Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
94
Completed
6
In Progress
94
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.SSB.03420 |
RPL10.Interior.SSB - Priority - P0 & P1 Hang Drywall Wall (West Sides) | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 01/05/26 | 01/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02480 |
RPL10.Interior.SSB-Corridor - Priority - Install Drywall at Exterior Wall | Priority Walls & OverHead | Complete | 01/05/26 | 01/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1280 |
RPL10.MCUP.Loop 1 - Set MTRs (4 per day) | OFE | Complete | 01/05/26 | 01/15/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01290 |
RPL10.SKIN.SSB - PSI Flynn Proceeds with the Termination Ends to move out of area & Comback for Remediation | Roofing Remediation 10-42 / 10-30 | Complete | 01/05/26 | 01/05/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01060 |
RPL10.Structure.EF12 - Adjust Drains\Clean Outs\Stubups and Grounding wire | Prep | Complete | 01/06/26 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01070 |
RPL10.Structure.EF12 - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Complete | 01/06/26 | 02/03/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01080 |
RPL10.Structure.EF12 - Install AB final grade and Vapor Barrier | Prep | Complete | 01/06/26 | 02/02/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01090 |
RPL10.Structure.EF12 - Asphalt Emulsion and Wrap Steel Columns | Prep | Complete | 01/06/26 | 02/03/26 | 3.8 | 0.0 |
|
0.0 |
NW.1160 |
Dry Cooler 230 Ton Crane Movement 01 - Finish | 230 Ton Crane (Dry Cooler) | Complete | 01/07/26 | 01/07/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01040 |
RPL10.EY.NS1 - Install Tent Final Grading | Tent and Temp Conditions | Complete | 01/07/26 | 01/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03460 |
RPL10.Interior.SSB - Priority - P0 & P1 Wall Tape Float Paint (West Sides) | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 01/07/26 | 01/22/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04420 |
RPL10.Interior.SSB - Priority - QC - Exterior Walls - Backings/In-Wall | Priority Walls and OverHead | Complete | 01/07/26 | 01/08/26 | 2.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02440 |
RPL10.Interior.SSB-Corridor - Priority - P2 Frame Remaining Wall | Priority Wall (P2) - Grid Line 10-38 | Complete | 01/07/26 | 01/09/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03420 |
RPL10.Interior.SSB-Corridor - Priority - Install Cementitious Spray to Deck - (LOE due to WI) | Priority Walls & OverHead | Complete | 01/07/26 | 02/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03760 |
RPL10.Interior.SSB-Corridor - Priority - Install Cementitious Spray to Deck - (Pre WI#08) | Priority Walls & OverHead | Complete | 01/07/26 | 01/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01010 |
RPL10.SKIN.NS12 - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | NS1 & NS2 | Active | 01/07/26 | 10/16/26 | 246.2 | 102.5 |
|
47.5 |
RPL10.SKN.NS12.01070 |
RPL10.SKIN.NS12 - Install Roof System - Exterior Wall Sheething and EJ | Roofing | Complete | 01/07/26 | 01/13/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01080 |
RPL10.SKIN.NS12 - Install Roof System - WBS Summary | Roofing | Complete | 01/07/26 | 03/18/26 | 56.2 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01100 |
RPL10.SKIN.NS12 - Install Roof System - DenseDeck & Peel & Stick | Roofing | Complete | 01/07/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01120 |
RPL10.Structure.NS12 - SOG F/R/P (Pour #10 -01/06 & #11 -01/08) - Grid lines 10-27/10-24 | F/R/P | Complete | 01/07/26 | 01/09/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.MCUP.FWM.01010 |
RPL10.MCUP.FWM - Install FWM | FWM | Complete | 01/08/26 | 01/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1180 |
RPL10.MCUP.Loop 1 - Cure for Pads | Foundations | Complete | 01/08/26 | 01/18/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01280 |
RPL10.SKIN.NS12 - Weather Event 01/08 (Flash Rain) | Roofing Weather Impact 10-30 / 10-20 | Complete | 01/08/26 | 01/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01330 |
RPL10.SKIN.SSB - PSI DPR Request for Recovery Schedule Again | Roofing Remediation 10-42 / 10-30 | Complete | 01/08/26 | 01/21/26 | 1.2 | 0.0 |
|
0.0 |
NW.1180 |
Dry Cooler 230 Ton Crane Movement 02 - Start | 230 Ton Crane (Dry Cooler) | Complete | 01/09/26 | 01/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.5090 |
RPL10 - Fabricate / Deliver - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Complete | 01/09/26 | 01/30/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01060 |
RPL10.Interior.SSB - Balance of Walls and Overheads - WBS Summary | Balance of Walls and OverHead | Active | 01/09/26 | 09/17/26 | 210.0 | 138.8 |
|
113.8 |
RPL10.INT.SSB.03400 |
RPL10.Interior.SSB - Priority - Install Drywall at Exterior Walls | Priority Walls and OverHead | Complete | 01/09/26 | 01/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04020 |
RPL10.Interior.SSB - Priority - P5 Frame Pony Walls | Priority Wall (P5) - Grid Line 10-C | Complete | 01/09/26 | 01/14/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04320 |
RPL10.Interior.SSB - BoW - Frame Pony Walls | Balance of Walls and OverHead | Complete | 01/09/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03520 |
RPL10.Interior.SSB-Corridor - Priority - Install Hang/Tape/Float/ Paint @ GS.MDF wall location | Priority Walls & OverHead | Complete | 01/09/26 | 01/22/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1320 |
RPL10.MCUP.Loop 1 - Set mCup #5 - Dry Coolers (6) (4 per week) | OFE | Complete | 01/09/26 | 01/13/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01220 |
RPL10.SKIN.NS12 - WI Removing Vapor Barrier/Dense Deck | Roofing Weather Impact 10-30 / 10-20 | Complete | 01/09/26 | 01/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01240 |
RPL10.SKIN.NS12 - WI Replacing Vapor Barrier/Dense Deck | Roofing Weather Impact 10-30 / 10-20 | Complete | 01/09/26 | 01/09/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01030 |
RPL10.Structure.NS43 - Install Decking & Detailing turnover #11 - Grid lines 10-10/10-07 | Steel and Decking | Complete | 01/09/26 | 01/13/26 | 3.8 | 0.0 |
|
0.0 |
JCL.C.1300 |
RPL10 - Cost Risk LOE-16 Fire Alarm Systems | Cost LOEs | Active | 01/12/26 | 02/22/27 | 315.0 | 270.0 |
|
67.5 |
PRE.FA.1200 |
Glass / Glazing - Final Agreement | Trade Partner Final Agreement | Complete | 01/12/26 | 01/12/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01015 |
RPL10.EY.NS1 - Install F/R/P Equipment Pads - 9-15 (Grid 10-32/10-42) (12'' Larger For Tolerance) | Foundations | Complete | 01/12/26 | 01/19/26 | 27.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01000 |
RPL10.Interior.Center-Corridor - Install Priority Walls and OverHead - WBS Summary | Priority Walls & OverHead | Active | 01/12/26 | 05/14/26 | 107.5 | 30.0 |
|
113.8 |
RPL10.INT.CTRC.01020 |
RPL10.Interior.Center-Corridor - Install Priority OH, Walls, Fitout and Build Back - WBS Summary | Center Corridor | Active | 01/12/26 | 07/29/26 | 172.5 | 95.0 |
|
146.2 |
RPL10.INT.CTRC.01040 |
RPL10.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) | Priority Walls & OverHead | Complete | 01/12/26 | 01/14/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01030 |
RPL10.Interior.NS1 - Priority - Install Fire Sprinkler | OverHead | Complete | 01/12/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01030 |
RPL10.Interior.NS2 - Priority - Install Fire Sprinkler | OverHead | Complete | 01/12/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01110 |
RPL10.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) | Priority Walls and OverHead | Complete | 01/12/26 | 01/21/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01660 |
RPL10.Interior.SSB - Priority - Install Plumbing (Highside OH space) - (LOE due to WI) | Priority Walls and OverHead | Complete | 01/12/26 | 02/25/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06900 |
RPL10.Interior.SSB - Priority - Install Plumbing (Highside OH space) - (Pre WI#08) | Priority Walls and OverHead | Complete | 01/12/26 | 01/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02460 |
RPL10.Interior.SSB-Corridor - Priority - Install Backing Exterior Wall | Priority Walls & OverHead | Complete | 01/12/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03620 |
RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall - (LOE due to WI) | Priority Walls & OverHead | Complete | 01/12/26 | 03/02/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03800 |
RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall - (Pre WI#08) | Priority Walls & OverHead | Complete | 01/12/26 | 01/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2300 |
RPL10.MCUP.Loop 1 - Set mCup #7 - Dry Coolers (6) (4 per week) | OFE | Complete | 01/12/26 | 01/14/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2380 |
RPL10.MCUP.Loop 1 - Set mCup #7 Facility water piping rack - (LOE due to WI) | OFE | Complete | 01/12/26 | 02/02/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2460 |
RPL10.MCUP.Loop 1 - F/R/P Pads for MVS Pad | Foundations | Complete | 01/12/26 | 01/15/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2520 |
RPL10.MCUP.Loop 1 - Set mCup #7 Facility water piping rack - (Pre WI#08) | OFE | Complete | 01/12/26 | 01/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01130 |
RPL10.Structure.NS12 - SOG F/R/P (Pour #12 -01/10 & #13 -01/13) - Grid lines 10-24/10-20 | F/R/P | Complete | 01/12/26 | 01/14/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07080 |
RPL10.Interior.Center-Corridor - Priority - P3 Frame Soffit and Hang Drywall | Priority Wall (P3) - Grid Line 10-25 | Complete | 01/13/26 | 01/19/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04340 |
RPL10.Interior.SSB - BoW - Hang Drywall Pony Wall (both sides) | Balance of Walls and OverHead | Complete | 01/13/26 | 01/22/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01050 |
RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-30/10-20(5)(with temp closures for openings) | South | Complete | 01/13/26 | 01/14/26 | 2.5 | 0.0 |
|
0.0 |
GCD.RPL10.1320 |
Steel Complete - RPL10 | Construction Milestones | Complete | 01/14/26 | 01/14/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01050 |
RPL10.EY.NS1 - Install Tent F/R/P SOG (30k Mock Up) - Changed as LOE due to WI#07 | Tent and Temp Conditions | Complete | 01/14/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01640 |
RPL10.EY.NS1 - Install Tent F/R/P SOG (Pre WI#07) | Tent and Temp Conditions | Complete | 01/14/26 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01011 |
RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) - (LOE due to WI) | Priority Walls & OverHead | Complete | 01/14/26 | 02/13/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03840 |
RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) - (Pre WI#08) | Priority Walls & OverHead | Complete | 01/14/26 | 01/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01010 |
RPL10.SKIN.EF12 - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | EF1 & EF2 | Active | 01/14/26 | 07/24/26 | 166.2 | 22.5 |
|
235.0 |
RPL10.SKN.EF12.01070 |
RPL10.SKIN.EF12 - Install Roof System - Exterior Wall Sheething and EJ | Roofing | Complete | 01/14/26 | 01/15/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01080 |
RPL10.SKIN.EF12 - Install Roof System - WBS Summary | Roofing | Complete | 01/14/26 | 03/27/26 | 65.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01100 |
RPL10.SKIN.EF12 - Install Roof System - DenseDeck & Peel & Stick | Roofing | Complete | 01/14/26 | 02/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01060 |
RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10 (8) (with temp closures for openings) | South | Complete | 01/14/26 | 01/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01040 |
RPL10.Structure.NS43 - Install Decking & Detailing turnover #12 - Grid lines 10-07/10-04 | Steel and Decking | Complete | 01/14/26 | 01/20/26 | 3.8 | 0.0 |
|
0.0 |
NW.1200 |
Dry Cooler 230 Ton Crane Movement 02 - Finish | 230 Ton Crane (Dry Cooler) | Complete | 01/15/26 | 01/15/26 | 0.0 | 0.0 |
|
0.0 |
NW.1860 |
Steel Crane #1 Demobilzation | Steel Crane #1 | Complete | 01/15/26 | 01/15/26 | 0.0 | 0.0 |
|
0.0 |
NW.1880 |
Steel Crane #2 Demobilization | Steel Crane #2 | Complete | 01/15/26 | 01/15/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02340 |
RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (LOE due to WI) | OverHead | Complete | 01/15/26 | 02/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.03020 |
RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (Pre WI#08) | OverHead | Complete | 01/15/26 | 01/23/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02000 |
RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (LOE due to WI) | OverHead | Complete | 01/15/26 | 02/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.03105 |
RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (Pre WI#08) | OverHead | Complete | 01/15/26 | 01/23/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04060 |
RPL10.Interior.SSB - Priority - P5 Hang Drywall Pony Wall (both sides) | Priority Wall (P5) - Grid Line 10-C | Complete | 01/15/26 | 01/21/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01260 |
RPL10.SKIN.NS12 - WI Inspection Vapor Barrier/Dense Deck | Roofing Weather Impact 10-30 / 10-20 | Complete | 01/15/26 | 01/15/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01100 |
RPL10.Structure.EF12 - SOG F/R/P (Pour #14 -01/15) - Grid lines 10-20/10-17 | F/R/P | Complete | 01/15/26 | 01/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01110 |
RPL10.Structure.EF12 - SOG F/R/P - WBS Summary | F/R/P | Complete | 01/15/26 | 03/21/26 | 58.8 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01140 |
RPL10.Structure.NS12 - Zone SOG Cure | F/R/P | Complete | 01/15/26 | 01/21/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.3890 |
RPL10 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) | (CFCI) Div. 22 - Plumbing | Complete | 01/16/26 | 01/26/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.7040 |
RPL10 - Fabricate / Deliver - Mechanical Piping Valve Delivery | (CFCI) Div. 22 - Plumbing | Complete | 01/16/26 | 03/24/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06740 |
RPL10.Interior.Center-Corridor - Priority - P3 Frame Remaining Wall | Priority Wall (P3) - Grid Line 10-25 | Complete | 01/16/26 | 01/21/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07100 |
RPL10.Interior.Center-Corridor - Priority - P3 Soffit Tape, Float and Paint, Fire Safing Both Sides | Priority Wall (P3) - Grid Line 10-25 | Complete | 01/16/26 | 01/22/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2480 |
RPL10.MCUP.Loop 1 - Cure for MVS Pad | Foundations | Complete | 01/16/26 | 01/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.01280 |
RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Install Bent Plate & Gusset Plates (Pre WI#08) | Expansion Joint Delay Event | Complete | 01/16/26 | 01/23/26 | 1.2 | 0.0 |
|
0.0 |
ICM.B10.1875 |
[NWB] Delivery of mCUP Skids (First Delivery) - RPL10 | Construction | Complete | 01/19/26 | 01/19/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.MCUP.FWM.01000 |
RPL10.MCUP.FWM - Install PTX | FWM | Complete | 01/19/26 | 01/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.FWM.01030 |
RPL10.MCUP.FWM - Install MVS | FWM | Complete | 01/19/26 | 01/19/26 | 5.0 | 0.0 |
|
0.0 |
GCD.RPL10.1182 |
Start mCUP Unit Set-In-Place - RPL10 | Construction Milestones | Complete | 01/20/26 | 01/20/26 | 0.0 | 0.0 |
|
0.0 |
NW.1000 |
MCUP 600 Ton Crane Mobilization | 600 Ton Crane (MCUP) | Complete | 01/20/26 | 01/20/26 | 0.0 | 0.0 |
|
0.0 |
NW.1020 |
MCUP 600 Ton Crane Movement 1 | 600 Ton Crane (MCUP) | Complete | 01/20/26 | 01/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01130 |
RPL10.EY.NS1 - Cure (High Early Mix) | Foundations | Complete | 01/20/26 | 01/23/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01520 |
RPL10.Interior.Center-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) All Corridor Wall (LOE) | Priority Walls & OverHead | Complete | 01/20/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01670 |
RPL10.Interior.Center-Corridor - Priority - Frame Priority Soffit and Hang Drywall (All CC & EF) ***Duration(LOE) | Priority Walls & OverHead | Complete | 01/20/26 | 02/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07180 |
RPL10.Interior.Center-Corridor - Priority - Frame Priority Soffit and Hang Drywall (All CC & EF) - (Pre WI#08) | Priority Walls & OverHead | Complete | 01/20/26 | 01/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07300 |
RPL10.Interior.Center-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Pre WI#08) | Priority Walls & OverHead | Complete | 01/20/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02140 |
RPL10.Interior.NS1 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall (LOE) | OverHead | Complete | 01/20/26 | 02/02/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.03100 |
RPL10.Interior.NS1 - Priority - Install Layout, Unistruts & Hangers - (Pre WI#08) | OverHead | Complete | 01/20/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01980 |
RPL10.Interior.NS2 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall(LOE) | OverHead | Complete | 01/20/26 | 02/02/26 | 6.2 | 0.0 |
|
0.0 |