Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
95
Completed
4
In Progress
95
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
PRE.TPBD.1080 |
Glass & Metal Panel Bid & Develop SA Package | Trade Partner Bid Development | Complete | 04/22/25 | 10/10/25 | 40.0 | 0.0 |
|
0.0 |
PRE.TPBD.1100 |
Roofing Bid & Develop SA Package | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 35.0 | 0.0 |
|
0.0 |
PRE.TPBD.1120 |
Fire Protection - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 18.8 | 0.0 |
|
0.0 |
PRE.TPBD.1160 |
Drywall / Ceilings - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 37.5 | 0.0 |
|
0.0 |
PRE.TPBD.1180 |
Waterproofing / Caulking / Expansion Joints - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 37.5 | 0.0 |
|
0.0 |
PRE.TPBD.1200 |
Hot Aisle Containment - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 10/03/25 | 37.5 | 0.0 |
|
0.0 |
PRE.TPBD.1220 |
Doors / Frames / Hardware - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 46.2 | 0.0 |
|
0.0 |
PRE.TPBD.1240 |
Balance of Trades - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 50.0 | 0.0 |
|
0.0 |
PRE.TPBD.1260 |
Kitchen Equipment - Submit for Meta Review | Trade Partner Bid Development | Complete | 04/22/25 | 06/06/25 | 57.5 | 0.0 |
|
0.0 |
RPL10.CFCI.6540 |
RPL10 - (DBC) Submittals - IWP | Exterior Metal Panels | Complete | 04/22/25 | 09/18/25 | 106.2 | 0.0 |
|
0.0 |
PRE.CIDD.1240 |
Approval of Building Permits (starting Foundations) | Precon - Critical Information / Decision Dates | Complete | 04/25/25 | 04/25/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.VDC.3720 |
RPL10.T0 (mCUP/Exterior) - BIM Model & Coordination - Priority 1 | Priority 1 mCUP Yard / Exterior | Complete | 05/05/25 | 08/28/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.VDC.3740 |
RPL10.T0 (SSB to Center EF) - BIM Model & Coordination - Priority 2 | Priority 2 Priority 2 SSB to Center of EF | Complete | 05/06/25 | 07/25/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.VDC.3760 |
RPL10.T0 (Center EF to End Corr.) - BIM Model & Coordination - Priority 3 | Priority 3 Priority 3 Center EF to End Corridor | Complete | 05/06/25 | 07/25/25 | 18.8 | 0.0 |
|
0.0 |
PRE.TPA.1100 |
Mechanical / Plumbing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 05/20/25 | 06/06/25 | 10.0 | 0.0 |
|
0.0 |
PRE.TPA.1060 |
Steel - Award and Issue Subcontract (Limited Contract Approved) | DPR issue Trade Parter Agreements | Complete | 05/23/25 | 06/11/25 | 10.0 | 0.0 |
|
0.0 |
PRE.FA.1040 |
Concrete - Final Agreement | Trade Partner Final Agreement | Complete | 05/24/25 | 05/24/25 | 0.0 | 0.0 |
|
0.0 |
RPL.PD.D.PX310.XR |
IFC Set - RPL-0 - Complete | IFC | Complete | 05/25/25 | 05/25/25 | 0.0 | 0.0 |
|
0.0 |
PRE.MIR.1080 |
Fire Protection SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 05/30/25 | 06/20/25 | 8.8 | 0.0 |
|
0.0 |
DES.IFC.1020 |
IFC Package - Design Completion | IFC | Complete | 06/02/25 | 06/02/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1280 |
Establish OFE Delivery ROJ Dates for Site Specific | Precon - Budget & Schedule | Complete | 06/02/25 | 06/02/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1320 |
iGMP Submission to Meta | Precon - Budget & Schedule | Complete | 06/06/25 | 06/06/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1340 |
iGMP Review by Meta | Precon - Budget & Schedule | Complete | 06/09/25 | 06/20/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3020 |
RPL10 - Prep / Submit for Rvw - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 06/09/25 | 07/29/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3040 |
RPL10 - Prep / Submit for Rvw - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 06/09/25 | 07/22/25 | 50.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6220 |
RPL10 - Prep / Submit for Review - AHUs | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 06/09/25 | 07/23/25 | 25.0 | 0.0 |
|
0.0 |
PRE.CIDD.1220 |
Steel Mill Order Package Release | Precon - Critical Information / Decision Dates | Complete | 06/11/25 | 06/11/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1080 |
Steel - Trade Partner Process Mill Order | DPR issue Trade Parter Agreements | Complete | 06/12/25 | 06/20/25 | 10.0 | 0.0 |
|
0.0 |
PRE.BNS.1300 |
fGMP Development | Precon - Budget & Schedule | Complete | 06/16/25 | 07/25/25 | 27.5 | 0.0 |
|
0.0 |
PRE.MIR.1100 |
Roofing SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 06/16/25 | 07/14/25 | 6.2 | 0.0 |
|
0.0 |
PRE.MIR.1140 |
Drywall SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 06/16/25 | 07/14/25 | 10.0 | 0.0 |
|
0.0 |
PRE.MIR.1240 |
Doors / Frames / Hardware SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 06/16/25 | 07/14/25 | 10.0 | 0.0 |
|
0.0 |
PRE.BNS.1360 |
Meta iGMP Submission Comments sent to GC | Precon - Budget & Schedule | Complete | 06/20/25 | 06/20/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1380 |
GMP Review and Final Submission (fGMP) | Precon - Budget & Schedule | Complete | 06/20/25 | 08/05/25 | 22.5 | 0.0 |
|
0.0 |
PRE.FA.1020 |
Electrical - Final Agreement | Trade Partner Final Agreement | Complete | 06/20/25 | 06/20/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1140 |
Steel Mill Order Placed | DPR issue Trade Parter Agreements | Complete | 06/20/25 | 06/20/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5675.XR |
Jaggers Temporary Pavement & Widening- Smalling to Wade | Logistics - Off-Site Receive XREF Milsetones | Complete | 06/20/25 | 06/20/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3010 |
RPL10 - FAB - Steel Mill Order - Released (PD=70 Day) | (CFCI) Div. 05 - Structural Steel | Complete | 06/20/25 | 06/20/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1120 |
Fire Supression - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 06/23/25 | 09/18/25 | 10.0 | 0.0 |
|
0.0 |
JCL.C.1020 |
RPL10 - Cost Risk LOE-2 Survey | Cost LOEs | Complete | 06/30/25 | 08/25/25 | 5.0 | 0.0 |
|
0.0 |
PRE.MIR.1180 |
Ceilings SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 06/30/25 | 07/11/25 | 10.0 | 0.0 |
|
0.0 |
RPL10.MR.1000 |
RPL10.MR - Mobilzation Start | Make Ready | Complete | 06/30/25 | 06/30/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.MR.1020 |
RPL10.MR - Trailer Setup | Make Ready | Complete | 06/30/25 | 07/22/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.MR.1160 |
RPL10.MR - Craft Tent Setup | Make Ready | Complete | 06/30/25 | 08/25/25 | 25.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5350.XR |
Logistics Area #5A - Batch Plant Install Area Available | Logistics - Area Turnovers XREF Milestones | Complete | 07/02/25 | 07/02/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.5460 |
RPL10 - Prep / Submit for Review - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 07/07/25 | 07/23/25 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1100 |
Mechanical / Plumbing - Final Agreement | Trade Partner Final Agreement | Complete | 07/08/25 | 07/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.1000 |
RPL10 - Prep / Submit for Review - Struc. Conc. (Fdn Ready Mix) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 07/14/25 | 07/18/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.1030 |
RPL10 - Prep / Submit for Review - Struc. Conc. (SOG/SOMD Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 07/14/25 | 07/18/25 | 6.2 | 0.0 |
|
0.0 |
PRE.TPA.1160 |
Roofing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 07/15/25 | 11/03/25 | 10.0 | 0.0 |
|
0.0 |
PRE.TPA.1220 |
Ceiling - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 07/15/25 | 09/18/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.OFE.TIA.7100 |
OFE Delivery ROJ: Ancillary Elec Skid (NS1) - POST IGMP - DELAY - ID'd on 07/15/25 | (MOFE) - RPL10 - Ancillary Electrical Skids | Active | 07/15/25 | 04/15/26 | 1.2 | 3.8 |
|
40.0 |
RPL10.OFE.TIA.7120 |
OFE Delivery ROJ: Ancillary Elec Skid (NS2) - POST IGMP - DELAY - ID'd on 07/15/25 | (MOFE) - RPL10 - Ancillary Electrical Skids | Active | 07/15/25 | 04/15/26 | 1.2 | 3.8 |
|
31.2 |
RPL10.OFE.TIA.7140 |
OFE Delivery ROJ: Ancillary Elec Skid (NS4) - POST IGMP - DELAY - ID'd on 07/15/25 | (MOFE) - RPL10 - Ancillary Electrical Skids | Active | 07/15/25 | 04/28/26 | 0.0 | 15.0 |
|
137.5 |
RPL10.OFE.TIA.7160 |
OFE Delivery ROJ: Ancillary Elec Skid (NS3) - POST IGMP - DELAY - ID'd on 07/15/25 | (MOFE) - RPL10 - Ancillary Electrical Skids | Active | 07/15/25 | 04/28/26 | 0.0 | 15.0 |
|
142.5 |
RPL10.MR.1140 |
RPL10.MR - Complex Interior Build out | Make Ready | Complete | 07/17/25 | 08/25/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.MR.1060 |
RPL10.MR - Temp Sewer Tie In | Make Ready | Complete | 07/18/25 | 08/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.MR.1100 |
RPL10.MR - Temp Water Tie In | Make Ready | Complete | 07/18/25 | 08/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.1010 |
RPL10 - Submittal Rvw/App'l - Struc. Conc. (Fdn Ready Mix) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 07/21/25 | 08/08/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.1040 |
RPL10 - Submittal Rvw/App'l - Struc. Conc. (SOG/SOMD/Pads Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 07/21/25 | 08/15/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.MR.1080 |
RPL10.MR - Connectivty Tie In | Make Ready | Complete | 07/21/25 | 08/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.MR.1120 |
RPL10.MR - Complex Exterior Build out | Make Ready | Complete | 07/22/25 | 08/25/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3930 |
RPL10- Submittal Rvw/App'l - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 07/23/25 | 07/29/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.MR.1220 |
RPL10.MR - Parking Areas Buildout | Make Ready | Complete | 07/23/25 | 08/25/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.5470 |
RPL10 - Submittal Rvw/App'l - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 07/24/25 | 07/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.5650 |
RPL10 - Prep / Submit for Review - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 07/24/25 | 07/28/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.6230 |
RPL10 - Submittal Rvw/App'l - AHUs | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 07/24/25 | 07/31/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.MR.1040 |
RPL10.MR - Temp Power Tie In | Make Ready | Complete | 07/24/25 | 08/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3700 |
RPL10 - (SPW - Div 07) Submittals - Below Grade Waterproofing | Waterproofing | Complete | 07/25/25 | 09/08/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.5480 |
RPL10 - Fabricate / Deliver - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 07/25/25 | 08/26/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.VDC.4220 |
RPL10.T1 (SSB to Center EF) - BIM Model & Coordination - Priority 1 | Priority 1 - SSB to EF | Complete | 07/25/25 | 08/28/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.VDC.4300 |
RPL10.T1 (Center EF to End Corr.) - BIM Model & Coordination - Priority 2 | Priority 2 - EF to End Corridor | Complete | 07/25/25 | 10/03/25 | 8.8 | 0.0 |
|
0.0 |
PRE.BNS.1460 |
fGMP Review Cycle | Precon - Budget & Schedule | Complete | 07/28/25 | 08/08/25 | 12.5 | 0.0 |
|
0.0 |
PRE.MIR.1160 |
Waterproofing / Caulking / Expansion Joints SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 07/28/25 | 08/13/25 | 10.0 | 0.0 |
|
0.0 |
PRE.MIR.1280 |
Kitchen Equipment SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 07/28/25 | 08/13/25 | 10.0 | 0.0 |
|
0.0 |
RPL06.PR.PRDC.01000 |
RPL06.PR.DHD & DHC Provision (constraint from RPL-1 - DH-1/2 - 2027.08.30) ( DO NOT DELETE) | Obsolete | Not Started | 07/28/25 | 09/22/25 | 50.0 | 50.0 |
|
722.5 |
RPL10.CFCI.6140 |
RPL10- Submittals - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 07/28/25 | 09/08/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.VDC.4060 |
RPL10.T0 (SSB to Center EF) - BIM Prepare & Submit Shops - Priority 2 | Priority 2 Priority 2 SSB to Center of EF | Complete | 07/28/25 | 07/29/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4080 |
RPL10.T0 (Center EF to End Corr.) - BIM Prepare & Submit Shops - Priority 3 | Priority 3 Priority 3 Center EF to End Corridor | Complete | 07/28/25 | 09/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4100 |
RPL10.BIM TIER 2 - 4 | TIER 2 - 4 | Complete | 07/28/25 | 07/28/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.VDC.4460 |
RPL10.BIM TIER 2 - 4 - ALL Model Coordination | TIER 2 - 4 | Complete | 07/28/25 | 09/02/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.5670 |
RPL10 - Submittal Rvw/App'l - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 07/29/25 | 08/11/25 | 12.5 | 0.0 |
|
0.0 |
PRE.TPA.1180 |
Drywall Metal Studs - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 07/30/25 | 09/18/25 | 6.2 | 0.0 |
|
0.0 |
PRE.TPA.1260 |
Doors / Frames / Hardware - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 07/30/25 | 08/14/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.3360 |
RPL10 - Prep / Submit for Review - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Complete | 07/30/25 | 08/07/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3420 |
RPL10- Review for Approval - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 07/30/25 | 08/18/25 | 17.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3960 |
RPL10- Fabricate / Deliver Joists (PD=60 Day) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 07/30/25 | 10/20/25 | 72.5 | 0.0 |
|
0.0 |
RPL10.CFCI.4520 |
RPL10- SSB - Deliver - Anchor Bolts | (CFCI) Div. 05 - Anchor Bolt Delivery | Complete | 07/30/25 | 08/15/25 | 16.2 | 0.0 |
|
0.0 |
RPL10.VDC.3800 |
RPL10.T0 (SSB to Center EF) - BIM Review & Approve Shops - Priority 2 | Priority 2 Priority 2 SSB to Center of EF | Complete | 07/30/25 | 09/02/25 | 12.5 | 0.0 |
|
0.0 |
RPL.CM.D.C5535.XR |
Logistics Area #3 - DPR Office Outpost #1 Area Available | Logistics - Area Turnovers XREF Milestones | Complete | 08/01/25 | 08/01/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1400 |
GMP Review by Legal | Precon - Budget & Schedule | Complete | 08/06/25 | 12/08/25 | 16.2 | 0.0 |
|
0.0 |
RPL10.CFCI.3650 |
RPL10 - Submittals - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 08/06/25 | 09/29/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.CFCI.3660 |
RPL10- Submittals - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 08/06/25 | 09/29/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.MR.1180 |
RPL10.MR - Craft Tent Buildout | Make Ready | Complete | 08/06/25 | 08/25/25 | 13.8 | 0.0 |
|
0.0 |
PRE.TPA.1200 |
Waterproofing / Caulking / Expansion Joints - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 08/07/25 | 09/05/25 | 10.0 | 0.0 |
|
0.0 |
PRE.BNS.1440 |
fGMP Issuance | Precon - Budget & Schedule | Complete | 08/08/25 | 08/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3570 |
RPL10 - Submittal Rvw/App'l - Fire Suppression (AHJ) | (CFCI) Div. 21 - Fire Suppression | Complete | 08/08/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.4340 |
RPL10 - Submittal Rvw/App'l - Below Grade Waterproofing | Waterproofing | Complete | 08/11/25 | 09/08/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.6240 |
RPL10 - Fabricate / Deliver - AHUs (East Side Part deliveries 01/15 & 01/16) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 08/11/25 | 01/22/26 | 145.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6800 |
RPL10 - Fabricate / Deliver - AHUs (West Side) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 08/11/25 | 01/29/26 | 145.0 | 0.0 |
|
0.0 |