Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
93
Completed
7
In Progress
93
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.MCUP.LP2.1080 RPL10.MCUP.Loop 2 - Install Mechanical UG Mechanical UG Complete 10/22/25 11/03/25 12.5 0.0
100%
0.0
RPL10.MCUP.LP2.2160 RPL10.MCUP.Loop 2 - Industrial Water UG (West) Mechanical UG Complete 10/22/25 11/03/25 6.2 0.0
100%
0.0
RPL10.SUB.NS43.01250 RPL10.SubStructure.NS43 - Install Stem walls - Grid lines 10-10/10-01 (After Impact) Foundations Complete 10/22/25 10/31/25 8.8 0.0
100%
0.0
RPL10.CFCI.5340 RPL10 - Fabricate / Deliver - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 10/24/25 10/24/25 1.2 0.0
100%
0.0
PRE.MIR.1260 Balance of Trades SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/27/25 11/03/25 0.0 0.0
100%
0.0
RPL10.CFCI.3710 RPL10- Prep / Submit for Review - Roofing Roofing Complete 10/27/25 10/27/25 0.0 0.0
100%
0.0
RPL10.MCUP.LP2.1140 RPL10.MCUP.Loop 2 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Complete 10/27/25 11/03/25 8.8 0.0
100%
0.0
RPL10.SUB.EF12.01170 RPL10.SubStructure.EF12 - Adjust,Scan,Install Backfill and Grading - Grid lines 10-20/10-10 (2nd Layer Backfill) Underground Complete 10/27/25 11/04/25 3.8 0.0
100%
0.0
RPL10.SUB.EF12.01190 RPL10.SubStructure.EF12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 2 Underground Complete 10/27/25 11/04/25 8.8 0.0
100%
0.0
RPL10.VDC.4340 RPL10.T1 (Center EF to End Corr.) - BIM Review & Approve Shops - Priority 2 Priority 2 - EF to End Corridor Complete 10/27/25 11/04/25 8.8 0.0
100%
0.0
RPL10.VDC.4420 RPL10.T1 (Misc. Steel) - BIM Review & Approve Shops - Priority 3 Priority 3 - Misc Steel Complete 10/28/25 11/03/25 6.2 0.0
100%
0.0
PRE.TPA.1240 Glass / Metal Panel / Glazing - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 10/29/25 01/07/26 10.0 0.0
100%
0.0
RPL10.SUB.NS43.01050 RPL10.SubStructure.NS43 - Strip Form Work And Apply Water Proofing System Foundations Complete 10/29/25 11/03/25 5.0 0.0
100%
0.0
RPL10.SUB.NS43.01190 RPL10.SubStructure.NS43 - Install UG Utilities - Plumbing/Testing/Backfill-Part2 Underground Complete 10/29/25 11/14/25 8.8 0.0
100%
0.0
RPL10.SUB.NS43.01210 RPL10.SubStructure.NS43 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part2 Underground Complete 10/29/25 11/18/25 7.5 0.0
100%
0.0
RPL10.CFCI.3590 RPL10 - Submittal Rvw/App'l - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Complete 10/30/25 11/25/25 12.5 0.0
100%
0.0
RPL10.SUB.NS43.01110 RPL10.SubStructure.NS43 - Scan, Install Backfill and Grading - Grid lines 10-10/10-01 (1st Layer Backfill) Underground Complete 10/30/25 11/03/25 5.0 0.0
100%
0.0
RPL10.SUB.NS43.01150 RPL10.SubStructure.NS43 - Adjust,Scan, Install Backfill and Grading - Grid lines 10-10/10-01 (2nd Layer Backfill) Underground Complete 10/31/25 11/07/25 5.0 0.0
100%
0.0
ICM.B10.1860 [NWB] Delivery of Dry Cooling Towers (First Delivery) - RPL10 Construction Complete 11/03/25 11/03/25 0.0 0.0
100%
0.0
PRE.FA.1140 Roofing - Final Agreement Trade Partner Final Agreement Complete 11/03/25 11/03/25 0.0 0.0
100%
0.0
PRE.FA.1300 Non-Critical Trade Buyout - Final Agreement Trade Partner Final Agreement Complete 11/03/25 11/03/25 0.0 0.0
100%
0.0
RPL10.CFCI.4300 RPL10- Fabricate / Deliver - Roofing Roofing Complete 11/03/25 12/05/25 6.2 0.0
100%
0.0
RPL10.EY.EF1.01020 RPL10.EY.EF1/4 - Install Foundations, UG Utilities, OFE, Fiber Support Platform - WBS Summary EF 1 Active 11/03/25 08/25/26 250.0 118.8
0%
402.5
RPL10.EY.EF1.01060 RPL10.EY.EF1 - Install Electrical UG Underground Complete 11/03/25 11/17/25 12.5 0.0
100%
0.0
RPL10.EY.EF1.01070 RPL10.EY.EF1 - Install UG Utilities - WBS Summary Underground Complete 11/03/25 12/22/25 25.0 0.0
100%
0.0
RPL10.EY.EF1.01200 RPL10.EY.EF1 - Install BMS UG Underground Complete 11/03/25 11/17/25 12.5 0.0
100%
0.0
RPL10.EY.EF1.01480 RPL10.EY.EF1 - Install Generator Conduit Feed - EY1 Generator to Grid 10-16 Underground Complete 11/03/25 11/07/25 6.2 0.0
100%
0.0
RPL10.EY.EF2.01000 RPL10.EY.EF2 - Install Electrical UG Underground Complete 11/03/25 11/17/25 12.5 0.0
100%
0.0
RPL10.EY.EF2.01010 RPL10.EY.EF2 - Install UG Utilities - WBS Summary Underground Complete 11/03/25 02/16/26 40.0 0.0
100%
0.0
RPL10.EY.EF2.01020 RPL10.EY.EF2 - Install Foundations, UG Utilities, OFE, FSP - WBS Summary EF 2 Active 11/03/25 02/01/27 383.8 252.5
0%
268.8
RPL10.EY.EF2.01120 RPL10.EY.EF2 - Install BMS UG Underground Complete 11/03/25 11/17/25 12.5 0.0
100%
0.0
RPL10.EY.EF2.01690 RPL10.EY.EF2 - Install Generator Conduit Feed - EY2 Generator to Grid 10-16 Underground Complete 11/03/25 11/07/25 6.2 0.0
100%
0.0
RPL10.EY.NS4.01030 RPL10.EY.NS4 - Install Foundations, UG Utilities, OFE - WBS Summary NS4 Active 11/03/25 01/27/27 380.0 248.8
0%
272.5
RPL10.EY.NS4.01080 RPL10.EY.NS4 - Install UG Utilities - WBS Summary Underground Complete 11/03/25 11/24/25 28.8 0.0
100%
0.0
RPL10.EY.NS4.01510 RPL10.EY.NS4 - Install Generator Conduit Feed - Grid 10-16 to Grid 10-11 Underground Complete 11/03/25 11/07/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1100 RPL10.MCUP.Loop 2 - Install Electrical UG Electrical UG Complete 11/03/25 11/14/25 8.8 0.0
100%
0.0
RPL10.MCUP.LP2.2220 RPL10.MCUP.Loop 2 - Install Generator Conduit Feed - Grid 10-01 to mCup #2,#4,#6,#8 Electrical UG Complete 11/03/25 11/18/25 5.0 0.0
100%
0.0
RPL10.MCUP.LP2.2240 RPL10.MCUP.Loop 2 - Industrial Water UG Fill & Testing Mechanical UG Complete 11/03/25 11/06/25 6.2 0.0
100%
0.0
RPL10.STR.SSB.01060 RPL10.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 10-42/10-38 Steel and Decking Complete 11/03/25 11/12/25 12.5 0.0
100%
0.0
RPL10.SUB.EF12.01210 RPL10.SubStructure.EF12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part 2 Underground Complete 11/03/25 11/07/25 6.2 0.0
100%
0.0
RPL10.VDC.4360 RPL10.T1 (Center EF to End Corr.) - BIM Model/Shops - Priority 2 Final Review (Page Turn) Priority 2 - EF to End Corridor Complete 11/03/25 12/08/25 18.8 0.0
100%
0.0
RPL10.VDC.4440 RPL10.T1 (Misc. Steel) - BIM Model/Shops - Priority 3 Final Review (Page Turn) Priority 3 - Misc Steel Complete 11/03/25 12/08/25 12.5 0.0
100%
0.0
RPL10.CFCI.4130 RPL10 - Submittal Rvw/App'l - Building Controls (CFCI) Div. 23 - Building Controls Complete 11/04/25 11/18/25 12.5 0.0
100%
0.0
RPL10.CFCI.4780 RPL10- Fabricate / Deliver - Gypsum System and Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Complete 11/04/25 02/20/26 0.0 0.0
100%
0.0
RPL10.EY.NS3.01030 RPL10.EY.NS3 - Install Foundations, UG Utilities, OFE - WBS Summary NS3 Active 11/04/25 03/02/27 407.5 277.5
0%
243.8
RPL10.EY.NS3.01060 RPL10.EY.NS3 - Install UG Utilities - WBS Summary Underground Complete 11/04/25 11/24/25 27.5 0.0
100%
0.0
RPL10.EY.NS3.01510 RPL10.EY.NS3 - Install Generator Conduit Feed - Grid 10-16 to Grid 10-11 Underground Complete 11/04/25 11/10/25 6.2 0.0
100%
0.0
RPL10.EY.NS3.01050 RPL10.EY.NS3 - Install Electrical UG Underground Complete 11/05/25 11/20/25 12.5 0.0
100%
0.0
RPL10.EY.NS3.01120 RPL10.EY.NS3 - Install BMS UG Underground Complete 11/05/25 11/19/25 12.5 0.0
100%
0.0
RPL10.EY.NS4.01070 RPL10.EY.NS4 - Install Electrical UG Underground Complete 11/05/25 11/20/25 12.5 0.0
100%
0.0
RPL10.EY.NS4.01130 RPL10.EY.NS4 - Install BMS UG Underground Complete 11/05/25 11/19/25 12.5 0.0
100%
0.0
RPL10.SUB.EF12.01100 RPL10.SubStructure.EF12 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill Underground Complete 11/05/25 11/07/25 3.8 0.0
100%
0.0
RPL10.SUB.NS43.01100 RPL10.SubStructure.NS43 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) Underground Complete 11/05/25 11/19/25 3.8 0.0
100%
0.0
GCD.RPL10.1456 Start RPL10 EY RMU Equipment Pad Placement - RPL10 Construction Milestones Complete 11/06/25 11/06/25 0.0 0.0
100%
0.0
RPL10.EY.NS1.01010 RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (12'' Larger For Tolerance) (Pre Impact) Foundations Complete 11/06/25 11/20/25 20.0 0.0
100%
0.0
RPL10.EY.NS1.01020 RPL10.EY.NS1 - Install Foundations - WBS Summary Foundations Complete 11/06/25 01/23/26 77.5 0.0
100%
0.0
RPL10.EY.NS2.01010 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (12'' Larger For Tolerance) (Pre Impact) Foundations Complete 11/06/25 11/20/25 20.0 0.0
100%
0.0
RPL10.EY.NS2.01020 RPL10.EY.NS2 - Install Foundations - WBS Summary Foundations Complete 11/06/25 02/21/26 75.0 0.0
100%
0.0
RPL10.EY.NS4.01530 RPL10.EY.NS4 - Install Generator Conduit Feed - Grid 10-10 to Grid 10-01 Underground Complete 11/07/25 11/12/25 6.2 0.0
100%
0.0
ICM.B10.1835 [NWB] Delivery of FCM - Fan Coil Module (First Delivery) Construction Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5470.XR Porg Pass Logistics - Onsite Receive XREF Milestones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5534.XR Hoth Street Logistics - Onsite Receive XREF Milestones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5600.XR Tattoonie Street Logistics - Onsite Receive XREF Milestones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5700.XR Burn Road West Logistics - Onsite Receive XREF Milestones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5880.XR Temporary Acces Road to RPL 10 from Bath Plant Logistics - Onsite Receive XREF Milestones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.N5660.XR Mill and Overlay LA 183 and LA 609 (US80 to I-20) Logistics - Off-Site Receive XREF Milsetones Complete 11/10/25 11/10/25 0.0 0.0
100%
0.0
RPL.CM.D.N5600.XR LA 183 /Burn Road - Turn Lane Logistics - Off-Site Receive XREF Milsetones Complete 11/11/25 11/11/25 0.0 0.0
100%
0.0
RPL.CM.D.N5610.XR LA 183 /Smalling - Turn Lane Logistics - Off-Site Receive XREF Milsetones Complete 11/11/25 11/11/25 0.0 0.0
100%
0.0
RPL.CM.D.N5700.XR Mill and Overlay LA183 (US 80 to Fortenberry) Logistics - Off-Site Receive XREF Milsetones Complete 11/11/25 11/11/25 0.0 0.0
100%
0.0
RPL10.CFCI.4630 RPL10 - Prep / Submit for Review - Fire Alarm (CFCI) Div. 26 - Fire Alarm Complete 11/11/25 11/13/25 25.0 0.0
100%
0.0
RPL10.EY.EF1.01190 RPL10.EY.EF1 - Install Mechanical UG (Pre WI#04) Underground Complete 11/11/25 11/24/25 12.5 0.0
100%
0.0
RPL10.EY.EF2.01110 RPL10.EY.EF2 - Install Mechanical UG (Pre WI#04) Underground Complete 11/11/25 11/24/25 12.5 0.0
100%
0.0
RPL10.EY.NS3.01530 RPL10.EY.NS3 - Install Generator Conduit Feed - Grid 10-10 to Grid 10-01 Underground Complete 11/11/25 11/14/25 6.2 0.0
100%
0.0
RPL10.CFCI.3600 RPL10 - Submittal Rvw/App'l - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Complete 11/12/25 12/17/25 18.8 0.0
100%
0.0
RPL10.CFCI.4750 RPL10 - Fabricate / Deliver - Cold Formed Metal Framing (CFCI) Div. 05 - Cold Formed Metal Framing Complete 11/12/25 11/17/25 0.0 0.0
100%
0.0
RPL10.INT.1000 RPL10.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary Interior Build-out Active 11/12/25 02/22/27 393.8 270.0
0%
220.0
RPL10.INT.SSB.01000 RPL10.Interior.SSB - Install Priority Walls and OverHead - WBS Summary Priority Walls and OverHead Complete 11/12/25 02/25/26 71.2 0.0
100%
0.0
RPL10.INT.SSB.01020 RPL10.Interior.SSB - Install Priority OH, Walls, Fitout and Build Back - WBS Summary SSB Active 11/12/25 09/17/26 262.5 138.8
0%
351.2
RPL10.INT.SSB.01040 RPL10.Interior.SSB - Priority - Install Temp Lighting (Show In Model) Priority Walls and OverHead Complete 11/12/25 11/18/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.2260 RPL10.MCUP.Loop 1 & 2 - Flowfill Backfill Mechanical UG Complete 11/12/25 11/17/25 7.5 0.0
100%
0.0
RPL10.STR.SSB.01070 RPL10.Structure.SSB - Install Decking & Detailing turnover #2 - Grid lines 10-38/10-36 (Saturday Work) Steel and Decking Complete 11/12/25 11/14/25 3.8 0.0
100%
0.0
RPL10.STR.SSB.01110 RPL10.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Complete 11/13/25 11/24/25 10.0 0.0
100%
0.0
RPL10.STR.SSB.01130 RPL10.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns Prep Complete 11/13/25 11/18/25 5.0 0.0
100%
0.0
RPL10.CFCI.4890 RPL10 - Submittal Rvw/App'l - Fire Alarm (CFCI) Div. 26 - Fire Alarm Complete 11/14/25 01/09/26 12.5 0.0
100%
0.0
RPL10.EY.ENDC.01010 RPL10.EY.End - Install UG Utilities - WBS Summary Underground Complete 11/14/25 11/21/25 12.5 0.0
100%
0.0
RPL10.EY.ENDC.01020 RPL10.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary End Corridor Active 11/14/25 06/26/26 188.8 67.5
0%
453.8
RPL10.EY.ENDC.01050 RPL10.EY.End - Install SD, DW, FW UG Underground Complete 11/14/25 11/21/25 12.5 0.0
100%
0.0
RPL10.STR.SSB.01100 RPL10.Structure.SSB - Adjust Drains\Clean Outs\Stubups and Grounding wire Prep Complete 11/14/25 11/24/25 6.2 0.0
100%
0.0
RPL10.CFCI.4030 RPL10 - Submittal Rvw/App'l - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Complete 11/17/25 11/24/25 12.5 0.0
100%
0.0
RPL10.CFCI.5680 RPL10 - Submittals - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Complete 11/17/25 02/23/26 21.2 0.0
100%
0.0
RPL10.EY.EF1.01300 RPL10.EY.EF1 - Install SD UG Underground Complete 11/17/25 11/21/25 12.5 0.0
100%
0.0
RPL10.EY.EF2.01230 RPL10.EY.EF2 - Install SD UG Underground Complete 11/17/25 11/21/25 12.5 0.0
100%
0.0
RPL10.EY.ENDC.01000 RPL10.EY.End - Install Electrical UG Underground Complete 11/17/25 11/21/25 6.2 0.0
100%
0.0
RPL10.EY.ENDC.01030 RPL10.EY.End - Install Mechanical UG Underground Complete 11/17/25 11/21/25 6.2 0.0
100%
0.0
RPL10.EY.ENDC.01040 RPL10.EY.End - Install BMS UG Underground Complete 11/17/25 11/21/25 6.2 0.0
100%
0.0
RPL10.STR.NS12.01000 RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20 (Pre WI#04) Steel and Decking Complete 11/17/25 11/24/25 10.0 0.0
100%
0.0
RPL10.STR.NS12.01010 RPL10.Structure.NS12 - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Complete 11/17/25 12/15/25 21.2 0.0
100%
0.0
RPL10.STR.NS12.01020 RPL10.Structure.NS12 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary NS1 & NS2 Complete 11/17/25 03/07/26 90.0 0.0
100%
0.0
NW.1700 IMP Crane #1 Movement 01 IMP Crane #1 Complete 11/18/25 11/18/25 0.0 0.0
100%
0.0
PRE.FA.1260 Kitchen Equipment - Final Agreement Trade Partner Final Agreement Complete 11/18/25 11/18/25 0.0 0.0
100%
0.0