Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
92
Completed
7
In Progress
92
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.CFCI.7020 RPL10 - Fabricate / Deliver - AHUs Duct Stand (East & West) (CFCI) Div. 23 - Air Handler Units (AHUs) Complete 08/11/25 03/12/26 145.0 0.0
100%
0.0
RPL10.MR.1200 RPL10.MR - Craft Tent Temp Utilities Buildout Make Ready Complete 08/11/25 08/25/25 6.2 0.0
100%
0.0
RPL10.MR.1240 RPL10.MR - Install Wayfinding/ Information Boards/ Signage Make Ready Complete 08/11/25 08/25/25 6.2 0.0
100%
0.0
RPL10.CFCI.5660 RPL10 - Fabricate / Deliver - SOG/SOMD/Pads Struc. Conc. (Rebar) (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 08/12/25 09/02/25 18.8 0.0
100%
0.0
PRE.FA.1240 Doors / Frames / Hardware - Final Agreement Trade Partner Final Agreement Complete 08/14/25 08/14/25 0.0 0.0
100%
0.0
RPL.CM.D.C5784.XR BB-8 Road Logistics - Onsite Receive XREF Milestones Complete 08/15/25 08/15/25 0.0 0.0
100%
0.0
RPL10.CFCI.4530 RPL10- Submittal Rvw/App'l - Cold Formed Metal Framing (CFCI) Div. 05 - Cold Formed Metal Framing Complete 08/15/25 11/11/25 12.5 0.0
100%
0.0
RPL10.CFCI.3560 RPL10 - Fabricate / Deliver - Structural Steel (CFCI) Div. 05 - Structural Steel Complete 08/19/25 10/20/25 55.0 0.0
100%
0.0
GCD.RPL10.1010 Break Ground Construction Milestones Complete 08/25/25 08/25/25 0.0 0.0
100%
0.0
GCD.RPL10.1056 Pad Ready - RPL10 Construction Milestones Complete 08/25/25 08/25/25 0.0 0.0
100%
0.0
ICM.B10.1060 [NWB] Start Foundations Construction Complete 08/25/25 08/25/25 0.0 0.0
100%
0.0
RPL.10.D.X1010.XR Pad Ready (75%) - RPL10 (10-09 /10-42) Pad Ready (XREFs) Complete 08/25/25 08/25/25 0.0 0.0
100%
0.0
RPL06.PR.PRDC.01000 RPL06.PR.DHD & DHC Provision (constraint from RPL-1 - DH-1/2 - 2027.08.30) ( DO NOT DELETE) Obsolete Not Started 08/25/25 10/20/25 50.0 50.0
0%
663.8
RPL10.CFCI.3430 RPL10 - Prep / Submit for Review - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Complete 08/25/25 11/14/25 25.0 0.0
100%
0.0
RPL10.CFCI.6820 RPL10 - Prep / Submit for Review - CRAC Units (CFCI) Div. 23 - CRAH Units Complete 08/25/25 09/15/25 25.0 0.0
100%
0.0
RPL10.CFCI.6880 RPL10 - Prep / Submit for Review - CRAH Units (CFCI) Div. 23 - CRAH Units Complete 08/25/25 09/15/25 25.0 0.0
100%
0.0
RPL10.MILE.1540 Overall Duration - FDN to Front End Complete NS12 & EF12 - (LOE) Overall Durations Summary Active 08/25/25 06/17/27 440.0 371.2
0%
1620.0
RPL10.MILE.1570 Overall Duration - FDN to Front End Complete NS43 & EF-3/4 - (LOE) Overall Durations Summary Active 08/25/25 11/23/27 541.2 508.8
0%
1482.5
RPL10.MR.1260 RPL10.MR - Mobilization Complete Make Ready Complete 08/25/25 08/25/25 0.0 0.0
100%
0.0
RPL10.SUB.1000 RPL10.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SubStructure Complete 08/25/25 11/19/25 77.5 0.0
100%
0.0
RPL10.SUB.SSB.01010 RPL10.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 08/25/25 10/14/25 40.0 0.0
100%
0.0
RPL10.SUB.SSB.01020 RPL10.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SSB Complete 08/25/25 10/14/25 45.0 0.0
100%
0.0
RPL10.SUB.SSB.01160 RPL10.SubStructure.SSB - Install Drilled Piers - Grid lines 10-42/10-30 -Before Impact - Part 1 Foundations Complete 08/25/25 08/28/25 5.0 0.0
100%
0.0
JCL.C.1080 RPL10 - Cost Risk LOE-5 Substructure Cost LOEs Active 08/27/25 12/23/26 5.0 221.2
0%
83.8
JCL.C.1200 RPL10 - Cost Risk LOE-11 HVAC Cost LOEs Active 08/27/25 02/05/27 0.0 257.5
0%
67.5
RPL10.SUB.NS12.01020 RPL10.SubStructure.NS12 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary NS1 & NS2 Complete 08/27/25 10/28/25 51.2 0.0
100%
0.0
RPL10.SUB.NS12.01070 RPL10.SubStructure.NS12 - Install UG Utilities - WBS Summary Underground Complete 08/27/25 10/28/25 51.2 0.0
100%
0.0
RPL10.SUB.NS12.01120 RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-Before Impact - Part 1 Underground Complete 08/27/25 08/28/25 8.8 0.0
100%
0.0
RPL10.SUB.NS12.01140 RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (West)-Before Impact - Part 1 Underground Complete 08/27/25 08/28/25 8.8 0.0
100%
0.0
RPL10.SUB.SSB.01050 RPL10.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill-Before Impact-Part 1 Underground Complete 08/27/25 08/28/25 20.0 0.0
100%
0.0
RPL10.SUB.SSB.01060 RPL10.SubStructure.SSB - Install UG Utilities - WBS Summary Underground Complete 08/27/25 10/14/25 40.0 0.0
100%
0.0
RPL10.SUB.SSB.01200 RPL10.SubStructure.SSB - Piers Protection Concrete Capping-Before Impact - Part 1 Foundations Complete 08/27/25 08/28/25 5.0 0.0
100%
0.0
RPL10.SUB.SSB.01180 RPL10.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-42/10-30-Before Impact-Part 1 Foundations Complete 08/28/25 08/28/25 16.2 0.0
100%
0.0
JCL.C.1220 RPL10 - Cost Risk LOE-12 Electrical Cost LOEs Active 08/29/25 02/05/27 0.0 257.5
0%
67.5
JCL.C.1240 RPL10 - Cost Risk LOE-13 Auxiliary Systems Cost LOEs Active 08/29/25 02/05/27 0.0 257.5
0%
67.5
NW.1940 Weather Event #1 - 08/29/25 Project Impacts Complete 08/29/25 08/29/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01000 RPL10.SubStructure.NS12 - Install Drilled Piers - Grid lines 10-30/10-20 - Before Impact - Part 1 Foundations Complete 08/29/25 08/29/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01010 RPL10.SubStructure.NS12 - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 08/29/25 10/17/25 41.2 0.0
100%
0.0
RPL10.SUB.SSB.01090 RPL10.SubStructure.SSB - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside) -Before Impact-Part1 Underground Complete 08/29/25 08/29/25 16.2 0.0
100%
0.0
PRE.FA.1220 Waterproofing / Caulking / Expansion Joints - Final Agreement Trade Partner Final Agreement Complete 09/02/25 09/02/25 0.0 0.0
100%
0.0
PRE.TPA.1280 Kitchen Equipment - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 09/02/25 11/18/25 72.5 0.0
100%
0.0
RPL10.CFCI.3830 RPL10 - Prep / Submit for Review - Building Controls (CFCI) Div. 23 - Building Controls Complete 09/02/25 11/03/25 25.0 0.0
100%
0.0
RPL10.CFCI.6150 RPL10- Submittal Rvw/App'l - CMU - Storm Shelter (CFCI) Div. 04 - Concrete Masonry Units Complete 09/02/25 09/19/25 3.8 0.0
100%
0.0
RPL10.SUB.EF12.01000 RPL10.SubStructure.EF12 - Install Drilled Piers - Grid lines 10-20/10-10 Foundations Complete 09/02/25 09/03/25 3.8 0.0
100%
0.0
RPL10.SUB.EF12.01010 RPL10.SubStructure.EF12 - Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 09/02/25 10/27/25 48.8 0.0
100%
0.0
RPL10.SUB.EF12.01020 RPL10.SubStructure.EF12 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary EF1 & EF2 Complete 09/02/25 11/07/25 61.2 0.0
100%
0.0
RPL10.SUB.NS12.01130 RPL10.SubStructure.NS12 - Piers Protection Concrete Capping Foundations Complete 09/02/25 09/08/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01160 RPL10.SubStructure.NS12 - Install Drilled Piers - Grid lines 10-30/10-20 - After Impact - Part 2 Foundations Complete 09/02/25 09/03/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01180 RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-After Impact - Part 2 Underground Complete 09/02/25 09/23/25 8.8 0.0
100%
0.0
RPL10.SUB.NS12.01200 RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (West)-After Impact - Part 2 Underground Complete 09/02/25 09/17/25 8.8 0.0
100%
0.0
RPL10.SUB.SSB.01000 RPL10.SubStructure.SSB - Install Drilled Piers - Grid lines 10-42/10-30 - After Impact - Part 2 Foundations Complete 09/02/25 09/02/25 5.0 0.0
100%
0.0
RPL10.SUB.SSB.01040 RPL10.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-42/10-30-After Impact-Part 2 Foundations Complete 09/02/25 10/03/25 16.2 0.0
100%
0.0
RPL10.SUB.SSB.01140 RPL10.SubStructure.SSB - Piers Protection Concrete Capping-After Impact - Part 2 Foundations Complete 09/02/25 09/10/25 5.0 0.0
100%
0.0
RPL10.VDC.4240 RPL10.T1 (SSB to Center EF) - BIM Prepare & Submit Shops - Priority 1 Priority 1 - SSB to EF Complete 09/02/25 10/03/25 6.2 0.0
100%
0.0
RPL10.VDC.4260 RPL10.T1 (SSB to Center EF) - BIM Review & Approve Shops - Priority 1 Priority 1 - SSB to EF Complete 09/02/25 10/21/25 8.8 0.0
100%
0.0
RPL10.VDC.4280 RPL10.T1 (SSB to Center EF) - BIM Model/Shops - Priority 1 Final Review (Page Turn) Priority 1 - SSB to EF Complete 09/02/25 10/21/25 18.8 0.0
100%
0.0
RPL10.VDC.4380 RPL10.T1 (Misc. Steel) - BIM Model & Coordination - Priority 3 Priority 3 - Misc Steel Complete 09/02/25 10/03/25 17.5 0.0
100%
0.0
RPL10.VDC.3860 RPL10.T0 (SSB to Center EF) - BIM Model/Shops - Priority 2 Final Review (Page Turn) Priority 2 Priority 2 SSB to Center of EF Complete 09/03/25 09/14/25 11.2 0.0
100%
0.0
RPL10.VDC.4540 RPL10.BIM TIER 2 - 4 - Clash Detection & Finalization TIER 2 - 4 Complete 09/03/25 11/25/25 25.0 0.0
100%
0.0
RPL10.SUB.SSB.01300 RPL10.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill - Before Impact Underground Complete 09/04/25 09/23/25 12.5 0.0
100%
0.0
RPL10.VDC.3820 RPL10.T0 (Center EF to End Corr.) - BIM Review & Approve Shops - Priority 3 Priority 3 Priority 3 Center EF to End Corridor Complete 09/04/25 09/04/25 1.2 0.0
100%
0.0
RPL10.VDC.3880 RPL10.T0 (Center EF to End Corr.) - BIM Model/Shops - Priority 3 Final Review (Page Turn) Priority 3 Priority 3 Center EF to End Corridor Complete 09/05/25 09/14/25 12.5 0.0
100%
0.0
PRE.FA.1080 Steel - Final Agreement Trade Partner Final Agreement Complete 09/08/25 09/08/25 0.0 0.0
100%
0.0
RPL10.CFCI.4490 RPL10 - (SPW - Div 07) Fabricate / Deliver - Below Grade Waterproofing Waterproofing Complete 09/08/25 09/19/25 8.8 0.0
100%
0.0
RPL10.CFCI.4550 RPL10 - Submittal Rvw/App'l - Doors, Frames and Hardware Doors, Frames & Hardware (HM and Wood) Complete 09/08/25 09/26/25 25.0 0.0
100%
0.0
RPL10.CFCI.4580 RPL10 - Prep / Submit for Review - Joint Sealants Joint Sealants Complete 09/08/25 09/16/25 8.8 0.0
100%
0.0
RPL10.CFCI.4590 RPL10- Prep / Submit for Review - Interior Expansion Joints (Spec 07 95 13.13) Building Expansion Joints (Spec 07 95 13.13) Complete 09/08/25 09/16/25 8.8 0.0
100%
0.0
RPL10.VDC.4040 RPL10.T0 (mCUP/Exterior) - BIM Prepare & Submit Shops - Priority 1 Priority 1 mCUP Yard / Exterior Complete 09/08/25 10/10/25 12.5 0.0
100%
0.0
RPL10.VDC.4480 RPL10.BIM TIER 2 - 4 - Submit Shops TIER 2 - 4 Complete 09/10/25 12/01/25 31.2 0.0
100%
0.0
RPL10.SUB.SSB.01030 RPL10.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU Foundations Complete 09/11/25 09/12/25 3.8 0.0
100%
0.0
RPL10.CFCI.3300 RPL10 - Prep / Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) Fixed Louvers Complete 09/12/25 09/22/25 25.0 0.0
100%
0.0
RPL.10.D.X1015.XR Pad Ready (Remaining 25%)- RPL10 (10-09 /10-01) Pad Ready (XREFs) Complete 09/15/25 09/15/25 0.0 0.0
100%
0.0
RPL10.SUB.EF12.01130 RPL10.SubStructure.EF12 - Piers Protection Concrete Capping Foundations Complete 09/15/25 09/26/25 3.8 0.0
100%
0.0
RPL10.SUB.NS43.01000 RPL10.SubStructure.NS43 - Install Drilled Piers - Grid lines 10-10/10-01 Foundations Complete 09/15/25 09/17/25 5.0 0.0
100%
0.0
RPL10.SUB.NS43.01010 RPL10.SubStructure.NS43 - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 09/15/25 11/03/25 45.0 0.0
100%
0.0
RPL10.SUB.NS43.01020 RPL10.SubStructure.NS43 - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary NS4 & NS3 Complete 09/15/25 11/19/25 60.0 0.0
100%
0.0
RPL10.SUB.SSB.01070 RPL10.SubStructure.SSB - Install Stem Walls - Grid lines 10-42/10-30 - Before Impact - Part 1 Foundations Complete 09/15/25 09/23/25 5.0 0.0
100%
0.0
RPL.CM.D.C5250.XR Logistics Area #5B - OES Equipment Yard Available Logistics - Area Turnovers XREF Milestones Complete 09/16/25 09/16/25 0.0 0.0
100%
0.0
RPL10.CFCI.3840 RPL10 - Prep / Submit for Review - Lighting (CFCI) Div. 26 - Lighting Complete 09/16/25 09/17/25 25.0 0.0
100%
0.0
RPL10.CFCI.4840 RPL10 - Submittal Rvw/App'l - Joint Sealants Joint Sealants Complete 09/16/25 09/19/25 25.0 0.0
100%
0.0
RPL10.CFCI.4850 RPL10 - Submittal Rvw/App'l - Interior Expansion Joints (Spec 07 95 13.13) Building Expansion Joints (Spec 07 95 13.13) Complete 09/16/25 09/19/25 12.5 0.0
100%
0.0
RPL10.CFCI.6840 RPL10 - Submittal Rvw/App'l - CRAC Units (CFCI) Div. 23 - CRAH Units Complete 09/16/25 10/13/25 11.2 0.0
100%
0.0
RPL10.CFCI.6900 RPL10 - Submittal Rvw/App'l - CRAH Units (CFCI) Div. 23 - CRAH Units Complete 09/16/25 10/13/25 11.2 0.0
100%
0.0
RPL10.SUB.NS12.01030 RPL10.SubStructure.NS12 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-30/10-20 - Before Impact)-Pt 1 Foundations Complete 09/16/25 09/23/25 13.8 0.0
100%
0.0
RPL10.VDC.4560 RPL10.BIM TIER 2 - 4 - Create Shops TIER 2 - 4 Complete 09/17/25 12/01/25 18.8 0.0
100%
0.0
PRE.FA.1120 Fire Supression - Final Agreement Trade Partner Final Agreement Complete 09/18/25 09/18/25 0.0 0.0
100%
0.0
PRE.FA.1160 Drywall Metal Studs - Final Agreement Trade Partner Final Agreement Complete 09/18/25 09/18/25 0.0 0.0
100%
0.0
PRE.FA.1180 Ceiling - Final Agreement Trade Partner Final Agreement Complete 09/18/25 09/18/25 0.0 0.0
100%
0.0
RPL10.CFCI.4040 RPL10 - Submittal Rvw/App'l - Lighting (CFCI) Div. 26 - Lighting Complete 09/18/25 11/06/25 12.5 0.0
100%
0.0
RPL10.CFCI.6560 RPL10 - Submittal Rvw/App'l - IWP Exterior Metal Panels Complete 09/18/25 10/20/25 12.5 0.0
100%
0.0
RPL10.CFCI.5130 RPL10 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) Building Expansion Joints (Spec 07 95 13.13) Complete 09/22/25 11/24/25 7.5 0.0
100%
0.0
RPL10.SUB.NS43.01130 RPL10.SubStructure.NS43 - Piers Protection Concrete Capping (Before Impact) Foundations Complete 09/22/25 09/23/25 6.2 0.0
100%
0.0
RPL10.CFCI.3810 RPL10 - Submittal Rvw/App'l - Exterior Louvers (w Ext Metal Panel Trade) Fixed Louvers Complete 09/23/25 09/26/25 12.5 0.0
100%
0.0
NW.1960 Weather Event #2 - 09/24/25 - 09/25/25 Project Impacts Complete 09/24/25 09/25/25 5.0 0.0
100%
0.0
RPL10.SUB.SSB.01110 RPL10.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill -After Impact Underground Complete 09/25/25 10/14/25 12.5 0.0
100%
0.0
JCL.C.1040 RPL10 - Cost Risk LOE-3 Earthwork Cost LOEs Active 09/26/25 08/24/26 5.0 117.5
0%
42.5
JCL.C.1060 RPL10 - Cost Risk LOE-4 Rammed Agg Piers Cost LOEs Complete 09/26/25 09/26/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01280 RPL10.SubStructure.NS12 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-30/10-20 - After Impact)-Pt 2 Foundations Complete 09/26/25 10/03/25 13.8 0.0
100%
0.0
RPL10.SUB.NS12.01300 RPL10.SubStructure.NS12 - Install UG Utilities - Building Generator Duct Bank (East)-After Impact - Part 3 Underground Complete 09/26/25 10/06/25 1.2 0.0
100%
0.0
RPL10.SUB.NS43.01230 RPL10.SubStructure.NS43 - Piers Protection Concrete Capping (After Impact) Foundations Complete 09/26/25 10/13/25 6.2 0.0
100%
0.0