Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
92
Completed
7
In Progress
92
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.CFCI.7020 |
RPL10 - Fabricate / Deliver - AHUs Duct Stand (East & West) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 08/11/25 | 03/12/26 | 145.0 | 0.0 |
|
0.0 |
RPL10.MR.1200 |
RPL10.MR - Craft Tent Temp Utilities Buildout | Make Ready | Complete | 08/11/25 | 08/25/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MR.1240 |
RPL10.MR - Install Wayfinding/ Information Boards/ Signage | Make Ready | Complete | 08/11/25 | 08/25/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.5660 |
RPL10 - Fabricate / Deliver - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 08/12/25 | 09/02/25 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1240 |
Doors / Frames / Hardware - Final Agreement | Trade Partner Final Agreement | Complete | 08/14/25 | 08/14/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5784.XR |
BB-8 Road | Logistics - Onsite Receive XREF Milestones | Complete | 08/15/25 | 08/15/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4530 |
RPL10- Submittal Rvw/App'l - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 08/15/25 | 11/11/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3560 |
RPL10 - Fabricate / Deliver - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 08/19/25 | 10/20/25 | 55.0 | 0.0 |
|
0.0 |
GCD.RPL10.1010 |
Break Ground | Construction Milestones | Complete | 08/25/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.1056 |
Pad Ready - RPL10 | Construction Milestones | Complete | 08/25/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1060 |
[NWB] Start Foundations | Construction | Complete | 08/25/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X1010.XR |
Pad Ready (75%) - RPL10 (10-09 /10-42) | Pad Ready (XREFs) | Complete | 08/25/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PR.PRDC.01000 |
RPL06.PR.DHD & DHC Provision (constraint from RPL-1 - DH-1/2 - 2027.08.30) ( DO NOT DELETE) | Obsolete | Not Started | 08/25/25 | 10/20/25 | 50.0 | 50.0 |
|
663.8 |
RPL10.CFCI.3430 |
RPL10 - Prep / Submit for Review - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 08/25/25 | 11/14/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6820 |
RPL10 - Prep / Submit for Review - CRAC Units | (CFCI) Div. 23 - CRAH Units | Complete | 08/25/25 | 09/15/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6880 |
RPL10 - Prep / Submit for Review - CRAH Units | (CFCI) Div. 23 - CRAH Units | Complete | 08/25/25 | 09/15/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.MILE.1540 |
Overall Duration - FDN to Front End Complete NS12 & EF12 - (LOE) | Overall Durations Summary | Active | 08/25/25 | 06/17/27 | 440.0 | 371.2 |
|
1620.0 |
RPL10.MILE.1570 |
Overall Duration - FDN to Front End Complete NS43 & EF-3/4 - (LOE) | Overall Durations Summary | Active | 08/25/25 | 11/23/27 | 541.2 | 508.8 |
|
1482.5 |
RPL10.MR.1260 |
RPL10.MR - Mobilization Complete | Make Ready | Complete | 08/25/25 | 08/25/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.SUB.1000 |
RPL10.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SubStructure | Complete | 08/25/25 | 11/19/25 | 77.5 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01010 |
RPL10.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 08/25/25 | 10/14/25 | 40.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01020 |
RPL10.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SSB | Complete | 08/25/25 | 10/14/25 | 45.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01160 |
RPL10.SubStructure.SSB - Install Drilled Piers - Grid lines 10-42/10-30 -Before Impact - Part 1 | Foundations | Complete | 08/25/25 | 08/28/25 | 5.0 | 0.0 |
|
0.0 |
JCL.C.1080 |
RPL10 - Cost Risk LOE-5 Substructure | Cost LOEs | Active | 08/27/25 | 12/23/26 | 5.0 | 221.2 |
|
83.8 |
JCL.C.1200 |
RPL10 - Cost Risk LOE-11 HVAC | Cost LOEs | Active | 08/27/25 | 02/05/27 | 0.0 | 257.5 |
|
67.5 |
RPL10.SUB.NS12.01020 |
RPL10.SubStructure.NS12 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | NS1 & NS2 | Complete | 08/27/25 | 10/28/25 | 51.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01070 |
RPL10.SubStructure.NS12 - Install UG Utilities - WBS Summary | Underground | Complete | 08/27/25 | 10/28/25 | 51.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01120 |
RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-Before Impact - Part 1 | Underground | Complete | 08/27/25 | 08/28/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01140 |
RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (West)-Before Impact - Part 1 | Underground | Complete | 08/27/25 | 08/28/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01050 |
RPL10.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill-Before Impact-Part 1 | Underground | Complete | 08/27/25 | 08/28/25 | 20.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01060 |
RPL10.SubStructure.SSB - Install UG Utilities - WBS Summary | Underground | Complete | 08/27/25 | 10/14/25 | 40.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01200 |
RPL10.SubStructure.SSB - Piers Protection Concrete Capping-Before Impact - Part 1 | Foundations | Complete | 08/27/25 | 08/28/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01180 |
RPL10.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-42/10-30-Before Impact-Part 1 | Foundations | Complete | 08/28/25 | 08/28/25 | 16.2 | 0.0 |
|
0.0 |
JCL.C.1220 |
RPL10 - Cost Risk LOE-12 Electrical | Cost LOEs | Active | 08/29/25 | 02/05/27 | 0.0 | 257.5 |
|
67.5 |
JCL.C.1240 |
RPL10 - Cost Risk LOE-13 Auxiliary Systems | Cost LOEs | Active | 08/29/25 | 02/05/27 | 0.0 | 257.5 |
|
67.5 |
NW.1940 |
Weather Event #1 - 08/29/25 | Project Impacts | Complete | 08/29/25 | 08/29/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01000 |
RPL10.SubStructure.NS12 - Install Drilled Piers - Grid lines 10-30/10-20 - Before Impact - Part 1 | Foundations | Complete | 08/29/25 | 08/29/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01010 |
RPL10.SubStructure.NS12 - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 08/29/25 | 10/17/25 | 41.2 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01090 |
RPL10.SubStructure.SSB - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside) -Before Impact-Part1 | Underground | Complete | 08/29/25 | 08/29/25 | 16.2 | 0.0 |
|
0.0 |
PRE.FA.1220 |
Waterproofing / Caulking / Expansion Joints - Final Agreement | Trade Partner Final Agreement | Complete | 09/02/25 | 09/02/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1280 |
Kitchen Equipment - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 09/02/25 | 11/18/25 | 72.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3830 |
RPL10 - Prep / Submit for Review - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 09/02/25 | 11/03/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6150 |
RPL10- Submittal Rvw/App'l - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 09/02/25 | 09/19/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01000 |
RPL10.SubStructure.EF12 - Install Drilled Piers - Grid lines 10-20/10-10 | Foundations | Complete | 09/02/25 | 09/03/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01010 |
RPL10.SubStructure.EF12 - Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 09/02/25 | 10/27/25 | 48.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01020 |
RPL10.SubStructure.EF12 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | EF1 & EF2 | Complete | 09/02/25 | 11/07/25 | 61.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01130 |
RPL10.SubStructure.NS12 - Piers Protection Concrete Capping | Foundations | Complete | 09/02/25 | 09/08/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01160 |
RPL10.SubStructure.NS12 - Install Drilled Piers - Grid lines 10-30/10-20 - After Impact - Part 2 | Foundations | Complete | 09/02/25 | 09/03/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01180 |
RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-After Impact - Part 2 | Underground | Complete | 09/02/25 | 09/23/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01200 |
RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (West)-After Impact - Part 2 | Underground | Complete | 09/02/25 | 09/17/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01000 |
RPL10.SubStructure.SSB - Install Drilled Piers - Grid lines 10-42/10-30 - After Impact - Part 2 | Foundations | Complete | 09/02/25 | 09/02/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01040 |
RPL10.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-42/10-30-After Impact-Part 2 | Foundations | Complete | 09/02/25 | 10/03/25 | 16.2 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01140 |
RPL10.SubStructure.SSB - Piers Protection Concrete Capping-After Impact - Part 2 | Foundations | Complete | 09/02/25 | 09/10/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.VDC.4240 |
RPL10.T1 (SSB to Center EF) - BIM Prepare & Submit Shops - Priority 1 | Priority 1 - SSB to EF | Complete | 09/02/25 | 10/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4260 |
RPL10.T1 (SSB to Center EF) - BIM Review & Approve Shops - Priority 1 | Priority 1 - SSB to EF | Complete | 09/02/25 | 10/21/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.VDC.4280 |
RPL10.T1 (SSB to Center EF) - BIM Model/Shops - Priority 1 Final Review (Page Turn) | Priority 1 - SSB to EF | Complete | 09/02/25 | 10/21/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.VDC.4380 |
RPL10.T1 (Misc. Steel) - BIM Model & Coordination - Priority 3 | Priority 3 - Misc Steel | Complete | 09/02/25 | 10/03/25 | 17.5 | 0.0 |
|
0.0 |
RPL10.VDC.3860 |
RPL10.T0 (SSB to Center EF) - BIM Model/Shops - Priority 2 Final Review (Page Turn) | Priority 2 Priority 2 SSB to Center of EF | Complete | 09/03/25 | 09/14/25 | 11.2 | 0.0 |
|
0.0 |
RPL10.VDC.4540 |
RPL10.BIM TIER 2 - 4 - Clash Detection & Finalization | TIER 2 - 4 | Complete | 09/03/25 | 11/25/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01300 |
RPL10.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill - Before Impact | Underground | Complete | 09/04/25 | 09/23/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.VDC.3820 |
RPL10.T0 (Center EF to End Corr.) - BIM Review & Approve Shops - Priority 3 | Priority 3 Priority 3 Center EF to End Corridor | Complete | 09/04/25 | 09/04/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.VDC.3880 |
RPL10.T0 (Center EF to End Corr.) - BIM Model/Shops - Priority 3 Final Review (Page Turn) | Priority 3 Priority 3 Center EF to End Corridor | Complete | 09/05/25 | 09/14/25 | 12.5 | 0.0 |
|
0.0 |
PRE.FA.1080 |
Steel - Final Agreement | Trade Partner Final Agreement | Complete | 09/08/25 | 09/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4490 |
RPL10 - (SPW - Div 07) Fabricate / Deliver - Below Grade Waterproofing | Waterproofing | Complete | 09/08/25 | 09/19/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.4550 |
RPL10 - Submittal Rvw/App'l - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 09/08/25 | 09/26/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4580 |
RPL10 - Prep / Submit for Review - Joint Sealants | Joint Sealants | Complete | 09/08/25 | 09/16/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.4590 |
RPL10- Prep / Submit for Review - Interior Expansion Joints (Spec 07 95 13.13) | Building Expansion Joints (Spec 07 95 13.13) | Complete | 09/08/25 | 09/16/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.VDC.4040 |
RPL10.T0 (mCUP/Exterior) - BIM Prepare & Submit Shops - Priority 1 | Priority 1 mCUP Yard / Exterior | Complete | 09/08/25 | 10/10/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.VDC.4480 |
RPL10.BIM TIER 2 - 4 - Submit Shops | TIER 2 - 4 | Complete | 09/10/25 | 12/01/25 | 31.2 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01030 |
RPL10.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU | Foundations | Complete | 09/11/25 | 09/12/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.CFCI.3300 |
RPL10 - Prep / Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) | Fixed Louvers | Complete | 09/12/25 | 09/22/25 | 25.0 | 0.0 |
|
0.0 |
RPL.10.D.X1015.XR |
Pad Ready (Remaining 25%)- RPL10 (10-09 /10-01) | Pad Ready (XREFs) | Complete | 09/15/25 | 09/15/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01130 |
RPL10.SubStructure.EF12 - Piers Protection Concrete Capping | Foundations | Complete | 09/15/25 | 09/26/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01000 |
RPL10.SubStructure.NS43 - Install Drilled Piers - Grid lines 10-10/10-01 | Foundations | Complete | 09/15/25 | 09/17/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01010 |
RPL10.SubStructure.NS43 - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 09/15/25 | 11/03/25 | 45.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01020 |
RPL10.SubStructure.NS43 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | NS4 & NS3 | Complete | 09/15/25 | 11/19/25 | 60.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01070 |
RPL10.SubStructure.SSB - Install Stem Walls - Grid lines 10-42/10-30 - Before Impact - Part 1 | Foundations | Complete | 09/15/25 | 09/23/25 | 5.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5250.XR |
Logistics Area #5B - OES Equipment Yard Available | Logistics - Area Turnovers XREF Milestones | Complete | 09/16/25 | 09/16/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3840 |
RPL10 - Prep / Submit for Review - Lighting | (CFCI) Div. 26 - Lighting | Complete | 09/16/25 | 09/17/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4840 |
RPL10 - Submittal Rvw/App'l - Joint Sealants | Joint Sealants | Complete | 09/16/25 | 09/19/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4850 |
RPL10 - Submittal Rvw/App'l - Interior Expansion Joints (Spec 07 95 13.13) | Building Expansion Joints (Spec 07 95 13.13) | Complete | 09/16/25 | 09/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.6840 |
RPL10 - Submittal Rvw/App'l - CRAC Units | (CFCI) Div. 23 - CRAH Units | Complete | 09/16/25 | 10/13/25 | 11.2 | 0.0 |
|
0.0 |
RPL10.CFCI.6900 |
RPL10 - Submittal Rvw/App'l - CRAH Units | (CFCI) Div. 23 - CRAH Units | Complete | 09/16/25 | 10/13/25 | 11.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01030 |
RPL10.SubStructure.NS12 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-30/10-20 - Before Impact)-Pt 1 | Foundations | Complete | 09/16/25 | 09/23/25 | 13.8 | 0.0 |
|
0.0 |
RPL10.VDC.4560 |
RPL10.BIM TIER 2 - 4 - Create Shops | TIER 2 - 4 | Complete | 09/17/25 | 12/01/25 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1120 |
Fire Supression - Final Agreement | Trade Partner Final Agreement | Complete | 09/18/25 | 09/18/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1160 |
Drywall Metal Studs - Final Agreement | Trade Partner Final Agreement | Complete | 09/18/25 | 09/18/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1180 |
Ceiling - Final Agreement | Trade Partner Final Agreement | Complete | 09/18/25 | 09/18/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4040 |
RPL10 - Submittal Rvw/App'l - Lighting | (CFCI) Div. 26 - Lighting | Complete | 09/18/25 | 11/06/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.6560 |
RPL10 - Submittal Rvw/App'l - IWP | Exterior Metal Panels | Complete | 09/18/25 | 10/20/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.5130 |
RPL10 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) | Building Expansion Joints (Spec 07 95 13.13) | Complete | 09/22/25 | 11/24/25 | 7.5 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01130 |
RPL10.SubStructure.NS43 - Piers Protection Concrete Capping (Before Impact) | Foundations | Complete | 09/22/25 | 09/23/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.3810 |
RPL10 - Submittal Rvw/App'l - Exterior Louvers (w Ext Metal Panel Trade) | Fixed Louvers | Complete | 09/23/25 | 09/26/25 | 12.5 | 0.0 |
|
0.0 |
NW.1960 |
Weather Event #2 - 09/24/25 - 09/25/25 | Project Impacts | Complete | 09/24/25 | 09/25/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01110 |
RPL10.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill -After Impact | Underground | Complete | 09/25/25 | 10/14/25 | 12.5 | 0.0 |
|
0.0 |
JCL.C.1040 |
RPL10 - Cost Risk LOE-3 Earthwork | Cost LOEs | Active | 09/26/25 | 08/24/26 | 5.0 | 117.5 |
|
42.5 |
JCL.C.1060 |
RPL10 - Cost Risk LOE-4 Rammed Agg Piers | Cost LOEs | Complete | 09/26/25 | 09/26/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01280 |
RPL10.SubStructure.NS12 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-30/10-20 - After Impact)-Pt 2 | Foundations | Complete | 09/26/25 | 10/03/25 | 13.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01300 |
RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-After Impact - Part 3 | Underground | Complete | 09/26/25 | 10/06/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01230 |
RPL10.SubStructure.NS43 - Piers Protection Concrete Capping (After Impact) | Foundations | Complete | 09/26/25 | 10/13/25 | 6.2 | 0.0 |
|
0.0 |