Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
93
Completed
7
In Progress
93
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.MCUP.LP2.1080 |
RPL10.MCUP.Loop 2 - Install Mechanical UG | Mechanical UG | Complete | 10/22/25 | 11/03/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2160 |
RPL10.MCUP.Loop 2 - Industrial Water UG (West) | Mechanical UG | Complete | 10/22/25 | 11/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01250 |
RPL10.SubStructure.NS43 - Install Stem walls - Grid lines 10-10/10-01 (After Impact) | Foundations | Complete | 10/22/25 | 10/31/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.5340 |
RPL10 - Fabricate / Deliver - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 10/24/25 | 10/24/25 | 1.2 | 0.0 |
|
0.0 |
PRE.MIR.1260 |
Balance of Trades SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/27/25 | 11/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3710 |
RPL10- Prep / Submit for Review - Roofing | Roofing | Complete | 10/27/25 | 10/27/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1140 |
RPL10.MCUP.Loop 2 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Complete | 10/27/25 | 11/03/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01170 |
RPL10.SubStructure.EF12 - Adjust,Scan,Install Backfill and Grading - Grid lines 10-20/10-10 (2nd Layer Backfill) | Underground | Complete | 10/27/25 | 11/04/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01190 |
RPL10.SubStructure.EF12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 2 | Underground | Complete | 10/27/25 | 11/04/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.VDC.4340 |
RPL10.T1 (Center EF to End Corr.) - BIM Review & Approve Shops - Priority 2 | Priority 2 - EF to End Corridor | Complete | 10/27/25 | 11/04/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.VDC.4420 |
RPL10.T1 (Misc. Steel) - BIM Review & Approve Shops - Priority 3 | Priority 3 - Misc Steel | Complete | 10/28/25 | 11/03/25 | 6.2 | 0.0 |
|
0.0 |
PRE.TPA.1240 |
Glass / Metal Panel / Glazing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 10/29/25 | 01/07/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01050 |
RPL10.SubStructure.NS43 - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 10/29/25 | 11/03/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01190 |
RPL10.SubStructure.NS43 - Install UG Utilities - Plumbing/Testing/Backfill-Part2 | Underground | Complete | 10/29/25 | 11/14/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01210 |
RPL10.SubStructure.NS43 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part2 | Underground | Complete | 10/29/25 | 11/18/25 | 7.5 | 0.0 |
|
0.0 |
RPL10.CFCI.3590 |
RPL10 - Submittal Rvw/App'l - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 10/30/25 | 11/25/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01110 |
RPL10.SubStructure.NS43 - Scan, Install Backfill and Grading - Grid lines 10-10/10-01 (1st Layer Backfill) | Underground | Complete | 10/30/25 | 11/03/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01150 |
RPL10.SubStructure.NS43 - Adjust,Scan, Install Backfill and Grading - Grid lines 10-10/10-01 (2nd Layer Backfill) | Underground | Complete | 10/31/25 | 11/07/25 | 5.0 | 0.0 |
|
0.0 |
ICM.B10.1860 |
[NWB] Delivery of Dry Cooling Towers (First Delivery) - RPL10 | Construction | Complete | 11/03/25 | 11/03/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1140 |
Roofing - Final Agreement | Trade Partner Final Agreement | Complete | 11/03/25 | 11/03/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1300 |
Non-Critical Trade Buyout - Final Agreement | Trade Partner Final Agreement | Complete | 11/03/25 | 11/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4300 |
RPL10- Fabricate / Deliver - Roofing | Roofing | Complete | 11/03/25 | 12/05/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01020 |
RPL10.EY.EF1/4 - Install Foundations, UG Utilities, OFE, Fiber Support Platform - WBS Summary | EF 1 | Active | 11/03/25 | 08/25/26 | 250.0 | 118.8 |
|
402.5 |
RPL10.EY.EF1.01060 |
RPL10.EY.EF1 - Install Electrical UG | Underground | Complete | 11/03/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01070 |
RPL10.EY.EF1 - Install UG Utilities - WBS Summary | Underground | Complete | 11/03/25 | 12/22/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01200 |
RPL10.EY.EF1 - Install BMS UG | Underground | Complete | 11/03/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01480 |
RPL10.EY.EF1 - Install Generator Conduit Feed - EY1 Generator to Grid 10-16 | Underground | Complete | 11/03/25 | 11/07/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01000 |
RPL10.EY.EF2 - Install Electrical UG | Underground | Complete | 11/03/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01010 |
RPL10.EY.EF2 - Install UG Utilities - WBS Summary | Underground | Complete | 11/03/25 | 02/16/26 | 40.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01020 |
RPL10.EY.EF2 - Install Foundations, UG Utilities, OFE, FSP - WBS Summary | EF 2 | Active | 11/03/25 | 02/01/27 | 383.8 | 252.5 |
|
268.8 |
RPL10.EY.EF2.01120 |
RPL10.EY.EF2 - Install BMS UG | Underground | Complete | 11/03/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01690 |
RPL10.EY.EF2 - Install Generator Conduit Feed - EY2 Generator to Grid 10-16 | Underground | Complete | 11/03/25 | 11/07/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01030 |
RPL10.EY.NS4 - Install Foundations, UG Utilities, OFE - WBS Summary | NS4 | Active | 11/03/25 | 01/27/27 | 380.0 | 248.8 |
|
272.5 |
RPL10.EY.NS4.01080 |
RPL10.EY.NS4 - Install UG Utilities - WBS Summary | Underground | Complete | 11/03/25 | 11/24/25 | 28.8 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01510 |
RPL10.EY.NS4 - Install Generator Conduit Feed - Grid 10-16 to Grid 10-11 | Underground | Complete | 11/03/25 | 11/07/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1100 |
RPL10.MCUP.Loop 2 - Install Electrical UG | Electrical UG | Complete | 11/03/25 | 11/14/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2220 |
RPL10.MCUP.Loop 2 - Install Generator Conduit Feed - Grid 10-01 to mCup #2,#4,#6,#8 | Electrical UG | Complete | 11/03/25 | 11/18/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2240 |
RPL10.MCUP.Loop 2 - Industrial Water UG Fill & Testing | Mechanical UG | Complete | 11/03/25 | 11/06/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01060 |
RPL10.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 10-42/10-38 | Steel and Decking | Complete | 11/03/25 | 11/12/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01210 |
RPL10.SubStructure.EF12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part 2 | Underground | Complete | 11/03/25 | 11/07/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4360 |
RPL10.T1 (Center EF to End Corr.) - BIM Model/Shops - Priority 2 Final Review (Page Turn) | Priority 2 - EF to End Corridor | Complete | 11/03/25 | 12/08/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.VDC.4440 |
RPL10.T1 (Misc. Steel) - BIM Model/Shops - Priority 3 Final Review (Page Turn) | Priority 3 - Misc Steel | Complete | 11/03/25 | 12/08/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.4130 |
RPL10 - Submittal Rvw/App'l - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 11/04/25 | 11/18/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.4780 |
RPL10- Fabricate / Deliver - Gypsum System and Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Complete | 11/04/25 | 02/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01030 |
RPL10.EY.NS3 - Install Foundations, UG Utilities, OFE - WBS Summary | NS3 | Active | 11/04/25 | 03/02/27 | 407.5 | 277.5 |
|
243.8 |
RPL10.EY.NS3.01060 |
RPL10.EY.NS3 - Install UG Utilities - WBS Summary | Underground | Complete | 11/04/25 | 11/24/25 | 27.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01510 |
RPL10.EY.NS3 - Install Generator Conduit Feed - Grid 10-16 to Grid 10-11 | Underground | Complete | 11/04/25 | 11/10/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01050 |
RPL10.EY.NS3 - Install Electrical UG | Underground | Complete | 11/05/25 | 11/20/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01120 |
RPL10.EY.NS3 - Install BMS UG | Underground | Complete | 11/05/25 | 11/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01070 |
RPL10.EY.NS4 - Install Electrical UG | Underground | Complete | 11/05/25 | 11/20/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01130 |
RPL10.EY.NS4 - Install BMS UG | Underground | Complete | 11/05/25 | 11/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.SUB.EF12.01100 |
RPL10.SubStructure.EF12 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill | Underground | Complete | 11/05/25 | 11/07/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.SUB.NS43.01100 |
RPL10.SubStructure.NS43 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) | Underground | Complete | 11/05/25 | 11/19/25 | 3.8 | 0.0 |
|
0.0 |
GCD.RPL10.1456 |
Start RPL10 EY RMU Equipment Pad Placement - RPL10 | Construction Milestones | Complete | 11/06/25 | 11/06/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01010 |
RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (12'' Larger For Tolerance) (Pre Impact) | Foundations | Complete | 11/06/25 | 11/20/25 | 20.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01020 |
RPL10.EY.NS1 - Install Foundations - WBS Summary | Foundations | Complete | 11/06/25 | 01/23/26 | 77.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01010 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (12'' Larger For Tolerance) (Pre Impact) | Foundations | Complete | 11/06/25 | 11/20/25 | 20.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01020 |
RPL10.EY.NS2 - Install Foundations - WBS Summary | Foundations | Complete | 11/06/25 | 02/21/26 | 75.0 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01530 |
RPL10.EY.NS4 - Install Generator Conduit Feed - Grid 10-10 to Grid 10-01 | Underground | Complete | 11/07/25 | 11/12/25 | 6.2 | 0.0 |
|
0.0 |
ICM.B10.1835 |
[NWB] Delivery of FCM - Fan Coil Module (First Delivery) | Construction | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5470.XR |
Porg Pass | Logistics - Onsite Receive XREF Milestones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5534.XR |
Hoth Street | Logistics - Onsite Receive XREF Milestones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5600.XR |
Tattoonie Street | Logistics - Onsite Receive XREF Milestones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5700.XR |
Burn Road West | Logistics - Onsite Receive XREF Milestones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5880.XR |
Temporary Acces Road to RPL 10 from Bath Plant | Logistics - Onsite Receive XREF Milestones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5660.XR |
Mill and Overlay LA 183 and LA 609 (US80 to I-20) | Logistics - Off-Site Receive XREF Milsetones | Complete | 11/10/25 | 11/10/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5600.XR |
LA 183 /Burn Road - Turn Lane | Logistics - Off-Site Receive XREF Milsetones | Complete | 11/11/25 | 11/11/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5610.XR |
LA 183 /Smalling - Turn Lane | Logistics - Off-Site Receive XREF Milsetones | Complete | 11/11/25 | 11/11/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5700.XR |
Mill and Overlay LA183 (US 80 to Fortenberry) | Logistics - Off-Site Receive XREF Milsetones | Complete | 11/11/25 | 11/11/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4630 |
RPL10 - Prep / Submit for Review - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Complete | 11/11/25 | 11/13/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01190 |
RPL10.EY.EF1 - Install Mechanical UG (Pre WI#04) | Underground | Complete | 11/11/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01110 |
RPL10.EY.EF2 - Install Mechanical UG (Pre WI#04) | Underground | Complete | 11/11/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01530 |
RPL10.EY.NS3 - Install Generator Conduit Feed - Grid 10-10 to Grid 10-01 | Underground | Complete | 11/11/25 | 11/14/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.3600 |
RPL10 - Submittal Rvw/App'l - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 11/12/25 | 12/17/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.CFCI.4750 |
RPL10 - Fabricate / Deliver - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 11/12/25 | 11/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.1000 |
RPL10.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Interior Build-out | Active | 11/12/25 | 02/22/27 | 393.8 | 270.0 |
|
220.0 |
RPL10.INT.SSB.01000 |
RPL10.Interior.SSB - Install Priority Walls and OverHead - WBS Summary | Priority Walls and OverHead | Complete | 11/12/25 | 02/25/26 | 71.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01020 |
RPL10.Interior.SSB - Install Priority OH, Walls, Fitout and Build Back - WBS Summary | SSB | Active | 11/12/25 | 09/17/26 | 262.5 | 138.8 |
|
351.2 |
RPL10.INT.SSB.01040 |
RPL10.Interior.SSB - Priority - Install Temp Lighting (Show In Model) | Priority Walls and OverHead | Complete | 11/12/25 | 11/18/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2260 |
RPL10.MCUP.Loop 1 & 2 - Flowfill Backfill | Mechanical UG | Complete | 11/12/25 | 11/17/25 | 7.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01070 |
RPL10.Structure.SSB - Install Decking & Detailing turnover #2 - Grid lines 10-38/10-36 (Saturday Work) | Steel and Decking | Complete | 11/12/25 | 11/14/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01110 |
RPL10.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Complete | 11/13/25 | 11/24/25 | 10.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01130 |
RPL10.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns | Prep | Complete | 11/13/25 | 11/18/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4890 |
RPL10 - Submittal Rvw/App'l - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Complete | 11/14/25 | 01/09/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01010 |
RPL10.EY.End - Install UG Utilities - WBS Summary | Underground | Complete | 11/14/25 | 11/21/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01020 |
RPL10.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary | End Corridor | Active | 11/14/25 | 06/26/26 | 188.8 | 67.5 |
|
453.8 |
RPL10.EY.ENDC.01050 |
RPL10.EY.End - Install SD, DW, FW UG | Underground | Complete | 11/14/25 | 11/21/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01100 |
RPL10.Structure.SSB - Adjust Drains\Clean Outs\Stubups and Grounding wire | Prep | Complete | 11/14/25 | 11/24/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.4030 |
RPL10 - Submittal Rvw/App'l - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 11/17/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.CFCI.5680 |
RPL10 - Submittals - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Complete | 11/17/25 | 02/23/26 | 21.2 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01300 |
RPL10.EY.EF1 - Install SD UG | Underground | Complete | 11/17/25 | 11/21/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01230 |
RPL10.EY.EF2 - Install SD UG | Underground | Complete | 11/17/25 | 11/21/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01000 |
RPL10.EY.End - Install Electrical UG | Underground | Complete | 11/17/25 | 11/21/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01030 |
RPL10.EY.End - Install Mechanical UG | Underground | Complete | 11/17/25 | 11/21/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01040 |
RPL10.EY.End - Install BMS UG | Underground | Complete | 11/17/25 | 11/21/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01000 |
RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20 (Pre WI#04) | Steel and Decking | Complete | 11/17/25 | 11/24/25 | 10.0 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01010 |
RPL10.Structure.NS12 - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Complete | 11/17/25 | 12/15/25 | 21.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01020 |
RPL10.Structure.NS12 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | NS1 & NS2 | Complete | 11/17/25 | 03/07/26 | 90.0 | 0.0 |
|
0.0 |
NW.1700 |
IMP Crane #1 Movement 01 | IMP Crane #1 | Complete | 11/18/25 | 11/18/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1260 |
Kitchen Equipment - Final Agreement | Trade Partner Final Agreement | Complete | 11/18/25 | 11/18/25 | 0.0 | 0.0 |
|