Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
87
Completed
13
In Progress
87
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.SUB.SSB.01120 |
RPL10.SubStructure.SSB - Scan, Install Backfill and Grading - Grid lines 10-42/10-30 (1st Layer Backfill) | Underground | Complete | 09/26/25 | 10/14/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01240 |
RPL10.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill-After Impact-Part 2 | Underground | Complete | 09/26/25 | 10/14/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01260 |
RPL10.SubStructure.SSB - Adjust,Scan Install Backfill and Grading - Grid lines 10-42/10-30 (2nd Layer Backfill) | Underground | Complete | 09/26/25 | 10/06/25 | 5.0 | 0.0 |
|
0.0 |
ICM.B10.1830 |
[NWB] Delivery of PTX - Pad Mounted Transformers (First Delivery) | Construction | Complete | 09/29/25 | 09/29/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4120 |
RPL10 - Fabricate / Deliver - Exterior Louvers | Fixed Louvers | Complete | 09/29/25 | 12/11/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.4310 |
RPL10 - Fabricate / Deliver - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 09/29/25 | 09/29/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4770 |
RPL10 - Fabricate / Deliver - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 09/29/25 | 12/19/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.STR.1000 |
RPL10.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | Structure | Complete | 10/01/25 | 04/10/26 | 160.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01000 |
RPL10.Structure.SSB - Install Storm Shelter CMU | Storm Shelter | Complete | 10/01/25 | 10/20/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01010 |
RPL10.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | SSB | Complete | 10/01/25 | 03/06/26 | 130.0 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01030 |
RPL10.SubStructure.EF12 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-20/10-10 | Foundations | Complete | 10/01/25 | 10/13/25 | 13.8 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01280 |
RPL10.SubStructure.SSB - Install Stem Walls - Grid lines 10-42/10-30 - After Impact - Part 2 | Foundations | Complete | 10/02/25 | 10/02/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1060 |
BMS Controls - Final Agreement | Trade Partner Final Agreement | Complete | 10/03/25 | 10/03/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1320 |
Non-Critical Trade Buyout - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 10/06/25 | 11/03/25 | 50.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3370 |
RPL10 - Prep / Submit for Review - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Complete | 10/06/25 | 01/05/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3380 |
RPL10 - Prep / Submit for Review - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 10/06/25 | 10/29/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01070 |
RPL10.SubStructure.EF12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 1 | Underground | Complete | 10/06/25 | 10/14/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01080 |
RPL10.SubStructure.EF12 - Install UG Utilities - WBS Summary | Underground | Complete | 10/06/25 | 11/07/25 | 31.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01040 |
RPL10.SubStructure.NS12 - Install Stem Walls - Grid lines 10-30/10-20 | Foundations | Complete | 10/06/25 | 10/13/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01060 |
RPL10.SubStructure.NS12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 1 | Underground | Complete | 10/06/25 | 10/14/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01080 |
RPL10.SubStructure.SSB - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 10/06/25 | 10/14/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01090 |
RPL10.SubStructure.EF12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part 1 | Underground | Complete | 10/07/25 | 10/13/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01090 |
RPL10.SubStructure.NS12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part1 | Underground | Complete | 10/07/25 | 10/13/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01100 |
RPL10.SubStructure.NS12 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) | Underground | Complete | 10/07/25 | 10/13/25 | 3.8 | 0.0 |
|
0.0 |
RPL.CM.D.C5560.XR |
Republic Road ( 3 TO's , Ist Upto GL 10-20, 2nd 10-01,3rd Mcup | Logistics - Onsite Receive XREF Milestones | Complete | 10/09/25 | 10/09/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01240 |
RPL10.SubStructure.NS12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 2 | Underground | Complete | 10/09/25 | 10/28/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01260 |
RPL10.SubStructure.NS12 - Install UG Utilities - Electrical/Inspection & Tie-ins-Part2 | Underground | Complete | 10/09/25 | 10/13/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01030 |
RPL10.SubStructure.NS43 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-10/10-01 | Foundations | Complete | 10/09/25 | 10/16/25 | 8.8 | 0.0 |
|
0.0 |
RPL.10.D.X1110.XR |
Pad Ready - RPL10 - mCup | Pad Ready (XREFs) | Complete | 10/10/25 | 10/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5580.XR |
Empire Road ( 3 TO's , Ist Upto GL 10-20, 2nd 10-01,3rd Mcup | Logistics - Onsite Receive XREF Milestones | Complete | 10/10/25 | 10/10/25 | 0.0 | 0.0 |
|
0.0 |
PRE.MIR.1200 |
Glass & Metal Panel SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/13/25 | 10/28/25 | 10.0 | 0.0 |
|
0.0 |
PRE.MIR.1220 |
Hot Aisle Containment Install SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/13/25 | 10/27/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.3680 |
RPL10- Submittals - FSC -Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 10/13/25 | 11/17/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3720 |
RPL10 - Submittals - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 10/13/25 | 10/24/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3730 |
RPL10 - Prep / Submit for Review - Gypsum System and Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Complete | 10/13/25 | 10/16/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.CFCI.5210 |
RPL10- Submittal Rvw/App'l - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 10/13/25 | 10/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1000 |
RPL10.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 1 | Active | 10/13/25 | 05/21/26 | 186.2 | 36.2 |
|
485.0 |
RPL10.MCUP.LP1.1040 |
RPL10.MCUP.Loop 1 - Install UG Utilities - WBS Summary | Underground | Complete | 10/13/25 | 11/12/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1060 |
RPL10.MCUP.Loop 1 - Install Mechanical UG | Mechanical UG | Complete | 10/13/25 | 10/29/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1080 |
RPL10.MCUP.Loop 1 - Install Electrical UG | Electrical UG | Complete | 10/13/25 | 11/03/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1140 |
RPL10.MCUP.Loop 1 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Complete | 10/13/25 | 10/29/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1160 |
RPL10.MCUP.Loop 1 - Install Grounding Wire | Grounding UG | Complete | 10/13/25 | 11/12/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2120 |
RPL10.MCUP.Loop 1 - Industrial Water UG (North) | Mechanical UG | Complete | 10/13/25 | 10/17/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2160 |
RPL10.MCUP.Loop 1 - Industrial Water UG (East) | Mechanical UG | Complete | 10/13/25 | 10/17/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2200 |
RPL10.MCUP.Loop 1 - Install Grounding Rod (30 ft depth) | Grounding UG | Complete | 10/13/25 | 11/12/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2240 |
RPL10.MCUP.Loop 1 - Install Generator Conduit Feed - Grid 10-01 to mCup #1,#3,#5,#7 | Electrical UG | Complete | 10/13/25 | 10/28/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1000 |
RPL10.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 2 | Active | 10/13/25 | 06/16/26 | 207.5 | 57.5 |
|
463.8 |
RPL10.MCUP.LP2.1060 |
RPL10.MCUP.Loop 2 - Install UG Utilities - WBS Summary | Underground | Complete | 10/13/25 | 11/24/25 | 37.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1120 |
RPL10.MCUP.Loop 2 - Install Grounding Wire | Grounding UG | Complete | 10/13/25 | 11/12/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2120 |
RPL10.MCUP.Loop 2 - Industrial Water UG (South) | Mechanical UG | Complete | 10/13/25 | 10/17/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2180 |
RPL10.MCUP.Loop 2 - Install Grounding Rod (30 ft depth) | Grounding UG | Complete | 10/13/25 | 11/12/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2200 |
RPL10.MCUP.Loop 2 - Install Exothermic Weld | Grounding UG | Complete | 10/13/25 | 11/12/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01040 |
RPL10.SubStructure.EF12 - Install Stem walls - Grid lines 10-20/10-10 | Foundations | Complete | 10/13/25 | 10/16/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.SSB.01220 |
RPL10.SubStructure.SSB - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside) -After Impact-Part2 | Underground | Complete | 10/13/25 | 10/14/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.VDC.3780 |
RPL10.T0 (mCUP/Exterior) - BIM Review & Approve Shops - Priority 1 | Priority 1 mCUP Yard / Exterior | Complete | 10/13/25 | 10/17/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.mCUP.1060 |
RPL10.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-8 - WBS Summary | mCUP Yard | Active | 10/13/25 | 06/16/26 | 207.5 | 57.5 |
|
463.8 |
RPL.CM.D.C5440.XR |
Logistics Area #4 - DPR Orientation Trailer & Services Available | Logistics - Area Turnovers XREF Milestones | Complete | 10/14/25 | 10/14/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6680 |
RPL10 - Fabricate / Deliver - MDF CU Units (8) | (CFCI) Div. 23 - MDF CU Units | Active | 10/14/25 | 04/23/26 | 67.5 | 11.2 |
|
127.5 |
RPL10.CFCI.6860 |
RPL10 - Fabricate / Deliver - CRAC Units EF - 3&4 EF Corridor Rooms (Inverter Room & IDF) | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 04/30/26 | 67.5 | 17.5 |
|
143.8 |
RPL10.CFCI.6920 |
RPL10 - Fabricate / Deliver - CRAH Units EF2 | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 04/30/26 | 67.5 | 17.5 |
|
136.2 |
RPL10.CFCI.6940 |
RPL10 - Fabricate / Deliver - CRAH Units EF1 | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 04/30/26 | 67.5 | 17.5 |
|
113.8 |
RPL10.CFCI.6960 |
RPL10 - Fabricate / Deliver - CRAC Units NS1 | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 06/17/26 | 67.5 | 58.8 |
|
41.2 |
RPL10.CFCI.6980 |
RPL10 - Fabricate / Deliver - CRAC Units NS2 | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 06/17/26 | 67.5 | 58.8 |
|
47.5 |
RPL10.CFCI.7000 |
RPL10 - Fabricate / Deliver - CRAC Units EF - 3&4 EF Corridor Rooms (UPS Room) | (CFCI) Div. 23 - CRAH Units | Active | 10/14/25 | 04/30/26 | 67.5 | 17.5 |
|
143.8 |
RPL10.SUB.NS12.01050 |
RPL10.SubStructure.NS12 - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 10/14/25 | 10/17/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.VDC.4320 |
RPL10.T1 (Center EF to End Corr.) - BIM Prepare & Submit Shops - Priority 2 | Priority 2 - EF to End Corridor | Complete | 10/14/25 | 10/20/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4400 |
RPL10.T1 (Misc. Steel) - BIM Prepare & Submit Shops - Priority 3 | Priority 3 - Misc Steel | Complete | 10/14/25 | 10/20/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2220 |
RPL10.MCUP.Loop 1 - Install Exothermic Weld | Grounding UG | Complete | 10/15/25 | 11/12/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01110 |
RPL10.SubStructure.EF12 - Scan, Install Backfill and Grading - Grid lines 10-20/10-10 (1st Layer Backfill) | Underground | Complete | 10/15/25 | 10/27/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01110 |
RPL10.SubStructure.NS12 - Scan, Install Backfill and Grading - Grid lines 10-30/10-20 (1st Layer Backfill) | Underground | Complete | 10/15/25 | 10/15/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS12.01220 |
RPL10.SubStructure.NS12 - Adjust,Scan, Install Backfill and Grading - Grid lines 10-30/10-20 (2nd Layer Backfill) | Underground | Complete | 10/15/25 | 10/15/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.4560 |
RPL10 - Submittal Rvw/App'l - Gypsum System and Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Complete | 10/17/25 | 11/03/25 | 25.0 | 0.0 |
|
0.0 |
GCD.RPL10.1360 |
Steel Erection Start - RPL10 | Construction Milestones | Complete | 10/20/25 | 10/20/25 | 0.0 | 0.0 |
|
0.0 |
NW.1340 |
Steel Crane #1 Mobilization | Steel Crane #1 | Complete | 10/20/25 | 10/20/25 | 0.0 | 0.0 |
|
0.0 |
NW.1360 |
Steel Crane #2 Mobilization | Steel Crane #2 | Complete | 10/20/25 | 10/20/25 | 0.0 | 0.0 |
|
0.0 |
NW.1980 |
Weather Event #3 - 10/20/25 - 10/21/25 | Project Impacts | Complete | 10/20/25 | 10/21/25 | 5.0 | 0.0 |
|
0.0 |
PRE.TPA.1300 |
Architectural/Security Fencing - Award and Issue Subcontract OBSOLETE | Obsolete | Complete | 10/20/25 | 11/04/25 | 15.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3390 |
RPL10 - Prep / Submit for Review - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 10/20/25 | 11/11/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4010 |
RPL10 - Submittal Rvw/App'l - Roofing | Roofing | Complete | 10/20/25 | 10/31/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.5040 |
RPL10 - Fabricate / Deliver - Joint Sealants | Joint Sealants | Complete | 10/20/25 | 11/17/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2260 |
RPL10.MCUP.Loop 1 - Industrial Water UG Fill & Testing | Mechanical UG | Complete | 10/20/25 | 11/05/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01050 |
RPL10.SubStructure.EF12 - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 10/20/25 | 10/27/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01040 |
RPL10.SubStructure.NS43 - Install Stem walls - Grid lines 10-10/10-01 ( Before Impact) | Foundations | Complete | 10/20/25 | 10/21/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01060 |
RPL10.SubStructure.NS43 - Install UG Utilities - Plumbing/Testing/Backfill-Part1 | Underground | Complete | 10/20/25 | 10/28/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01070 |
RPL10.SubStructure.NS43 - Install UG Utilities - WBS Summary | Underground | Complete | 10/20/25 | 11/19/25 | 28.8 | 0.0 |
|
0.0 |
RPL10.VDC.3840 |
RPL10.T0 (mCUP/Exterior) - BIM Model/Shops - Priority 1 Final Review (Page Turn) | Priority 1 mCUP Yard / Exterior | Complete | 10/20/25 | 10/30/25 | 11.2 | 0.0 |
|
0.0 |
JCL.C.1100 |
RPL10 - Cost Risk LOE-6 Structure | Cost LOEs | Complete | 10/21/25 | 04/10/26 | 71.2 | 0.0 |
|
0.0 |
RPL10.CFCI.6210 |
RPL10 - SOG Mock-up | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 10/21/25 | 10/24/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.CFCI.6580 |
RPL10 - (DBC) Fabricate / Deliver - IWP | Exterior Metal Panels | Complete | 10/21/25 | 11/14/25 | 15.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01040 |
RPL10.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 10-42/10-30 | Steel and Decking | Complete | 10/21/25 | 11/14/25 | 15.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01050 |
RPL10.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Complete | 10/21/25 | 11/26/25 | 30.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01090 |
RPL10.SubStructure.NS43 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part1 | Underground | Complete | 10/21/25 | 10/27/25 | 7.5 | 0.0 |
|
0.0 |
RPL.CM.D.C5805.XR |
Far Far Away Lane (Around School) | Logistics - Onsite Receive XREF Milestones | Complete | 10/22/25 | 10/22/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01030 |
RPL10.EY.NS1 - Install Foundations, UG Utilities, OFE - WBS Summary | NS1 | Active | 10/22/25 | 10/22/26 | 311.2 | 170.0 |
|
351.2 |
RPL10.EY.NS1.01070 |
RPL10.EY.NS1 - Install UG Utilities - WBS Summary | Underground | Complete | 10/22/25 | 12/19/25 | 68.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01520 |
RPL10.EY.NS1 - Install Electrical UG (Grid 10-32/10-25) | Underground | Complete | 10/22/25 | 10/29/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01030 |
RPL10.EY.NS2 - Install Foundations, UG Utilities, OFE- WBS Summary | NS2 | Active | 10/22/25 | 11/19/26 | 335.0 | 193.8 |
|
327.5 |
RPL10.EY.NS2.01070 |
RPL10.EY.NS2 - Install UG Utilities - WBS Summary | Underground | Complete | 10/22/25 | 01/07/26 | 62.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01520 |
RPL10.EY.NS2 - Install Electrical UG (Grid 10-32\10-25) | Underground | Complete | 10/22/25 | 10/29/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01030 |
RPL10.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary | Electrical Yard (within ring road) | Active | 10/22/25 | 03/02/27 | 418.8 | 277.5 |
|
243.8 |