Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
96
Completed
4
In Progress
96
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.CFCI.4540 |
RPL10 - Submittal Rvw/App'l - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 11/18/25 | 12/18/25 | 21.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01090 |
RPL10.EY.NS3 - Install Mechanical UG | Underground | Complete | 11/18/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01100 |
RPL10.EY.NS3 - Install SD, DW, FW UG | Underground | Complete | 11/18/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01100 |
RPL10.EY.NS4 - Install Mechanical UG | Underground | Complete | 11/18/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01110 |
RPL10.EY.NS4 - Install SD, DW, FW UG | Underground | Complete | 11/18/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01000 |
RPL10.Interior.SSB-Corridor - Install Priority Walls and OverHead - WBS Summary | Priority Walls & OverHead | Complete | 11/18/25 | 03/13/26 | 97.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01020 |
RPL10.Interior.SSB-Corridor - Install Priority OH, Walls, Fitout and Build Back - WBS Summary | SSB Corridor | Active | 11/18/25 | 12/09/26 | 328.8 | 208.8 |
|
26.2 |
RPL10.INT.SSBC.01040 |
RPL10.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show in Model) | Priority Walls & OverHead | Complete | 11/18/25 | 11/20/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01080 |
RPL10.Structure.SSB - Install Decking & Detailing turnover #3 - Grid lines 10-36/10-33 | Steel and Decking | Complete | 11/18/25 | 11/21/25 | 3.8 | 0.0 |
|
0.0 |
GCD.RPL10.1380 |
IMP Start - RPL10 | Construction Milestones | Complete | 11/19/25 | 11/19/25 | 0.0 | 0.0 |
|
0.0 |
JCL.C.1140 |
RPL10 - Cost Risk LOE-8 Facade | Cost LOEs | Active | 11/19/25 | 01/27/27 | 5.0 | 248.8 |
|
77.5 |
RPL10.CFCI.4380 |
RPL10 - Fabricate / Deliver - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 11/19/25 | 12/05/25 | 50.0 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01010 |
RPL10.EY.NS3 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) (12'' Larger For Tolerance) - (LOE due to WI) | Foundations | Complete | 11/19/25 | 02/18/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01020 |
RPL10.EY.NS3 - Install Foundations - WBS Summary | Foundations | Complete | 11/19/25 | 02/20/26 | 78.8 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01550 |
RPL10.EY.NS3 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) - (Pre WI#08) | Foundations | Complete | 11/19/25 | 01/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2100 |
RPL10.MCUP.Loop 2 - Install Remaining 4.16kV Electrical Ductbanks | Electrical UG | Complete | 11/19/25 | 11/24/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SKIN.01000 |
RPL10.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary | Skin | Active | 11/19/25 | 01/27/27 | 367.5 | 248.8 |
|
115.0 |
RPL10.SKN.S.01000 |
RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-41/10-42(1) (with temp closures for openings) | South | Complete | 11/19/25 | 11/19/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01010 |
RPL10.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary | South | Complete | 11/19/25 | 03/11/26 | 100.0 | 0.0 |
|
0.0 |
NW.1740 |
IMP Crane #1 Movement 02 | IMP Crane #1 | Complete | 11/20/25 | 11/20/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1020 |
RPL10.MCUP.Loop 1 - Install Foundations - WBS Summary | Foundations | Complete | 11/20/25 | 01/18/26 | 48.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1100 |
RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Pre WI#04) | Foundations | Complete | 11/20/25 | 11/24/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.E.01000 |
RPL10.SKIN.East - Install IMP Flashing,Panels & Caulking - Grid lines 10F/10A(2) (with temp closures for openings) | East | Complete | 11/20/25 | 11/21/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.E.01010 |
RPL10.SKIN.East - Install IMP Insulated Metal Panels System - WBS Summary | East | Complete | 11/20/25 | 02/13/26 | 71.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01120 |
RPL10.Structure.SSB - Install AB final grade and Vapor Barrier | Prep | Complete | 11/20/25 | 11/24/25 | 6.2 | 0.0 |
|
0.0 |
NW.2000 |
111925 - Non Weather Impact #1 - NS1 & NS2 MV Skid Foundation Demolition | Project Impacts | Complete | 11/21/25 | 12/05/25 | 7.5 | 0.0 |
|
0.0 |
RPL10.CFCI.4610 |
RPL10 - Prep / Submit for Review - Interior Painting (Spec 09 91 23) | (CFCI) Div. 09 - Painting | Complete | 11/21/25 | 01/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01090 |
RPL10.Structure.SSB - Install Decking & Detailing turnover #4 - Grid lines 10-33/10-30 | Steel and Decking | Complete | 11/21/25 | 11/26/25 | 2.5 | 0.0 |
|
0.0 |
NW.1780 |
IMP Crane #1 Movement 03 | IMP Crane #1 | Complete | 11/24/25 | 11/24/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5660.XR |
Wayward Path | Logistics - Onsite Receive XREF Milestones | Complete | 11/24/25 | 11/24/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01000 |
RPL10.EY.NS2 - Install Shallow Tent UG (Pre WI#04) | Tent and Temp Conditions | Complete | 11/24/25 | 11/24/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01060 |
RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Pre WI#04) | Underground | Complete | 11/24/25 | 11/24/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01540 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Pre WI#04) | Foundations | Complete | 11/24/25 | 11/24/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01010 |
RPL10.EY.NS4 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) (12'' Larger For Tolerance) - (LOE due to WI) | Foundations | Complete | 11/24/25 | 02/18/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01020 |
RPL10.EY.NS4 - Install Foundations - WBS Summary | Foundations | Complete | 11/24/25 | 02/20/26 | 105.0 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01550 |
RPL10.EY.NS4 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) - (Pre WI#08) | Foundations | Complete | 11/24/25 | 01/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.SKN.N.01000 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Pre WI #04) | North | Complete | 11/24/25 | 11/24/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.N.01010 |
RPL10.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary | North | Complete | 11/24/25 | 02/13/26 | 66.2 | 0.0 |
|
0.0 |
RPL10.VDC.4520 |
RPL10.BIM TIER 2 - 4 - Shops/Model Revise Resubmit | TIER 2 - 4 | Complete | 11/24/25 | 12/12/25 | 18.8 | 0.0 |
|
0.0 |
NW.2020 |
Weather Event #4 - 11/25/25 | Project Impacts | Complete | 11/25/25 | 11/25/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.CFCI.4140 |
RPL10 - Fabricate / Deliver - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 11/25/25 | 02/23/26 | 63.8 | 0.0 |
|
0.0 |
RPL10.CFCI.4190 |
RPL10 - Fabricate / Deliver - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Complete | 11/25/25 | 12/09/25 | 13.8 | 0.0 |
|
0.0 |
GCD.RPL10.1500 |
Start Slab-On-Grade Concrete - RPL10 | Construction Milestones | Complete | 11/26/25 | 11/26/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3900 |
RPL10 - Fabricate / Deliver - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 11/26/25 | 12/05/25 | 11.2 | 0.0 |
|
0.0 |
RPL10.CFCI.6740 |
RPL10 - Prep / Submit for Review -Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Complete | 11/26/25 | 12/02/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01710 |
RPL10.EY.EF2 - Install Mechanical UG (Post WI#04) (Pre WI#08) | Underground | Complete | 11/26/25 | 01/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01000 |
RPL10.EY.NS1 - Install Shallow Tent UG (Pre WI#05) | Tent and Temp Conditions | Complete | 11/26/25 | 11/26/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01540 |
RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (WI#04-Start) (Pre WI#05) | Foundations | Complete | 11/26/25 | 11/26/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01560 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#04) (Pre WI#05) | Foundations | Complete | 11/26/25 | 11/26/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01600 |
RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#04) (Pre WI#05) | Underground | Complete | 11/26/25 | 11/26/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01640 |
RPL10.EY.NS2 - Install Shallow Tent UG (Post WI#04) (Pre WI#05) | Tent and Temp Conditions | Complete | 11/26/25 | 11/26/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01020 |
RPL10.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary | SSB | Active | 11/26/25 | 01/08/27 | 338.8 | 233.8 |
|
287.5 |
RPL10.EY.SSB.01040 |
RPL10.EY.SSB - Install Electrical UG (Pre WI#05) | Underground | Complete | 11/26/25 | 11/26/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01060 |
RPL10.EY.SSB - Install UG Utilities - WBS Summary | Underground | Complete | 11/26/25 | 01/20/26 | 33.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2400 |
RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#04) (Pre WI#05) | Foundations | Complete | 11/26/25 | 11/26/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.N.01160 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #04) (Pre WI#05) | North | Complete | 11/26/25 | 11/26/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01200 |
RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#04) (Pre WI#05) | Steel and Decking | Complete | 11/26/25 | 11/26/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01140 |
RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Trigger Int Wall) (Pre WI#05) | F/R/P | Complete | 11/26/25 | 11/26/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01150 |
RPL10.Structure.SSB - SOG F/R/P - WBS Summary | F/R/P | Complete | 11/26/25 | 03/06/26 | 80.0 | 0.0 |
|
0.0 |
NW.2040 |
Weather Event #5 - 12/01/25 | Project Impacts | Complete | 12/01/25 | 12/01/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01015 |
RPL10.EY.NS3 - Install F/R/P Equipment Pads - 9-16 (Grid 10-09/10-01) (12'' Larger For Tolerance) | Foundations | Complete | 12/01/25 | 12/08/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01500 |
RPL10.EY.EF1 - Install Mechanical UG (Post WI#04) (Pre WI#06) | Underground | Complete | 12/02/25 | 12/03/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01560 |
RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Post WI#05) (Pre WI#06) | Foundations | Complete | 12/02/25 | 12/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01580 |
RPL10.EY.NS1 - Install Shallow Tent UG (Post WI#05) (Pre WI#06) | Tent and Temp Conditions | Complete | 12/02/25 | 12/03/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01620 |
RPL10.EY.NS1 - Install Shallow Tent UG (Post WI#06) | Tent and Temp Conditions | Complete | 12/02/25 | 12/08/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01100 |
RPL10.EY.NS2 - Install Mechanical UG (Pre WI#06) | Underground | Complete | 12/02/25 | 12/03/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01580 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#05) (Pre WI#06) | Foundations | Complete | 12/02/25 | 12/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01620 |
RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#05) (Pre WI#06) | Underground | Complete | 12/02/25 | 12/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01660 |
RPL10.EY.NS2 - Install Shallow Tent UG (Post WI#05) | Tent and Temp Conditions | Complete | 12/02/25 | 12/03/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01380 |
RPL10.EY.SSB - Install Electrical UG (Post WI#05) (Pre WI#06) | Underground | Complete | 12/02/25 | 12/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2420 |
RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#05) (Pre WI#06) | Foundations | Complete | 12/02/25 | 12/03/25 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.N.01180 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #05) (Pre WI#06) | North | Complete | 12/02/25 | 12/03/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01030 |
RPL10.Structure.NS12 - Install Decking & Detailing turnover #5 - Grid lines 10-30/10-27 (WI#05 to Start)(Pre WI#06) | Steel and Decking | Complete | 12/02/25 | 12/03/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01220 |
RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#05) (Pre WI#06) | Steel and Decking | Complete | 12/02/25 | 12/03/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01250 |
RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Post WI#05) (Pre WI#06) | F/R/P | Complete | 12/02/25 | 12/03/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4500 |
RPL10.BIM TIER 2 - 4 - Finalize Model | TIER 2 - 4 | Complete | 12/02/25 | 12/05/25 | 18.8 | 0.0 |
|
0.0 |
RPL10.CFCI.6760 |
RPL10 - Submittal Rvw/App'l - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Complete | 12/03/25 | 12/16/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01015 |
RPL10.EY.NS4 - Install F/R/P Equipment Pads - 9-16 (Grid 10-09/10-01) (12'' Larger For Tolerance) | Foundations | Complete | 12/03/25 | 12/12/25 | 18.8 | 0.0 |
|
0.0 |
NW.2060 |
Weather Event #6 - 12/04/25 | Project Impacts | Complete | 12/04/25 | 12/04/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.CFCI.4320 |
RPL10 - Fabricate / Deliver - Lighting | (CFCI) Div. 26 - Lighting | Complete | 12/05/25 | 02/20/26 | 37.5 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01520 |
RPL10.EY.EF1 - Install Mechanical UG (Post WI#06) | Underground | Complete | 12/05/25 | 12/22/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01600 |
RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Post WI#06) | Foundations | Complete | 12/05/25 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01680 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#06) (Pre WI#07) | Foundations | Complete | 12/05/25 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01700 |
RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#06) | Underground | Complete | 12/05/25 | 12/22/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01720 |
RPL10.EY.NS2 - Install Mechanical UG (Post WI#06) | Underground | Complete | 12/05/25 | 01/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01400 |
RPL10.EY.SSB - Install Electrical UG (Post WI#06) | Underground | Complete | 12/05/25 | 12/16/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2440 |
RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#06) | Foundations | Complete | 12/05/25 | 01/07/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.N.01200 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #06) | North | Complete | 12/05/25 | 12/05/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01240 |
RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#06) | Steel and Decking | Complete | 12/05/25 | 12/05/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01260 |
RPL10.Structure.NS12 - Install Decking & Detailing turnover #5 - Grid lines 10-30/10-27 (Post WI#06) | Steel and Decking | Complete | 12/05/25 | 12/05/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01020 |
RPL10.Structure.SSB - Install Storm Shelter Steel and Decking (WI#05 to Start) | Storm Shelter | Complete | 12/05/25 | 01/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01270 |
RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Post WI#06) | F/R/P | Complete | 12/05/25 | 12/08/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.VDC.4580 |
RPL10.BIM TIER 2 - 4 - Model Completion | TIER 2 - 4 | Complete | 12/05/25 | 12/05/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.VDC.4600 |
RPL10.BIM TIER 2 - 4 - Release & Fabricate | TIER 2 - 4 | Complete | 12/05/25 | 12/05/25 | 1.2 | 0.0 |
|
0.0 |
NW.1820 |
IMP Crane #1 Movement 04 | IMP Crane #1 | Complete | 12/08/25 | 12/08/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1420 |
GMP Approved by Meta Legal | Precon - Budget & Schedule | Complete | 12/08/25 | 12/08/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1480 |
Execution of fGMP | Precon - Budget & Schedule | Complete | 12/08/25 | 12/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5160.XR |
Logistics Area #6 - Complete | Logistics - Area Turnovers XREF Milestones | Complete | 12/08/25 | 12/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.N5615.XR |
LA 183 /Wade - Turn Lane | Logistics - Off-Site Receive XREF Milsetones | Complete | 12/08/25 | 12/08/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01080 |
RPL10.EY.SSB - Install BMS UG | Underground | Complete | 12/08/25 | 12/16/25 | 6.2 | 0.0 |
|
0.0 |