Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
93
Completed
7
In Progress
93
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.NS2.02320 RPL10.Interior.NS2 - Priority - Install Drywall at Exterior Wall - (LOE due to WI) OverHead Complete 01/20/26 02/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03145 RPL10.Interior.NS2 - Priority - Install Drywall at Exterior Wall - (Pre WI#08) OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03225 RPL10.Interior.NS2 - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Pre WI#08) OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.04080 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Pony Wall (both sides) - (LOE due to WI) Priority Wall (P5) - Grid Line 10-C Complete 01/20/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.04360 RPL10.Interior.SSB - BoW - Tape Float Paint Pony Wall (both sides) - (LOE due to WI) Balance of Walls and OverHead Complete 01/20/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06780 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Pony Wall (both sides) (Pre WI#08) Priority Wall (P5) - Grid Line 10-C Complete 01/20/26 01/23/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06860 RPL10.Interior.SSB - BoW - Tape Float Paint Pony Wall (both sides) - (Pre WI#08) Balance of Walls and OverHead Complete 01/20/26 01/23/26 6.0 0.0
100%
0.0
RPL10.INT.SSBC.01012 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) - (LOE due to WI) Priority Walls & OverHead Complete 01/20/26 02/20/26 18.8 0.0
100%
0.0
RPL10.INT.SSBC.02180 RPL10.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) - (LOE due to WI) Priority Walls & OverHead Complete 01/20/26 02/09/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03120 RPL10.Interior.SSB-Corridor - Priority - P2 Wall MEP Backing/In-Wall Rough Ins - (LOE due to WI) Priority Wall (P2) - Grid Line 10-38 Complete 01/20/26 02/12/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03720 RPL10.Interior.SSB-Corridor - Priority - P2 Wall MEP Backing/In-Wall Rough Ins - (Pre WI#08) Priority Wall (P2) - Grid Line 10-38 Complete 01/20/26 01/23/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03880 RPL10.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03920 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 18.8 0.0
100%
0.0
RPL10.MCUP.LP1.1340 RPL10.MCUP.Loop 1 - Set mCUPs #1 (1 per 5 days) (01.05.26) OFE Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1200 RPL10.MCUP.Loop 2 - OFE - WBS Summary OFE Active 01/20/26 04/24/26 83.8 12.5
0%
130.0
RPL10.MCUP.LP2.2320 RPL10.MCUP.Loop 2 - Set mCup #2 Facility water piping rack - (LOE due to WI) OFE Complete 01/20/26 02/02/26 15.0 0.0
100%
0.0
RPL10.MCUP.LP2.2420 RPL10.MCUP.Loop 2 - Set mCup #2 Facility water piping rack - (Pre WI#07) OFE Complete 01/20/26 01/20/26 15.0 0.0
100%
0.0
RPL10.STR.EF12.01120 RPL10.Structure.EF12 - SOG F/R/P (Pour #15 -01/17 & #16 -01/20) - Grid lines 10-17/10-14 - (LOE due to WI) F/R/P Complete 01/20/26 02/05/26 5.0 0.0
100%
0.0
RPL10.STR.EF12.01200 RPL10.Structure.EF12 - SOG F/R/P (Pour #15 -01/17 & #16 -01/20) - Grid lines 10-17/10-14 (Pre WI#07) F/R/P Complete 01/20/26 01/20/26 5.0 0.0
100%
0.0
NW.2080 Weather Event #7 - 01/21/26 Project Impacts Complete 01/21/26 01/21/26 1.2 0.0
100%
0.0
RPL10.INT.CTRC.01030 RPL10.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) - (LOE due to WI) Priority Walls & OverHead Complete 01/21/26 03/06/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07220 RPL10.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) - (Pre WI#08) Priority Walls & OverHead Complete 01/21/26 01/23/26 6.2 0.0
100%
0.0
NW.1720 IMP Crane #1 Movement 07 IMP Crane #1 Complete 01/22/26 01/22/26 0.0 0.0
100%
0.0
RPL10.EY.NS1.01660 RPL10.EY.NS1 - Install Tent F/R/P SOG (Post WI#07) Tent and Temp Conditions Complete 01/22/26 01/23/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01740 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#07) (Pre WI#08) Foundations Complete 01/22/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01690 RPL10.Interior.Center-Corridor - Priority - Install IMP Exterior Wall In-Wall Rough-Ins - (LOE due to WI) Priority Walls & OverHead Complete 01/22/26 03/09/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06760 RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall Rough Ins - (LOE due to WI) Priority Wall (P3) - Grid Line 10-25 Complete 01/22/26 02/13/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06780 RPL10.Interior.Center-Corridor - Priority - P3 Wall Backing - (LOE due to WI) Priority Wall (P3) - Grid Line 10-25 Complete 01/22/26 02/13/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07260 RPL10.Interior.Center-Corridor - Priority - Install IMP Exterior Wall In-Wall Rough-Ins - (Pre WI#08) Priority Walls & OverHead Complete 01/22/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07340 RPL10.Interior.Center-Corridor - Priority - P3 Wall Backing - (Pre WI#08) Priority Wall (P3) - Grid Line 10-25 Complete 01/22/26 01/23/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07380 RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall Rough Ins - (Pre WI#08) Priority Wall (P3) - Grid Line 10-25 Complete 01/22/26 01/23/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.01070 RPL10.Interior.SSB-Corridor - Balance Of Walls - WBS Summary Balance of Walls & OverHead Active 01/22/26 10/21/26 237.5 168.8
0%
66.2
RPL10.INT.SSBC.01180 RPL10.Interior.SSB-Corridor - Install Fitout (GSMDF Elec2x, Riser Room, GS EF Room, Carrier MDF,SSB Mech) - WBS Summary Balance of Walls & OverHead Active 01/22/26 10/21/26 237.5 168.8
0%
66.2
RPL10.INT.SSBC.03960 RPL10.Interior.SSB-Corridor - BoW - Frame Balance of Wall - (Pre WI#08) Balance of Walls & OverHead Complete 01/22/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.04000 RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - Framing - (Pre WI#08) Balance of Walls & OverHead Complete 01/22/26 01/23/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.2440 RPL10.MCUP.Loop 2 - Set mCup #2 Facility water piping rack - (Post WI#07) (Pre WI#08) OFE Complete 01/22/26 01/23/26 15.0 0.0
100%
0.0
RPL10.MCUP.LP2.2480 RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Post WI#07) (Pre WI#08) Foundations Complete 01/22/26 01/23/26 25.0 0.0
100%
0.0
RPL10.SKN.N.01070 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10(7) (Post WI#07) (Pre WI#08) North Complete 01/22/26 01/23/26 2.5 0.0
100%
0.0
RPL10.STR.EF12.01220 RPL10.Structure.EF12 - SOG F/R/P (Pour #15 -01/17 & #16 -01/20) - Grid lines 10-17/10-14 (Post WI#07) (Pre WI#08) F/R/P Complete 01/22/26 01/23/26 5.0 0.0
100%
0.0
RPL10.STR.NS43.01050 RPL10.Structure.NS43 - Install Decking & Detailing turnover #13 - Grid lines 10-04/10-01 (Saturday Work) Steel and Decking Complete 01/22/26 01/23/26 3.8 0.0
100%
0.0
NW.1760 IMP Crane #1 Movement 08 IMP Crane #1 Complete 01/23/26 01/23/26 0.0 0.0
100%
0.0
RPL10.EY.EF2.01130 RPL10.EY.EF2 - Install Generator OFE Complete 01/23/26 01/23/26 2.5 0.0
100%
0.0
RPL10.EY.EF2.01150 RPL10.EY.EF2 - OFE - WBS Summary OFE Active 01/23/26 04/27/26 81.2 2.5
0%
192.5
RPL10.INT.SSB.03220 RPL10.Interior.SSB - Priority - QC - P0 & P1 Priority Walls- Backings/In-Wall - (LOE due to WI) Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 01/23/26 02/12/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.06740 RPL10.Interior.SSB - Priority - QC - P0 & P1 Priority Walls- Backings/In-Wall (Pre #WI08) Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 01/23/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01050 RPL10.Interior.SSB-Corridor - BoW - Frame Balance of Wall - (LOE due to WI) Balance of Walls & OverHead Complete 01/23/26 02/02/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03680 RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - Framing - (LOE due to WI) Balance of Walls & OverHead Complete 01/23/26 02/02/26 2.5 0.0
100%
0.0
RPL10.EY.NS1.01080 RPL10.EY.NS1 - Tent SOG Cure Tent and Temp Conditions Complete 01/24/26 02/07/26 8.8 0.0
100%
0.0
NW.2100 Weather Event #8 - 01/26/26 - 01/30/26 Project Impacts Complete 01/26/26 01/30/26 1.2 0.0
100%
0.0
RPL10.CFCI.4870 RPL10- Submittal Rvw/App'l - Interior Painting (Spec 09 91 23) (CFCI) Div. 09 - Painting Complete 01/26/26 01/29/26 25.0 0.0
100%
0.0
RPL10.CFCI.5060 RPL10- Fabricate / Deliver - Interior Painting (Spec 09 91 23) (CFCI) Div. 09 - Painting Complete 01/30/26 02/20/26 25.0 0.0
100%
0.0
RPL10.EY.EF1.01080 RPL10.EY.EF1 - Install Generator OFE Complete 02/02/26 02/03/26 2.5 0.0
100%
0.0
RPL10.EY.EF1.01110 RPL10.EY.EF1 - OFE - WBS Summary OFE Active 02/02/26 04/27/26 73.8 2.5
0%
127.5
RPL10.EY.EF2.01750 RPL10.EY.EF2 - Install Mechanical UG (Post WI#08) Underground Complete 02/02/26 02/16/26 12.5 0.0
100%
0.0
RPL10.EY.NS2.01760 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#08) Foundations Complete 02/02/26 02/06/26 6.2 0.0
100%
0.0
RPL10.EY.NS3.01570 RPL10.EY.NS3 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) - (Post WI#08) Foundations Complete 02/02/26 02/18/26 18.8 0.0
100%
0.0
RPL10.EY.NS4.01570 RPL10.EY.NS4 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) - (Post WI#08) Foundations Complete 02/02/26 02/18/26 18.8 0.0
100%
0.0
RPL10.EY.SSB.01110 RPL10.EY.SSB - Install LD Electrical UG Loading Dock Complete 02/02/26 02/05/26 5.0 0.0
100%
0.0
RPL10.EY.SSB.01140 RPL10.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary Loading Dock Active 02/02/26 09/10/26 192.5 20.0
0%
42.5
RPL10.EY.SSB.01150 RPL10.EY.SSB - Install LD Mechanical UG Loading Dock Complete 02/02/26 02/06/26 12.5 0.0
100%
0.0
RPL10.INT.CTRC.01540 RPL10.Interior.Center-Corridor - Priority - Install Supplemental Steel (Grid 10-D to 10-C) Priority Walls & OverHead Complete 02/02/26 02/06/26 12.5 0.0
100%
0.0
RPL10.INT.CTRC.07200 RPL10.Interior.Center-Corridor - Priority - Frame Priority Soffit and Hang Drywall (All CC & EF) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/16/26 18.8 0.0
100%
0.0
RPL10.INT.CTRC.07240 RPL10.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07280 RPL10.Interior.Center-Corridor - Priority - Install IMP Exterior Wall In-Wall Rough-Ins - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 03/09/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07320 RPL10.Interior.Center-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/20/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07360 RPL10.Interior.Center-Corridor - Priority - P3 Wall Backing - (Post WI#08) Priority Wall (P3) - Grid Line 10-25 Complete 02/02/26 02/13/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07400 RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall Rough Ins - (Post WI#08) Priority Wall (P3) - Grid Line 10-25 Complete 02/02/26 02/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.03000 RPL10.Interior.NS1 - Priority - Install Backing Exterior Wall - (Post WI#08) OverHead Complete 02/02/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.03040 RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (Post WI#08) (Pre WI#09) OverHead Complete 02/02/26 02/02/26 15.0 0.0
100%
0.0
RPL10.INT.NS1.03080 RPL10.Interior.NS1 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Post WI#08) OverHead Complete 02/02/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.03120 RPL10.Interior.NS1 - Priority - Install Layout, Unistruts & Hangers - (Post WI#08) OverHead Complete 02/02/26 02/02/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03085 RPL10.Interior.NS2 - Priority - Install Backing Exterior Wall - (Post WI#08) OverHead Complete 02/02/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03125 RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (Post WI#08) OverHead Complete 02/02/26 02/02/26 15.0 0.0
100%
0.0
RPL10.INT.NS2.03165 RPL10.Interior.NS2 - Priority - Install Drywall at Exterior Wall - (Post WI#08) OverHead Complete 02/02/26 02/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03205 RPL10.Interior.NS2 - Priority - Install IMP Exterior In-Wall Rough-Ins - (Post WI#08) OverHead Complete 02/02/26 02/03/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03245 RPL10.Interior.NS2 - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Post WI#08) OverHead Complete 02/02/26 02/02/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.06760 RPL10.Interior.SSB - Priority - QC - P0 & P1 Priority Walls- Backings/In-Wall (Post WI#08) Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 02/02/26 02/12/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.06800 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Pony Wall (both sides) (Post WI#08) Priority Wall (P5) - Grid Line 10-C Complete 02/02/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06840 RPL10.Interior.SSB - Priority - Install Duct (Highside OH space) - (Post WI#08) Priority Walls and OverHead Complete 02/02/26 02/04/26 7.5 0.0
100%
0.0
RPL10.INT.SSB.06880 RPL10.Interior.SSB - BoW - Tape Float Paint Pony Wall (both sides) - (Post WI#08) Balance of Walls and OverHead Complete 02/02/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06920 RPL10.Interior.SSB - Priority - Install Plumbing (Highside OH space) - (Post WI#08) Priority Walls and OverHead Complete 02/02/26 02/25/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.01010 RPL10.Interior.SSB-Corridor - Priority - Install Duct (LOE) Priority Walls & OverHead Complete 02/02/26 02/20/26 25.0 0.0
100%
0.0
RPL10.INT.SSBC.03740 RPL10.Interior.SSB-Corridor - Priority - P2 Wall MEP Backing/In-Wall Rough Ins - (Post WI#08) Priority Wall (P2) - Grid Line 10-38 Complete 02/02/26 02/12/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03780 RPL10.Interior.SSB-Corridor - Priority - Install Cementitious Spray to Deck - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/02/26 25.0 0.0
100%
0.0
RPL10.INT.SSBC.03820 RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall - (Post WI#08) ** Priority Walls & OverHead Complete 02/02/26 03/02/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03860 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/13/26 18.8 0.0
100%
0.0
RPL10.INT.SSBC.03900 RPL10.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/09/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03940 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) - (Post WI#08) Priority Walls & OverHead Complete 02/02/26 02/20/26 18.8 0.0
100%
0.0
RPL10.INT.SSBC.03980 RPL10.Interior.SSB-Corridor - BoW - Frame Balance of Wall - (Post WI#08) Balance of Walls & OverHead Complete 02/02/26 02/06/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.04020 RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - Framing - (Post WI#08) Balance of Walls & OverHead Complete 02/02/26 02/06/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP1.2540 RPL10.MCUP.Loop 1 - Set mCup #7 Facility water piping rack - (Post WI#08) OFE Complete 02/02/26 02/02/26 12.5 0.0
100%
0.0
RPL10.MCUP.LP2.2500 RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Post WI#08) (Pre WI#09) Foundations Complete 02/02/26 02/02/26 25.0 0.0
100%
0.0
RPL10.MCUP.LP2.2520 RPL10.MCUP.Loop 2 - Set mCup #2 Facility water piping rack - (Post WI#08) OFE Complete 02/02/26 02/02/26 15.0 0.0
100%
0.0
RPL10.SKN.01340 RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Install Bent Plate & Gusset Plates (Post WI#08) Expansion Joint Delay Event Complete 02/02/26 02/02/26 1.2 0.0
100%
0.0
RPL10.SKN.N.01100 RPL10.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin North Complete 02/02/26 02/13/26 12.5 0.0
100%
0.0
RPL10.SKN.N.01220 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10(7) (Post WI#08) North Complete 02/02/26 02/02/26 2.5 0.0
100%
0.0
RPL10.SKN.NS12.01000 RPL10.SKIN.NS12 - Install Temp Doors Glazing, Doors and Ext Devices Complete 02/02/26 02/03/26 2.5 0.0
100%
0.0
RPL10.SKN.NS12.01020 RPL10.SKIN.NS12 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Active 02/02/26 10/16/26 225.0 102.5
0%
47.5
RPL10.STR.EF12.01240 RPL10.Structure.EF12 - SOG F/R/P (Pour #15 -01/17 & #16 -01/20) - Grid lines 10-17/10-14 (Post WI#08) F/R/P Complete 02/02/26 02/05/26 5.0 0.0
100%
0.0
RPL10.STR.NS12.01280 RPL10.Structure.NS12 - PSI RFI Plumbing/Slab Remediation F/R/P Complete 02/02/26 02/10/26 6.2 0.0
100%
0.0