Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
93
Completed
7
In Progress
93
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.SKN.01220 |
RPL10.SKIN - RFI783 - To Provide Bent Plate sizing and Welding Requirements | Expansion Joint Delay Event | Complete | 12/08/25 | 12/09/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01030 |
RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-41/10-30(4) (with temp closures for openings) | South | Complete | 12/08/25 | 12/12/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01000 |
RPL10.Structure.EF12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-20/10-10 | Steel and Decking | Complete | 12/08/25 | 12/24/25 | 11.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01010 |
RPL10.Structure.EF12 - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Complete | 12/08/25 | 01/06/26 | 23.8 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01020 |
RPL10.Structure.EF12 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | EF1 & EF2 | Complete | 12/08/25 | 03/21/26 | 86.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01040 |
RPL10.Structure.NS12 - Install Decking & Detailing turnover #6 - Grid lines 10-27/10-24 | Steel and Decking | Complete | 12/08/25 | 12/10/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01060 |
RPL10.EY.NS1 - Install Electrical UG (Grid 10-42/10-32) | Underground | Complete | 12/09/25 | 12/15/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01090 |
RPL10.EY.NS1 - Install Mechanical UG | Underground | Complete | 12/09/25 | 12/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01100 |
RPL10.EY.NS1 - Install SD, DW, FW UG | Underground | Complete | 12/09/25 | 12/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01120 |
RPL10.EY.NS1 - Install BMS UG | Underground | Complete | 12/09/25 | 12/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01020 |
RPL10.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | SSB | Active | 12/09/25 | 10/16/26 | 267.5 | 165.0 |
|
47.5 |
RPL10.SKN.SSB.01080 |
RPL10.SKIN.SSB - Install Roof System - Exterior Wall Sheething and EJ (See SmartSheet for Seq Div 7 & Roofer) (WI #06) | Roofing | Complete | 12/09/25 | 12/19/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01090 |
RPL10.SKIN.SSB - Install Roof System - WBS Summary | Roofing | Complete | 12/09/25 | 03/13/26 | 62.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01160 |
RPL10.Structure.SSB - SOG F/R/P (Pour #3 -12/09 & #4 -12/11) - Grid lines 10-38/10-36 | F/R/P | Complete | 12/09/25 | 12/16/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.02680 |
RPL10.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) | Priority Walls and OverHead | Complete | 12/10/25 | 01/12/26 | 17.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.02820 |
RPL10.Interior.SSB - Priority - Priority - Frame Priority Soffit and Hang Drywall | Priority Walls and OverHead | Complete | 12/10/25 | 01/07/26 | 17.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01110 |
RPL10.SKIN.SSB - Install Roof System - DenseDeck & Peel & Stick | Roofing | Complete | 12/10/25 | 12/19/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01060 |
RPL10.Structure.NS12 - Adjust Drains\Clean Outs\Stubups and Grounding wire | Prep | Complete | 12/10/25 | 12/18/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01070 |
RPL10.Structure.NS12 - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Complete | 12/10/25 | 01/05/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01050 |
RPL10.Structure.NS12 - Install Decking & Detailing turnover #7 - Grid lines 10-24/10-20 | Steel and Decking | Complete | 12/11/25 | 12/15/25 | 2.5 | 0.0 |
|
0.0 |
JCL.C.1180 |
RPL10 - Cost Risk LOE-10 Fire Protection | Cost LOEs | Active | 12/12/25 | 01/11/27 | 5.0 | 235.0 |
|
80.0 |
RPL10.INT.SSB.01030 |
RPL10.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) | Priority Walls and OverHead | Complete | 12/12/25 | 12/22/25 | 12.5 | 0.0 |
|
0.0 |
JCL.C.1120 |
RPL10 - Cost Risk LOE-7 Interior Fitout | Cost LOEs | Active | 12/15/25 | 01/13/27 | 5.0 | 237.5 |
|
85.0 |
NW.1900 |
IMP Crane #1 Movement 05 | IMP Crane #1 | Complete | 12/15/25 | 12/15/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01670 |
RPL10.EY.EF2 - Install Remaining UG | Underground | Complete | 12/15/25 | 12/19/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01050 |
RPL10.Interior.SSB - Priority - P0 & P1 Frame Wall | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 12/15/25 | 12/22/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1200 |
RPL10.MCUP.Loop 1 - OFE - WBS Summary | OFE | Active | 12/15/25 | 04/15/26 | 55.0 | 3.8 |
|
17.5 |
RPL10.MCUP.LP1.2320 |
RPL10.MCUP.Loop 1 - Set mCUP #1 Facility water piping rack | OFE | Complete | 12/15/25 | 01/06/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01110 |
RPL10.EY.NS2 - Install SD, DW, FW UG | Underground | Complete | 12/16/25 | 01/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01120 |
RPL10.EY.NS2 - Install BMS UG | Underground | Complete | 12/16/25 | 12/22/25 | 12.5 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01030 |
RPL10.Structure.EF12 - Install Decking & Detailing turnover #8 - Grid lines 10-20/10-17 | Steel and Decking | Complete | 12/16/25 | 12/19/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01080 |
RPL10.Structure.NS12 - Install AB final grade and Vapor Barrier | Prep | Complete | 12/16/25 | 01/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01090 |
RPL10.Structure.NS12 - Asphalt Emulsion and Wrap Steel Columns | Prep | Complete | 12/16/25 | 01/05/26 | 3.8 | 0.0 |
|
0.0 |
NW.1920 |
IMP Crane #1 Movement 06 | IMP Crane #1 | Complete | 12/17/25 | 12/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4760 |
RPL10 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 12/17/25 | 12/19/25 | 5.0 | 0.0 |
|
0.0 |
RPL10.CFCI.6780 |
RPL10 - Fabricate / Deliver - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Complete | 12/17/25 | 03/06/26 | 17.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02400 |
RPL10.Interior.SSB-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) | Priority Walls & OverHead | Complete | 12/17/25 | 01/16/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1240 |
RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock(1x GS.IDF) NX11 (12.17.25) | OFE | Complete | 12/17/25 | 12/23/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1300 |
RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock (1x GS.IDF) NX13 (12.17.25) | OFE | Complete | 12/17/25 | 12/23/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01050 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-30/10-20(6) (with temp closures for openings) | North | Complete | 12/17/25 | 12/18/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01170 |
RPL10.Structure.SSB - SOG F/R/P (Pour #5 -12/13 & #6 -12/16) - Grid lines 10-36/10-33 | F/R/P | Complete | 12/17/25 | 12/19/25 | 5.0 | 0.0 |
|
0.0 |
NW.1120 |
Dry Cooler 230 Ton Crane Mobilization | 230 Ton Crane (Dry Cooler) | Complete | 12/18/25 | 12/18/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.3910 |
RPL10 - Fabricate / Deliver - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 12/18/25 | 01/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01000 |
RPL10.EY.EF1 - Install F/R/P Generator Pad | Foundations | Complete | 12/18/25 | 01/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01010 |
RPL10.EY.EF1 - Install Foundations - WBS Summary | Foundations | Complete | 12/18/25 | 02/16/26 | 13.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01040 |
RPL10.EY.EF2 - Install F/R/P Generator Pad | Foundations | Complete | 12/18/25 | 01/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01050 |
RPL10.EY.EF2 - Install Foundations - WBS Summary | Foundations | Complete | 12/18/25 | 03/06/26 | 67.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01030 |
RPL10.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Priority Walls & OverHead | Complete | 12/18/25 | 12/25/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1260 |
RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock (1x GS.IDF) NX12 (01.09.26) | OFE | Complete | 12/18/25 | 12/23/25 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01000 |
RPL10.SKIN.SSB - Install Temp Doors | Glazing, Doors and Ext Devices | Complete | 12/18/25 | 12/26/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01030 |
RPL10.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Active | 12/18/25 | 10/16/26 | 258.8 | 165.0 |
|
47.5 |
NW.1140 |
Dry Cooler 230 Ton Crane Movement 01 - Start | 230 Ton Crane (Dry Cooler) | Complete | 12/19/25 | 12/19/25 | 0.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1220 |
RPL10.MCUP.Loop 1 - Set mCup #1 - Dry Coolers (6) (4 per week) (12.18.25) | OFE | Complete | 12/19/25 | 01/06/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01070 |
RPL10.EY.SSB - Install Mechanical UG | Underground | Complete | 12/22/25 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01130 |
RPL10.EY.SSB - Install SD, DW, FW UG | Underground | Complete | 12/22/25 | 01/07/26 | 13.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01000 |
RPL10.Interior.NS1 - Install Priority - WBS Summary | OverHead | Complete | 12/22/25 | 03/16/26 | 72.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01020 |
RPL10.Interior.NS1 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | NS1 | Active | 12/22/25 | 09/11/26 | 225.0 | 133.8 |
|
107.5 |
RPL10.INT.NS1.01040 |
RPL10.Interior.NS1 - Priority - Install Temp Lighting | OverHead | Complete | 12/22/25 | 12/24/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01000 |
RPL10.Interior.NS2 - Priority - WBS Summary | OverHead | Complete | 12/22/25 | 03/16/26 | 72.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01020 |
RPL10.Interior.NS2 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | NS2 | Active | 12/22/25 | 10/21/26 | 260.0 | 168.8 |
|
83.8 |
RPL10.INT.NS2.01040 |
RPL10.Interior.NS2 - Priority - Install Temp Lighting | OverHead | Complete | 12/22/25 | 12/24/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01010 |
RPL10.Interior.SSB - Priority - Install Duct (Highside OH space) - (LOE due to WI) | Priority Walls and OverHead | Complete | 12/22/25 | 02/04/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03440 |
RPL10.Interior.SSB - Priority - P0 & P1 Install MEP In-Wall & Backing | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 12/22/25 | 01/20/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06820 |
RPL10.Interior.SSB - Priority - Install Duct (Highside OH space) - (Pre WI#08) | Priority Walls and OverHead | Complete | 12/22/25 | 01/23/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03540 |
RPL10.Interior.SSB-Corridor - Priority - Install Framing Priority Soffit (All Soffit) | Priority Walls & OverHead | Complete | 12/22/25 | 01/08/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2340 |
RPL10.MCUP.Loop 1 - Set mCup #3 Facility water piping rack | OFE | Complete | 12/22/25 | 01/08/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1020 |
RPL10.MCUP.Loop 2 - Install Foundations - WBS Summary | Foundations | Complete | 12/22/25 | 03/04/26 | 42.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1160 |
RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) - (LOE due to WI) | Foundations | Complete | 12/22/25 | 02/27/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2460 |
RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Pre WI#07) | Foundations | Complete | 12/22/25 | 01/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01190 |
RPL10.SKIN.SSB - PSI META /Epstien Identified Work Deficient | Roofing Remediation 10-42 / 10-30 | Complete | 12/22/25 | 12/22/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01210 |
RPL10.SKIN.SSB - PSI DPR Notified Flynn to proceed Remediation Work | Roofing Remediation 10-42 / 10-30 | Complete | 12/22/25 | 12/22/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01230 |
RPL10.SKIN.SSB - PSI RFI# to Utilize the 5/8th board in Lieu of 1/2in board | Roofing Remediation 10-42 / 10-30 | Complete | 12/22/25 | 12/22/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01040 |
RPL10.Structure.EF12 - Install Decking & Detailing turnover #9 - Grid lines 10-17/10-14 | Steel and Decking | Complete | 12/22/25 | 12/31/25 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01180 |
RPL10.Structure.SSB - SOG F/R/P (Pour #7 -12/18) - Grid lines 10-33/10-30 | F/R/P | Complete | 12/22/25 | 12/23/25 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03200 |
RPL10.Interior.SSB - Priority - Install Backing and In-Wall Exterior Wall | Priority Walls and OverHead | Complete | 12/23/25 | 01/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03340 |
RPL10.Interior.SSB - Priority - Install IMP Exterior In-Wall Rough-Ins | Priority Walls and OverHead | Complete | 12/23/25 | 01/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2280 |
RPL10.MCUP.Loop 1 - Set mCup #3 - Dry Coolers (6) (4 per week) | OFE | Complete | 12/23/25 | 01/07/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2360 |
RPL10.MCUP.Loop 1 - Set mCup #5 Facility water piping rack | OFE | Complete | 12/23/25 | 01/12/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.01240 |
RPL10.SKIN - RFI840 - Shift the Bent Plate Horontally due to Bowing Joist | Expansion Joint Delay Event | Complete | 12/23/25 | 12/30/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01250 |
RPL10.SKIN.SSB - PSI Flynn Elects to hold off on remediation work for manufacture | Roofing Remediation 10-42 / 10-30 | Complete | 12/23/25 | 12/23/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01190 |
RPL10.Structure.SSB - Zone SOG Cure | F/R/P | Complete | 12/24/25 | 12/30/25 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.02840 |
RPL10.Interior.SSB - Priority - Tape, Float and Paint Priority Soffit, Fire Safing (Top Out) | Priority Walls and OverHead | Complete | 12/29/25 | 01/09/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01270 |
RPL10.SKIN.SSB - PSI Flynn & Suprema (manufacturer) walk the Deficient work | Roofing Remediation 10-42 / 10-30 | Complete | 12/29/25 | 12/29/25 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01100 |
RPL10.Structure.NS12 - SOG F/R/P (Pour #8 -12/20 & 9 -12/23) - Grid lines 10-30/10-27 | F/R/P | Complete | 12/29/25 | 01/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01110 |
RPL10.Structure.NS12 - SOG F/R/P - Grid Lines 10-30/10-20 - WBS Summary | F/R/P | Complete | 12/29/25 | 03/07/26 | 57.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01000 |
RPL10.Structure.NS43 - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 10-10/10-01 | Steel and Decking | Complete | 12/29/25 | 01/14/26 | 11.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01010 |
RPL10.Structure.NS43 - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Complete | 12/29/25 | 01/23/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01020 |
RPL10.Structure.NS43 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | NS4 & NS3 | Complete | 12/29/25 | 04/10/26 | 87.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01310 |
RPL10.SKIN.SSB - PSI DPR Sends Letter for Quality Deficiency / Request for Recovery Schedule | Roofing Remediation 10-42 / 10-30 | Complete | 12/30/25 | 01/06/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.01260 |
RPL10.SKIN - Gusset Procurement After RFI840 Approval - Expected Delivery | Expansion Joint Delay Event | Complete | 12/31/25 | 01/15/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01050 |
RPL10.Structure.EF12 - Install Decking & Detailing turnover #10 - Grid lines 10-14/10-10 | Steel and Decking | Complete | 01/02/26 | 01/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.CFCI.3580 |
RPL10 - Submittal Rvw/App'l - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Complete | 01/05/26 | 01/15/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01070 |
RPL10.Interior.NS1 - Priority - Install IMP Exterior In-Wall Rough-Ins - (LOE due to WI) | OverHead | Complete | 01/05/26 | 02/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02960 |
RPL10.Interior.NS1 - Priority - Install Backing Exterior Wall - (LOE due to WI) | OverHead | Complete | 01/05/26 | 02/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02980 |
RPL10.Interior.NS1 - Priority - Install Backing Exterior Wall - (Pre WI#08) | OverHead | Complete | 01/05/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.03060 |
RPL10.Interior.NS1 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Pre WI#08) | OverHead | Complete | 01/05/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02300 |
RPL10.Interior.NS2 - Priority - Install IMP Exterior In-Wall Rough-Ins - (LOE due to WI) | OverHead | Complete | 01/05/26 | 02/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.03045 |
RPL10.Interior.NS2 - Priority - Install Backing Exterior Wall - (LOE due to WI) | OverHead | Complete | 01/05/26 | 02/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.03065 |
RPL10.Interior.NS2 - Priority - Install Backing Exterior Wall - (Pre WI#08) | OverHead | Complete | 01/05/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.03185 |
RPL10.Interior.NS2 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Pre WI#08) | OverHead | Complete | 01/05/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |