Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
93
Completed
7
In Progress
93
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SKN.01220 RPL10.SKIN - RFI783 - To Provide Bent Plate sizing and Welding Requirements Expansion Joint Delay Event Complete 12/08/25 12/09/25 1.2 0.0
100%
0.0
RPL10.SKN.S.01030 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-41/10-30(4) (with temp closures for openings) South Complete 12/08/25 12/12/25 2.5 0.0
100%
0.0
RPL10.STR.EF12.01000 RPL10.Structure.EF12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-20/10-10 Steel and Decking Complete 12/08/25 12/24/25 11.2 0.0
100%
0.0
RPL10.STR.EF12.01010 RPL10.Structure.EF12 - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Complete 12/08/25 01/06/26 23.8 0.0
100%
0.0
RPL10.STR.EF12.01020 RPL10.Structure.EF12 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary EF1 & EF2 Complete 12/08/25 03/21/26 86.2 0.0
100%
0.0
RPL10.STR.NS12.01040 RPL10.Structure.NS12 - Install Decking & Detailing turnover #6 - Grid lines 10-27/10-24 Steel and Decking Complete 12/08/25 12/10/25 2.5 0.0
100%
0.0
RPL10.EY.NS1.01060 RPL10.EY.NS1 - Install Electrical UG (Grid 10-42/10-32) Underground Complete 12/09/25 12/15/25 6.2 0.0
100%
0.0
RPL10.EY.NS1.01090 RPL10.EY.NS1 - Install Mechanical UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.EY.NS1.01100 RPL10.EY.NS1 - Install SD, DW, FW UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.EY.NS1.01120 RPL10.EY.NS1 - Install BMS UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.SKN.SSB.01020 RPL10.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary SSB Active 12/09/25 10/16/26 267.5 165.0
0%
47.5
RPL10.SKN.SSB.01080 RPL10.SKIN.SSB - Install Roof System - Exterior Wall Sheething and EJ (See SmartSheet for Seq Div 7 & Roofer) (WI #06) Roofing Complete 12/09/25 12/19/25 5.0 0.0
100%
0.0
RPL10.SKN.SSB.01090 RPL10.SKIN.SSB - Install Roof System - WBS Summary Roofing Complete 12/09/25 03/13/26 62.5 0.0
100%
0.0
RPL10.STR.SSB.01160 RPL10.Structure.SSB - SOG F/R/P (Pour #3 -12/09 & #4 -12/11) - Grid lines 10-38/10-36 F/R/P Complete 12/09/25 12/16/25 6.2 0.0
100%
0.0
RPL10.INT.SSB.02680 RPL10.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls and OverHead Complete 12/10/25 01/12/26 17.5 0.0
100%
0.0
RPL10.INT.SSB.02820 RPL10.Interior.SSB - Priority - Priority - Frame Priority Soffit and Hang Drywall Priority Walls and OverHead Complete 12/10/25 01/07/26 17.5 0.0
100%
0.0
RPL10.SKN.SSB.01110 RPL10.SKIN.SSB - Install Roof System - DenseDeck & Peel & Stick Roofing Complete 12/10/25 12/19/25 6.2 0.0
100%
0.0
RPL10.STR.NS12.01060 RPL10.Structure.NS12 - Adjust Drains\Clean Outs\Stubups and Grounding wire Prep Complete 12/10/25 12/18/25 6.2 0.0
100%
0.0
RPL10.STR.NS12.01070 RPL10.Structure.NS12 - Install Remaining UG and Subgrade Prep - WBS Summary Prep Complete 12/10/25 01/05/26 12.5 0.0
100%
0.0
RPL10.STR.NS12.01050 RPL10.Structure.NS12 - Install Decking & Detailing turnover #7 - Grid lines 10-24/10-20 Steel and Decking Complete 12/11/25 12/15/25 2.5 0.0
100%
0.0
JCL.C.1180 RPL10 - Cost Risk LOE-10 Fire Protection Cost LOEs Active 12/12/25 01/11/27 5.0 235.0
0%
80.0
RPL10.INT.SSB.01030 RPL10.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) Priority Walls and OverHead Complete 12/12/25 12/22/25 12.5 0.0
100%
0.0
JCL.C.1120 RPL10 - Cost Risk LOE-7 Interior Fitout Cost LOEs Active 12/15/25 01/13/27 5.0 237.5
0%
85.0
NW.1900 IMP Crane #1 Movement 05 IMP Crane #1 Complete 12/15/25 12/15/25 0.0 0.0
100%
0.0
RPL10.EY.EF2.01670 RPL10.EY.EF2 - Install Remaining UG Underground Complete 12/15/25 12/19/25 6.2 0.0
100%
0.0
RPL10.INT.SSB.01050 RPL10.Interior.SSB - Priority - P0 & P1 Frame Wall Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 12/15/25 12/22/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1200 RPL10.MCUP.Loop 1 - OFE - WBS Summary OFE Active 12/15/25 04/15/26 55.0 3.8
0%
17.5
RPL10.MCUP.LP1.2320 RPL10.MCUP.Loop 1 - Set mCUP #1 Facility water piping rack OFE Complete 12/15/25 01/06/26 15.0 0.0
100%
0.0
RPL10.EY.NS2.01110 RPL10.EY.NS2 - Install SD, DW, FW UG Underground Complete 12/16/25 01/07/26 12.5 0.0
100%
0.0
RPL10.EY.NS2.01120 RPL10.EY.NS2 - Install BMS UG Underground Complete 12/16/25 12/22/25 12.5 0.0
100%
0.0
RPL10.STR.EF12.01030 RPL10.Structure.EF12 - Install Decking & Detailing turnover #8 - Grid lines 10-20/10-17 Steel and Decking Complete 12/16/25 12/19/25 3.8 0.0
100%
0.0
RPL10.STR.NS12.01080 RPL10.Structure.NS12 - Install AB final grade and Vapor Barrier Prep Complete 12/16/25 01/05/26 6.2 0.0
100%
0.0
RPL10.STR.NS12.01090 RPL10.Structure.NS12 - Asphalt Emulsion and Wrap Steel Columns Prep Complete 12/16/25 01/05/26 3.8 0.0
100%
0.0
NW.1920 IMP Crane #1 Movement 06 IMP Crane #1 Complete 12/17/25 12/17/25 0.0 0.0
100%
0.0
RPL10.CFCI.4760 RPL10 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Complete 12/17/25 12/19/25 5.0 0.0
100%
0.0
RPL10.CFCI.6780 RPL10 - Fabricate / Deliver - Cable Tray (CFCI) Div. 26 - Power Equip. & Material Complete 12/17/25 03/06/26 17.5 0.0
100%
0.0
RPL10.INT.SSBC.02400 RPL10.Interior.SSB-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls & OverHead Complete 12/17/25 01/16/26 12.5 0.0
100%
0.0
RPL10.MCUP.LP1.1240 RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock(1x GS.IDF) NX11 (12.17.25) OFE Complete 12/17/25 12/23/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1300 RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock (1x GS.IDF) NX13 (12.17.25) OFE Complete 12/17/25 12/23/25 6.2 0.0
100%
0.0
RPL10.SKN.N.01050 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-30/10-20(6) (with temp closures for openings) North Complete 12/17/25 12/18/25 2.5 0.0
100%
0.0
RPL10.STR.SSB.01170 RPL10.Structure.SSB - SOG F/R/P (Pour #5 -12/13 & #6 -12/16) - Grid lines 10-36/10-33 F/R/P Complete 12/17/25 12/19/25 5.0 0.0
100%
0.0
NW.1120 Dry Cooler 230 Ton Crane Mobilization 230 Ton Crane (Dry Cooler) Complete 12/18/25 12/18/25 0.0 0.0
100%
0.0
RPL10.CFCI.3910 RPL10 - Fabricate / Deliver - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Complete 12/18/25 01/05/26 6.2 0.0
100%
0.0
RPL10.EY.EF1.01000 RPL10.EY.EF1 - Install F/R/P Generator Pad Foundations Complete 12/18/25 01/07/26 6.2 0.0
100%
0.0
RPL10.EY.EF1.01010 RPL10.EY.EF1 - Install Foundations - WBS Summary Foundations Complete 12/18/25 02/16/26 13.8 0.0
100%
0.0
RPL10.EY.EF2.01040 RPL10.EY.EF2 - Install F/R/P Generator Pad Foundations Complete 12/18/25 01/07/26 6.2 0.0
100%
0.0
RPL10.EY.EF2.01050 RPL10.EY.EF2 - Install Foundations - WBS Summary Foundations Complete 12/18/25 03/06/26 67.5 0.0
100%
0.0
RPL10.INT.SSBC.01030 RPL10.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Priority Walls & OverHead Complete 12/18/25 12/25/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1260 RPL10.MCUP.Loop 1 - Set GS.IDF Hut, Climate Control, Grounded, & Lock (1x GS.IDF) NX12 (01.09.26) OFE Complete 12/18/25 12/23/25 6.2 0.0
100%
0.0
RPL10.SKN.SSB.01000 RPL10.SKIN.SSB - Install Temp Doors Glazing, Doors and Ext Devices Complete 12/18/25 12/26/25 2.5 0.0
100%
0.0
RPL10.SKN.SSB.01030 RPL10.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Active 12/18/25 10/16/26 258.8 165.0
0%
47.5
NW.1140 Dry Cooler 230 Ton Crane Movement 01 - Start 230 Ton Crane (Dry Cooler) Complete 12/19/25 12/19/25 0.0 0.0
100%
0.0
RPL10.MCUP.LP1.1220 RPL10.MCUP.Loop 1 - Set mCup #1 - Dry Coolers (6) (4 per week) (12.18.25) OFE Complete 12/19/25 01/06/26 10.0 0.0
100%
0.0
RPL10.EY.SSB.01070 RPL10.EY.SSB - Install Mechanical UG Underground Complete 12/22/25 01/20/26 6.2 0.0
100%
0.0
RPL10.EY.SSB.01130 RPL10.EY.SSB - Install SD, DW, FW UG Underground Complete 12/22/25 01/07/26 13.8 0.0
100%
0.0
RPL10.INT.NS1.01000 RPL10.Interior.NS1 - Install Priority - WBS Summary OverHead Complete 12/22/25 03/16/26 72.5 0.0
100%
0.0
RPL10.INT.NS1.01020 RPL10.Interior.NS1 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS1 Active 12/22/25 09/11/26 225.0 133.8
0%
107.5
RPL10.INT.NS1.01040 RPL10.Interior.NS1 - Priority - Install Temp Lighting OverHead Complete 12/22/25 12/24/25 3.8 0.0
100%
0.0
RPL10.INT.NS2.01000 RPL10.Interior.NS2 - Priority - WBS Summary OverHead Complete 12/22/25 03/16/26 72.5 0.0
100%
0.0
RPL10.INT.NS2.01020 RPL10.Interior.NS2 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS2 Active 12/22/25 10/21/26 260.0 168.8
0%
83.8
RPL10.INT.NS2.01040 RPL10.Interior.NS2 - Priority - Install Temp Lighting OverHead Complete 12/22/25 12/24/25 3.8 0.0
100%
0.0
RPL10.INT.SSB.01010 RPL10.Interior.SSB - Priority - Install Duct (Highside OH space) - (LOE due to WI) Priority Walls and OverHead Complete 12/22/25 02/04/26 7.5 0.0
100%
0.0
RPL10.INT.SSB.03440 RPL10.Interior.SSB - Priority - P0 & P1 Install MEP In-Wall & Backing Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 12/22/25 01/20/26 2.5 0.0
100%
0.0
RPL10.INT.SSB.06820 RPL10.Interior.SSB - Priority - Install Duct (Highside OH space) - (Pre WI#08) Priority Walls and OverHead Complete 12/22/25 01/23/26 7.5 0.0
100%
0.0
RPL10.INT.SSBC.03540 RPL10.Interior.SSB-Corridor - Priority - Install Framing Priority Soffit (All Soffit) Priority Walls & OverHead Complete 12/22/25 01/08/26 12.5 0.0
100%
0.0
RPL10.MCUP.LP1.2340 RPL10.MCUP.Loop 1 - Set mCup #3 Facility water piping rack OFE Complete 12/22/25 01/08/26 15.0 0.0
100%
0.0
RPL10.MCUP.LP2.1020 RPL10.MCUP.Loop 2 - Install Foundations - WBS Summary Foundations Complete 12/22/25 03/04/26 42.5 0.0
100%
0.0
RPL10.MCUP.LP2.1160 RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) - (LOE due to WI) Foundations Complete 12/22/25 02/27/26 25.0 0.0
100%
0.0
RPL10.MCUP.LP2.2460 RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Pre WI#07) Foundations Complete 12/22/25 01/20/26 25.0 0.0
100%
0.0
RPL10.SKN.SSB.01190 RPL10.SKIN.SSB - PSI META /Epstien Identified Work Deficient Roofing Remediation 10-42 / 10-30 Complete 12/22/25 12/22/25 1.2 0.0
100%
0.0
RPL10.SKN.SSB.01210 RPL10.SKIN.SSB - PSI DPR Notified Flynn to proceed Remediation Work Roofing Remediation 10-42 / 10-30 Complete 12/22/25 12/22/25 1.2 0.0
100%
0.0
RPL10.SKN.SSB.01230 RPL10.SKIN.SSB - PSI RFI# to Utilize the 5/8th board in Lieu of 1/2in board Roofing Remediation 10-42 / 10-30 Complete 12/22/25 12/22/25 1.2 0.0
100%
0.0
RPL10.STR.EF12.01040 RPL10.Structure.EF12 - Install Decking & Detailing turnover #9 - Grid lines 10-17/10-14 Steel and Decking Complete 12/22/25 12/31/25 3.8 0.0
100%
0.0
RPL10.STR.SSB.01180 RPL10.Structure.SSB - SOG F/R/P (Pour #7 -12/18) - Grid lines 10-33/10-30 F/R/P Complete 12/22/25 12/23/25 2.5 0.0
100%
0.0
RPL10.INT.SSB.03200 RPL10.Interior.SSB - Priority - Install Backing and In-Wall Exterior Wall Priority Walls and OverHead Complete 12/23/25 01/06/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.03340 RPL10.Interior.SSB - Priority - Install IMP Exterior In-Wall Rough-Ins Priority Walls and OverHead Complete 12/23/25 01/07/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2280 RPL10.MCUP.Loop 1 - Set mCup #3 - Dry Coolers (6) (4 per week) OFE Complete 12/23/25 01/07/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.2360 RPL10.MCUP.Loop 1 - Set mCup #5 Facility water piping rack OFE Complete 12/23/25 01/12/26 12.5 0.0
100%
0.0
RPL10.SKN.01240 RPL10.SKIN - RFI840 - Shift the Bent Plate Horontally due to Bowing Joist Expansion Joint Delay Event Complete 12/23/25 12/30/25 1.2 0.0
100%
0.0
RPL10.SKN.SSB.01250 RPL10.SKIN.SSB - PSI Flynn Elects to hold off on remediation work for manufacture Roofing Remediation 10-42 / 10-30 Complete 12/23/25 12/23/25 1.2 0.0
100%
0.0
RPL10.STR.SSB.01190 RPL10.Structure.SSB - Zone SOG Cure F/R/P Complete 12/24/25 12/30/25 8.8 0.0
100%
0.0
RPL10.INT.SSB.02840 RPL10.Interior.SSB - Priority - Tape, Float and Paint Priority Soffit, Fire Safing (Top Out) Priority Walls and OverHead Complete 12/29/25 01/09/26 12.5 0.0
100%
0.0
RPL10.SKN.SSB.01270 RPL10.SKIN.SSB - PSI Flynn & Suprema (manufacturer) walk the Deficient work Roofing Remediation 10-42 / 10-30 Complete 12/29/25 12/29/25 1.2 0.0
100%
0.0
RPL10.STR.NS12.01100 RPL10.Structure.NS12 - SOG F/R/P (Pour #8 -12/20 & 9 -12/23) - Grid lines 10-30/10-27 F/R/P Complete 12/29/25 01/06/26 6.2 0.0
100%
0.0
RPL10.STR.NS12.01110 RPL10.Structure.NS12 - SOG F/R/P - Grid Lines 10-30/10-20 - WBS Summary F/R/P Complete 12/29/25 03/07/26 57.5 0.0
100%
0.0
RPL10.STR.NS43.01000 RPL10.Structure.NS43 - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 10-10/10-01 Steel and Decking Complete 12/29/25 01/14/26 11.2 0.0
100%
0.0
RPL10.STR.NS43.01010 RPL10.Structure.NS43 - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Complete 12/29/25 01/23/26 22.5 0.0
100%
0.0
RPL10.STR.NS43.01020 RPL10.Structure.NS43 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary NS4 & NS3 Complete 12/29/25 04/10/26 87.5 0.0
100%
0.0
RPL10.SKN.SSB.01310 RPL10.SKIN.SSB - PSI DPR Sends Letter for Quality Deficiency / Request for Recovery Schedule Roofing Remediation 10-42 / 10-30 Complete 12/30/25 01/06/26 1.2 0.0
100%
0.0
RPL10.SKN.01260 RPL10.SKIN - Gusset Procurement After RFI840 Approval - Expected Delivery Expansion Joint Delay Event Complete 12/31/25 01/15/26 1.2 0.0
100%
0.0
RPL10.STR.EF12.01050 RPL10.Structure.EF12 - Install Decking & Detailing turnover #10 - Grid lines 10-14/10-10 Steel and Decking Complete 01/02/26 01/06/26 3.8 0.0
100%
0.0
RPL10.CFCI.3580 RPL10 - Submittal Rvw/App'l - Plumbing (OH / In Wall) (CFCI) Div. 22 - Plumbing Complete 01/05/26 01/15/26 25.0 0.0
100%
0.0
RPL10.INT.NS1.01070 RPL10.Interior.NS1 - Priority - Install IMP Exterior In-Wall Rough-Ins - (LOE due to WI) OverHead Complete 01/05/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02960 RPL10.Interior.NS1 - Priority - Install Backing Exterior Wall - (LOE due to WI) OverHead Complete 01/05/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02980 RPL10.Interior.NS1 - Priority - Install Backing Exterior Wall - (Pre WI#08) OverHead Complete 01/05/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.03060 RPL10.Interior.NS1 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Pre WI#08) OverHead Complete 01/05/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02300 RPL10.Interior.NS2 - Priority - Install IMP Exterior In-Wall Rough-Ins - (LOE due to WI) OverHead Complete 01/05/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03045 RPL10.Interior.NS2 - Priority - Install Backing Exterior Wall - (LOE due to WI) OverHead Complete 01/05/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03065 RPL10.Interior.NS2 - Priority - Install Backing Exterior Wall - (Pre WI#08) OverHead Complete 01/05/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03185 RPL10.Interior.NS2 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Pre WI#08) OverHead Complete 01/05/26 01/23/26 6.2 0.0
100%
0.0