Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
95
Completed
5
In Progress
95
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.WP4.NS4.03280 RPL10.Connectivity.WP4 FENW NS4 MFD 4.5 Network Suite [JXSW<>MA] Multi Drop Cable *OBSOLETE Obsolete Complete 10/17/24 10/17/24 10.0 0.0
100%
0.0
RPL10.WP4.NS4.03300 RPL10.Connectivity.WP4 FENW NS4 MFD 4.5 GS.MDF <> Network Suites Management Trunks *OBSOLETE Obsolete Complete 10/17/24 10/17/24 10.0 0.0
100%
0.0
RPL10.WP4.NS4.03320 RPL10.Connectivity.WP4 FENW NS4 MFD 4.5 Network Suite Management and Console In-Row Cabling - PON *OBSOLETE Obsolete Complete 10/17/24 10/17/24 10.0 0.0
100%
0.0
RPL10.WP4.NS4.03340 RPL10.Connectivity.WP4 FENW NS4 MFD 4.5 Network Suite Management and Console In-Rack Fanout - PON *OBSOLETE Obsolete Complete 10/17/24 10/17/24 10.0 0.0
100%
0.0
RPL10.WP4.NS4.03640 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite <> NetworkSuite [MA<>EB] *OBSOLETE Obsolete Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.WP4.NS4.03660 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite Multi Drop Cable [MA<>EB] *OBSOLETE Obsolete Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.WP4.NS4.03680 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite [EB<>DR] *OBSOLETE Obsolete Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.WP4.NS4.03700 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite [DR<>DR] *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03720 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite [JXSW<>MA] Trunks *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03740 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite [JXSW<>MA] Fanouts *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03760 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite [JXSW<>MA] Multi Drop Cable *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03780 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 GS.MDF <> Network Suites Management Trunks *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03800 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite Management and Console In-Row Cabling - PON *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.WP4.NS4.03820 RPL10.Connectivity.WP4 FENW NS4 MFD 4.6 Network Suite Management and Console In-Rack Fanout - PON *OBSOLETE Obsolete Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
PRE.EP.1100 Revised PWO Document Submission (GC) Precon- Early Precon Complete 10/21/24 11/04/24 6.2 0.0
100%
0.0
RPL.CM.D.C5760.XR Temporary Bypass Road ( 3A to RPL10) (Obsolete) Obsolete Complete 10/21/24 10/21/24 0.0 0.0
100%
0.0
RPL10.EY.SSB.01210 RPL10.EY.SSB - Install LD Electical In walls OBSOLETE Obsolete Complete 10/21/24 10/24/24 5.0 0.0
100%
0.0
RPL10.INT.SSB.03240 RPL10.Interior.SSB - Priority - Install Drywall at Exterior Walls (Highside OH space) OBSOLETE Priority Wall (P2) - Grid Line 10-38 Complete 10/21/24 10/25/24 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02760 RPL10.Interior.SSB-Corridor - Priority - Install Blocking/Steel Support Assembly for Metal Canopy OBSOLETE Obsolete Complete 10/21/24 10/24/24 5.0 0.0
100%
0.0
RPL10.SKN.NS43.01140 RPL10.SKIN.NS43 - Install Backing of Exterior Wall OBSOLETE Obsolete Complete 10/21/24 10/25/24 6.2 0.0
100%
0.0
ICM.G.0001.2 Commencement Date - Contractual IMS P0 Milestones Complete 11/01/24 11/01/24 0.0 0.0
100%
0.0
PRE.EP.1120 PWO Meta Legal Review Precon- Early Precon Complete 11/05/24 12/03/24 18.8 0.0
100%
0.0
DES.FSO.1000 Foundation & Steel Mill Order Design Package Development Foundation & Steel Mill Order Design Package Complete 11/18/24 03/10/25 93.8 0.0
100%
0.0
PRE.CIDD.1040 Early Steel (Steel Mill Order) Bid Package Precon - Critical Information / Decision Dates Complete 11/18/24 02/14/25 75.0 0.0
100%
0.0
PRE.EP.1140 PWO Signed Precon- Early Precon Complete 12/04/24 12/04/24 0.0 0.0
100%
0.0
DES.EP.1120 Site BIM Coordination Package [Civil & Struct. Foundation IFP Set] Early Packages Complete 01/03/25 03/31/25 75.0 0.0
100%
0.0
DES.IFP.1000 Building Permit Package - 100% IFP Development IFP Complete 01/13/25 04/21/25 85.0 0.0
100%
0.0
DES.PRS.1020 Project Review Set (PRS) PRS Complete 01/13/25 01/13/25 0.0 0.0
100%
0.0
DES.PRS.1040 PRS Issuance PRS Complete 01/13/25 01/13/25 0.0 0.0
100%
0.0
PRE.BNS.1100 Finalize GC/GRs for BL 2 (DPR to Meta) Precon - Budget & Schedule Complete 01/13/25 02/24/25 0.0 0.0
100%
0.0
PRE.BNS.1120 Site Logistics Create and Approval for BL 2 Precon - Budget & Schedule Complete 01/13/25 02/12/25 0.0 0.0
100%
0.0
PRE.BNS.1140 Develop Project Review Set - Baseline 2 Estimate & Schedule Precon - Budget & Schedule Complete 01/13/25 02/10/25 25.0 0.0
100%
0.0
PRE.CIDD.1060 OFE - Finalize OFE Site Specific Scope and RACI with GC; Finalize GR/GC Needs Precon - Critical Information / Decision Dates Complete 01/13/25 02/24/25 72.5 0.0
100%
0.0
RPL.PD.D.PX110.XR PRS Set - RPL-0 - Complete PRS Complete 01/13/25 01/13/25 0.0 0.0
100%
0.0
DES.PRS.1060 PRS Review Cycle PRS Complete 01/14/25 02/18/25 30.0 0.0
100%
0.0
PRE.CIDD.1080 OFE - Identify OFE Elements to Site Specific Design Precon - Critical Information / Decision Dates Complete 01/14/25 01/14/25 1.2 0.0
100%
0.0
PRE.CIDD.1100 OFE - Establish Cost and Schedule Benchmarks for Use of OFE Elements Precon - Critical Information / Decision Dates Complete 01/14/25 01/24/25 12.5 0.0
100%
0.0
PRE.BNS.1160 Baseline 2 Development Precon - Budget & Schedule Complete 01/15/25 02/19/25 30.0 0.0
100%
0.0
DES.PRS.1080 PRS Page Turn PRS Complete 01/21/25 01/23/25 8.8 0.0
100%
0.0
DES.FSO.1020 Foundations/Steel/Utilitties Package Completion Foundation & Steel Mill Order Design Package Complete 03/10/25 03/10/25 0.0 0.0
100%
0.0
PRE.BNS.1180 Meta Review & Comment - Baseline 2 Precon - Budget & Schedule Complete 03/10/25 03/21/25 43.8 0.0
100%
0.0
PRE.BNS.1200 Baseline 2 Issuance Precon - Budget & Schedule Complete 03/10/25 03/10/25 0.0 0.0
100%
0.0
PRE.CIDD.1120 Finalize Site Logistics Precon - Critical Information / Decision Dates Complete 03/10/25 04/16/25 35.0 0.0
100%
0.0
PRE.CIDD.1140 OFE - Provide for Delivery Schedule for OFE Elements to Support Level 2 Schedule Development Precon - Critical Information / Decision Dates Complete 03/10/25 05/27/25 5.0 0.0
100%
0.0
PRE.CIDD.1160 OFE - Finalize Delivery Schedule for OFE Elements to Support Level 3 Schedule Development Precon - Critical Information / Decision Dates Complete 03/10/25 05/27/25 5.0 0.0
100%
0.0
PRE.TPBD.1040 Turnkey Concrete (Foundations Only) - Submit for Meta Review Trade Partner Bid Development Complete 03/10/25 04/10/25 30.0 0.0
100%
0.0
PRE.TPBD.1060 Steel - Mill Order Development for Meta Review Trade Partner Bid Development Complete 03/10/25 03/28/25 18.8 0.0
100%
0.0
RPL10.OFCI.2020 OFE Delivery ROJ: PLC Panels - DH Manager/RIO (NS1) - 12 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 340.0 0.0
100%
0.0
RPL10.OFCI.2030 OFE Delivery ROJ: PLC Panels - DH Manager/RIO (NS2) - 12 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 352.5 0.0
100%
0.0
RPL10.OFCI.2240 OFE Delivery ROJ: 3MW Generator (NS1/NS4) - 1 (See Notes) (OFCI) - RPL10 - Generators Complete 03/10/25 01/30/26 262.5 0.0
100%
0.0
RPL10.OFCI.2260 OFE Delivery ROJ: 3MW Generator (NS2/NS3) - 1 (OFCI) - RPL10 - Generators Complete 03/10/25 01/22/26 276.2 0.0
100%
0.0
RPL10.OFCI.2300 OFE Delivery ROJ: GSB (NS1/NS4) - 1 (OFCI) - RPL10 - Generator Switchboard GSB Complete 03/10/25 11/11/25 262.5 0.0
100%
0.0
RPL10.OFCI.2320 OFE Delivery ROJ: GSB (NS2/NS3) - 1 (OFCI) - RPL10 - Generator Switchboard GSB Complete 03/10/25 11/11/25 276.2 0.0
100%
0.0
RPL10.OFCI.2830 OFE Delivery ROJ: UPS - Core UPS (NS1) - 12 (OFCI) - RPL10 - UPS Complete 03/10/25 11/18/25 340.0 0.0
100%
0.0
RPL10.OFCI.3070 OFE Delivery ROJ: PLC Panels - DH Manager/RIO (NS4) - 12 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 500.0 0.0
100%
0.0
RPL10.OFCI.3090 OFE Delivery ROJ: PLC Panels - DH Manager/RIO (NS3) - 12 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 512.5 0.0
100%
0.0
RPL10.OFCI.3110 OFE Delivery ROJ: UPS - Core UPS (NS2) - 12 (OFCI) - RPL10 - UPS Complete 03/10/25 11/18/25 352.5 0.0
100%
0.0
RPL10.OFCI.3130 OFE Delivery ROJ: UPS - Core UPS (NS4) - 12 (OFCI) - RPL10 - UPS Complete 03/10/25 02/19/26 500.0 0.0
100%
0.0
RPL10.OFCI.3150 OFE Delivery ROJ: UPS - Core UPS (NS3) - 12 (OFCI) - RPL10 - UPS Complete 03/10/25 02/19/26 512.5 0.0
100%
0.0
RPL10.OFCI.3170 OFE Delivery ROJ: UPS - Control Power UPS (EF) - 2 (OFCI) - RPL10 - UPS Complete 03/10/25 11/18/25 351.2 0.0
100%
0.0
RPL10.OFCI.3190 OFE Delivery ROJ: UPS - Control Power UPS (SSB) - 2 (OFCI) - RPL10 - UPS Complete 03/10/25 11/18/25 436.2 0.0
100%
0.0
RPL10.OFCI.3210 OFE Delivery ROJ: PLC Panels - Misc I/O (NS1) - 4 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 340.0 0.0
100%
0.0
RPL10.OFCI.3230 OFE Delivery ROJ: PLC Panels - Misc I/O (NS2) - 4 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 352.5 0.0
100%
0.0
RPL10.OFCI.3250 OFE Delivery ROJ: PLC Panels - Misc I/O (NS4) - 4 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 500.0 0.0
100%
0.0
RPL10.OFCI.3270 OFE Delivery ROJ: PLC Panels - Misc I/O (NS3) - 4 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/22/25 512.5 0.0
100%
0.0
RPL10.OFCI.3290 OFE Delivery ROJ: PLC Panels - FCM I/O (NS1) - 1 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/20/25 321.2 0.0
100%
0.0
RPL10.OFCI.3310 OFE Delivery ROJ: PLC Panels - FCM I/O (NS2) - 1 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/20/25 333.8 0.0
100%
0.0
RPL10.OFCI.3330 OFE Delivery ROJ: PLC Panels - FCM I/O (NS4) - 1 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/20/25 483.8 0.0
100%
0.0
RPL10.OFCI.3350 OFE Delivery ROJ: PLC Panels - FCM I/O (NS3) - 1 (OFCI) - RPL10 - PLC Panels Complete 03/10/25 10/20/25 496.2 0.0
100%
0.0
RPL10.OFCI.6620 OFE Delivery ROJ: PTX-FWM (CUP) - 1 (Original 09.29.25) (OFCI) - RPL10 - PTX Complete 03/10/25 09/29/25 177.5 0.0
100%
0.0
RPL10.OFCI.6640 OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 12/08/25 208.8 0.0
100%
0.0
RPL10.OFCI.6660 OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/03/25 208.8 0.0
100%
0.0
RPL10.OFCI.6680 OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 12/15/25 208.8 0.0
100%
0.0
RPL10.OFCI.6700 OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/04/25 208.8 0.0
100%
0.0
RPL10.OFCI.6720 OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/12/25 215.0 0.0
100%
0.0
RPL10.OFCI.6740 OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/12/25 215.0 0.0
100%
0.0
RPL10.OFCI.6760 OFE Delivery ROJ: Interior Dry Coolers - mCUP7 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/18/25 215.0 0.0
100%
0.0
RPL10.OFCI.6780 OFE Delivery ROJ: Interior Dry Coolers - mCUP8 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/18/25 215.0 0.0
100%
0.0
RPL10.OFCI.6785 OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 12/08/25 213.8 0.0
100%
0.0
RPL10.OFCI.6790 OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/11/25 213.8 0.0
100%
0.0
RPL10.OFCI.6795 OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/19/25 222.5 0.0
100%
0.0
RPL10.OFCI.6800 OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 01/09/26 222.5 0.0
100%
0.0
RPL10.OFCI.6805 OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 12/15/25 213.8 0.0
100%
0.0
RPL10.OFCI.6810 OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 11/11/25 213.8 0.0
100%
0.0
RPL10.OFCI.6815 OFE Delivery ROJ: Exterior Dry Coolers - mCUP7 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 01/09/26 222.5 0.0
100%
0.0
RPL10.OFCI.6820 OFE Delivery ROJ: Exterior Dry Coolers - mCUP8 (CUP) - 3 (OFCI) - RPL10 - Dry Coolers Complete 03/10/25 01/09/26 222.5 0.0
100%
0.0
RPL10.OFE OFE Delivery ROJ - FWM (CUP) - 1 (Orginal CD 09.29.25) (MOFE) - RPL10 - Facility Water Complete 03/10/25 01/07/26 177.5 0.0
100%
0.0
RPL10.OFE.1050 OFE Delivery ROJ: MV Skid (NS1) - 15 (MOFE) - RPL10 - RMU Electrical Yard / MV Skids - Outside Complete 03/10/25 03/02/26 315.0 0.0
100%
0.0
RPL10.OFE.1060 OFE Delivery ROJ: MV Skid (NS2) - 15 (MOFE) - RPL10 - RMU Electrical Yard / MV Skids - Outside Complete 03/10/25 03/20/26 327.5 0.0
100%
0.0
RPL10.OFE.1080 OFE Delivery ROJ: MV Skid (NS4) - 15 (MOFE) - RPL10 - RMU Electrical Yard / MV Skids - Outside Active 03/10/25 05/11/26 347.5 26.2
0%
107.5
RPL10.OFE.1100 OFE Delivery ROJ: MV Skid (NS3) - 15 (MOFE) - RPL10 - RMU Electrical Yard / MV Skids - Outside Active 03/10/25 05/18/26 352.5 32.5
0%
101.2
RPL10.OFE.1110 OFE Delivery ROJ: GS.MDF (NS1) - 1 (MOFE) - RPL10 - GS.MDF Module (Facnet) Complete 03/10/25 02/11/26 278.8 0.0
100%
0.0
RPL10.OFE.1140 OFE Delivery ROJ: GS.IDF Hut - Exterior (CUP) - 3 (NX11, NX12, NX13) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Complete 03/10/25 12/15/25 208.8 0.0
100%
0.0
RPL10.OFE.1150 OFE Delivery ROJ: GS.IDF Hut - Exterior (NS1) - 2 (NX01, NX02) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Complete 03/10/25 04/08/26 340.0 0.0
100%
0.0
RPL10.OFE.1160 OFE Delivery ROJ: GS.IDF Hut - Exterior (NS2) - 2 (NX06, NX07) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Active 03/10/25 04/21/26 243.8 8.8
0%
31.2
RPL10.OFE.1170 OFE Delivery ROJ: GS.IDF Hut - Exterior (NS3) - 2 (NX08, NX09) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Active 03/10/25 06/03/26 377.5 46.2
0%
112.5
RPL10.OFE.1180 OFE Delivery ROJ: GS.IDF Hut - Exterior (NS4) - 2 (NX03, NX04) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Active 03/10/25 05/28/26 372.5 41.2
0%
117.5
RPL10.OFE.1200 OFE Delivery ROJ: GS.IDF Room - Interior (NS1) - 1 (N13) (Center Corrdior) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Complete 03/10/25 02/17/26 332.5 0.0
100%
0.0
RPL10.OFE.1220 OFE Delivery ROJ: GS.IDF Room - Interior (NS2) - 1 (N23) (Center Corridor) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Complete 03/10/25 02/17/26 345.0 0.0
100%
0.0
RPL10.OFE.1230 OFE Delivery ROJ: GS.IDF Room - Interior (NS3) - 2 (Center Corridor) (MOFE) - RPL10 - GS.IDF (Exterior and Interior) Complete 03/10/25 03/06/26 351.2 0.0
100%
0.0