROJ01.21.27) (RVCD02.02.27) (MOFE) - RPL08 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 02/02/27 481.2 253.8
0%
236.2
RPL08.OFE.1110 OFE Delivery ROJ: GS.MDF (DHB) - 1 (ROJ11.05.26) (RVCD11.12.26) (MOFE) - RPL08 - GS.MDF Module (Facnet) Active 07/25/25 11/12/26 392.5 187.5
0%
182.5
RPL08.OFE.1140 OFE Delivery ROJ: GS.IDF Hut - Exterior (CUP) - 3 qty (GS.IDFXX01,02,03) (ROJ08.04.26) (RVCD08.13.26) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 08/13/26 316.2 108.8
0%
223.8
RPL08.OFE.1150 OFE Delivery ROJ: GS.IDF Hut - Exterior (South Yard*) - 1qty (GS.IDFXX04) (ROJ10.08.26) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 10/08/26 388.8 157.5
0%
357.5
RPL08.OFE.1200 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF8B2) - 1 qty (ROJ10.29.26) (RVCD08.13.26) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 08/13/26 1.2 108.8
0%
302.5
RPL08.OFE.1220 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF8A2) - 1 qty (ROJ10.29.26) (RVCD12.17.26) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 12/17/26 458.8 216.2
0%
195.0
RPL08.OFE.1228 OFE Delivery ROJ: FWM (CUP) - 1 (MOFE) - RPL08 - Facility Water Active 07/25/25 08/04/26 316.2 100.0
0%
237.5
RPL08.OFE.1230 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF8D2) - 1 qty (ROJ01.20.27) (RVCD01.21.27) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 01/21/27 507.5 243.8
0%
255.0
RPL08.OFE.1240 OFE Delivery ROJ: GS.MDF (DHA) - 1 (ROJ11.13.26) (RVCD11.12.26) (MOFE) - RPL08 - GS.MDF Module (Facnet) Active 07/25/25 11/12/26 400.0 187.5
0%
188.8
RPL08.OFE.1250 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF8C2) - 1 qty (ROJ01.12.27) (RVCD01.21.27) (MOFE) - RPL08 - GS.IDF (Exterior and Interior) Active 07/25/25 01/12/27 500.0 236.2
0%
256.2
RPL08.OFE.1400 OFE Delivery ROJ: MES CDU/MTR (DHB) - 12 (MOFE) - RPL08 - MES CDU/MTR Active 07/25/25 11/09/26 436.2 185.0
0%
171.2
RPL08.OFE.1420 OFE Delivery ROJ: MES CDU/MTR (DHA) - 12 (MOFE) - RPL08 - MES CDU/MTR Active 07/25/25 12/03/26 430.0 203.8
0%
152.5
RPL08.OFE.1440 OFE Delivery ROJ: MES CDU/MTR (DHD) - 12 (MOFE) - RPL08 - MES CDU/MTR Active 07/25/25 12/24/26 438.8 222.5
0%
197.5
RPL08.OFE.1460 OFE Delivery ROJ: MES CDU/MTR (DHC) - 12 (MOFE) - RPL08 - MES CDU/MTR Active 07/25/25 01/13/27 475.0 237.5
0%
171.2
RPL08.OFE.2050 OFE Delivery ROJ: mCUP - mCUP1 - 1 (6 Pieces) (ROJ08.03.26) (MOFE) - RPL08 - mCUP Active 07/25/25 08/03/26 343.8 98.8
0%
221.2
RPL08.OFE.3480 OFE Delivery ROJ: mCUP - mCUP5 - 1 (6 Pieces) (ROJ08.31.26) (MOFE) - RPL08 - mCUP Active 07/25/25 08/31/26 376.2 123.8
0%
360.0
RPL08.OFE.3490 OFE Delivery ROJ: mCUP - mCUP2 - 1 (6 Pieces) (ROJ08.10.26) (MOFE) - RPL08 - mCUP Active 07/25/25 08/10/26 350.0 105.0
0%
221.2
RPL08.OFE.3510 OFE Delivery ROJ: mCUP - mCUP3 - 1 (6 Pieces) (ROJ08.17.26) (MOFE) - RPL08 - mCUP Active 07/25/25 08/17/26 356.2 111.2
0%
221.2
RPL08.OFE.3540 OFE Delivery ROJ: mCUP - mCUP4 - 1 (6 Pieces) (ROJ08.24.26) (MOFE) - RPL08 - mCUP Active 07/25/25 08/24/26 362.5 117.5
0%
221.2
RPL08.OFE.3560 OFE Delivery ROJ: mCUP - mCUP6 - 1 (6 Pieces) (ROJ09.08.26) (MOFE) - RPL08 - mCUP Active 07/25/25 09/08/26 382.5 130.0
0%
360.0
RPL08.OFE.5460 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHB) - 21 (MOFE) - RPL08 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 11/17/26 431.2 191.2
0%
138.8
RPL08.OFE.5470 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHA) - 21 (MOFE) - RPL08 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 12/04/26 1.2 205.0
0%
137.5
RPL08.OFE.5480 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHD) - 17 (MOFE) - RPL08 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 02/09/27 552.5 260.0
0%
180.0
RPL08.OFE.5490 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHC) - 17 (MOFE) - RPL08 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 02/25/27 565.0 273.8
0%
175.0
RPL08.OFE.6800 OFE Delivery ROJ: LV Skid (DHB) - 12 (ROJ11.09.26) (RVCD12.02.26) (MOFE) - RPL08 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 12/02/26 417.5 202.5
0%
116.2
RPL08.OFE.6820 OFE Delivery ROJ: LV Skid (DHA) - 12 (ROJ12.03.26) (RVCD01.12.27) (MOFE) - RPL08 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 01/12/27 430.0 236.2
0%
101.2
RPL08.OFE.6840 OFE Delivery ROJ: LV Skid (DHD) - 10 (ROJ12.24.26) (RVCD01.20.27) (MOFE) - RPL08 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 01/20/27 438.8 242.5
0%
153.8
RPL08.OFE.6860 OFE Delivery ROJ: LV Skid (DHC) - 10 (ROJ01.13.27) (RVCD01.26.27) (MOFE) - RPL08 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 01/26/27 475.0 247.5
0%
161.2
RPL08.OFE.6920 OFE Delivery ROJ: mCUP Elec Skid - mCUP1 - 1 (ROJ08.18.26) (RVCD08.13.26) Follows MCUP 2 (MOFE) - RPL08 - mCup Electrical Skids - Outside Active 07/25/25 08/13/26 350.0 108.8
0%
232.5
RPL08.OFE.6940 OFE Delivery ROJ: mCUP Elec Skid - mCUP5 - 1 (ROJ09.15.26) (RVCD09.10.26) Follows MCUP 6 (MOFE) - RPL08 - mCup Electrical Skids - Outside Active 07/25/25 09/10/26 382.5 132.5
0%
365.0
RPL08.OFE.6960 OFE Delivery ROJ: mCUP Elec Skid - mCUP2 - 1 (ROJ08.18.26) (RVCD08.13.26) Follows MCUP 2 (MOFE) - RPL08 - mCup Electrical Skids - Outside Active 07/25/25 08/13/26 356.2 108.8
0%
235.0