Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
94
Completed
6
In Progress
94
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.STR.NS43.01060 |
RPL10.Structure.NS43 - Adjust Drains\Clean Outs\Stubups and Grounding wire | Prep | Complete | 02/02/26 | 02/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01070 |
RPL10.Structure.NS43 - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Complete | 02/02/26 | 02/20/26 | 8.8 | 0.0 |
|
0.0 |
GCD.RPL10.1280 |
Interior fit-out Start RPL10 - NS12 | Construction Milestones | Complete | 02/03/26 | 02/03/26 | 0.0 | 0.0 |
|
0.0 |
NW.2120 |
Weather Event #9 - 02/03/26 | Project Impacts | Complete | 02/03/26 | 02/03/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01010 |
RPL10.Interior.NS1 - Priority - Install Duct | OverHead | Complete | 02/03/26 | 02/20/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02080 |
RPL10.Interior.NS1 - Priority - Install Plumbing/Mechanical Piping | OverHead | Complete | 02/03/26 | 02/09/26 | 3.8 | 0.0 |
|
0.0 |
NW.1060 |
MCUP 600 Ton Crane Movement 3 | 600 Ton Crane (MCUP) | Complete | 02/04/26 | 02/04/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01110 |
RPL10.EY.NS1 - Install Tent | Tent and Temp Conditions | Complete | 02/04/26 | 03/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01015 |
RPL10.EY.NS2 - Install F/R/P Equipment Pads - 9-15 (Grid 10-32/10-42) (12'' Larger For Tolerance) | Foundations | Complete | 02/04/26 | 02/06/26 | 20.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01040 |
RPL10.EY.NS2 - Install Tent Final Grading | Tent and Temp Conditions | Complete | 02/04/26 | 02/05/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01000 |
RPL10.EY.NS4 - Install Shallow Tent UG | Tent and Temp Conditions | Complete | 02/04/26 | 02/05/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01750 |
RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint Priority Soffit, Fire Safing Both Sides (All CC & EF) | Priority Walls & OverHead | Complete | 02/04/26 | 03/13/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06800 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall (West Side) | Priority Wall (P3) - Grid Line 10-25 | Complete | 02/04/26 | 02/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01010 |
RPL10.Interior.EF1 - Priority OH - WBS Summary | OverHead | Active | 02/04/26 | 05/29/26 | 102.5 | 42.5 |
|
136.2 |
RPL10.INT.EF1.01020 |
RPL10.Interior.EF1 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | EF1 | Active | 02/04/26 | 07/24/26 | 151.2 | 91.2 |
|
158.8 |
RPL10.INT.EF1.01040 |
RPL10.Interior.EF1 - Priority OH - Install Temp Lighting | OverHead | Complete | 02/04/26 | 02/05/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02360 |
RPL10.Interior.NS1 - Priority - Install Drywall at Exterior Wall | OverHead | Complete | 02/04/26 | 02/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.03140 |
RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (Post WI#09) | OverHead | Complete | 02/04/26 | 02/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02360 |
RPL10.Interior.NS2 - Priority - Install Security | OverHead | Complete | 02/04/26 | 02/05/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.03265 |
RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (Post WI#09) | OverHead | Complete | 02/04/26 | 02/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04120 |
RPL10.Interior.SSB - Priority - P5 Frame Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 02/04/26 | 02/06/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01080 |
RPL10.Interior.SSB-Corridor - BoW - Install Doors Frame | Balance of Walls & OverHead | Complete | 02/04/26 | 02/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03500 |
RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - MEP In-Wall | Balance of Walls & OverHead | Complete | 02/04/26 | 02/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.04040 |
RPL10.Interior.SSB-Corridor - Priority - Install Cementitious Spray to Deck - (Post WI#09) | Priority Walls & OverHead | Complete | 02/04/26 | 02/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1380 |
RPL10.MCUP.Loop 1 - Set mCUPs #3 (1 per 5 days) | OFE | Complete | 02/04/26 | 02/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1340 |
RPL10.MCUP.Loop 2 - Remaining Electrical F/R/P Pads 4 (12'' larger) | Foundations | Complete | 02/04/26 | 02/27/26 | 17.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2340 |
RPL10.MCUP.Loop 2 - Set mCup #4 Facility water piping rack | OFE | Complete | 02/04/26 | 02/05/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2540 |
RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Post WI#09) | Foundations | Complete | 02/04/26 | 02/27/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.01360 |
RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Install Bent Plate & Gusset Plates (Post WI#09) | Expansion Joint Delay Event | Complete | 02/04/26 | 02/09/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01240 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10(7) (Post WI#09) | North | Complete | 02/04/26 | 02/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01080 |
RPL10.Structure.NS43 - Install AB final grade and Vapor Barrier | Prep | Complete | 02/04/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01040 |
RPL10.EY.NS4 - Install Final Grading | Tent and Temp Conditions | Complete | 02/05/26 | 02/06/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01440 |
RPL10.EY.SSB - Dig Walls | Loading Dock | Complete | 02/05/26 | 02/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01030 |
RPL10.Interior.EF1 - Priority OH - Install Fire Sprinkler | OverHead | Complete | 02/05/26 | 02/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01730 |
RPL10.Interior.EF1 - Priority OH - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall | OverHead | Complete | 02/05/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01120 |
RPL10.Interior.NS1 - Priority - Install Security | OverHead | Complete | 02/05/26 | 02/06/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01170 |
RPL10.Interior.NS1 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 02/05/26 | 02/11/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02820 |
RPL10.Interior.SSB-Corridor - BoW - Install Backing BoW | Balance of Walls & OverHead | Complete | 02/05/26 | 02/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03660 |
RPL10.Interior.SSB-Corridor - BoW - Install Remaining Unistruts & Hangers | Balance of Walls & OverHead | Complete | 02/05/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1360 |
RPL10.MCUP.Loop 1 - Set Electrical Skids #1 | OFE | Complete | 02/05/26 | 02/05/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2360 |
RPL10.MCUP.Loop 2 - Set mCup #6 Facility water piping rack | OFE | Complete | 02/05/26 | 02/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01090 |
RPL10.Structure.NS43 - Asphalt Emulsion and Wrap Steel Columns | Prep | Complete | 02/05/26 | 02/20/26 | 3.8 | 0.0 |
|
0.0 |
ICM.B10.1750 |
[NWB] Room Ready for GS.MDF Module Placement - RPL10 | Construction | Complete | 02/06/26 | 02/06/26 | 0.0 | 0.0 |
|
0.0 |
NW.1220 |
Dry Cooler 230 Ton Crane Movement 03 - Start | 230 Ton Crane (Dry Cooler) | Complete | 02/06/26 | 02/06/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01540 |
RPL10.EY.EF1 - Install F/R/P Remaining Equipment Pads for GSB & IDF Huts | Foundations | Complete | 02/06/26 | 02/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01730 |
RPL10.EY.EF2 - Install F/R/P Remaining Equipment Pads for GSB | Foundations | Complete | 02/06/26 | 02/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01050 |
RPL10.EY.NS2 - Install Tent F/R/P SOG (30k Mock Up) | Tent and Temp Conditions | Complete | 02/06/26 | 02/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01000 |
RPL10.EY.NS3 - Install Shallow Tent UG | Tent and Temp Conditions | Complete | 02/06/26 | 02/09/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01230 |
RPL10.EY.SSB - Install LD F/R/P Loading Dock Walls | Loading Dock | Complete | 02/06/26 | 02/09/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01050 |
RPL10.Interior.Center-Corridor - Priority - Frame Perimeter Remaining Walls (EF1 & EF2) | EF Perimeter Walls | Complete | 02/06/26 | 02/17/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02380 |
RPL10.Interior.Center-Corridor - Priority - P4 Frame Remaining Wall (EF2 Wall Along Grid 10-D) | Priority Wall (P4) - Grid Line 10-D | Complete | 02/06/26 | 02/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01010 |
RPL10.Interior.EF2 - Install Priority OH - WBS Summary | OverHead | Active | 02/06/26 | 06/11/26 | 108.8 | 50.0 |
|
136.2 |
RPL10.INT.EF2.01020 |
RPL10.Interior.EF2 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | EF2 | Active | 02/06/26 | 08/11/26 | 161.2 | 106.2 |
|
156.2 |
RPL10.INT.EF2.01040 |
RPL10.Interior.EF2 - Priority OH - Install Temp Lighting | OverHead | Complete | 02/06/26 | 02/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01070 |
RPL10.Interior.EF2 - Priority - WBS Summary | OverHead | Active | 02/06/26 | 06/11/26 | 108.8 | 50.0 |
|
136.2 |
RPL10.MCUP.LP1.1520 |
RPL10.MCUP.Loop 1 - Set Electrical Skids #3 | OFE | Complete | 02/06/26 | 02/06/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1220 |
RPL10.MCUP.Loop 2 - Set mCup #2 - Dry Coolers (6) (4 per week) | OFE | Complete | 02/06/26 | 02/09/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01350 |
RPL10.SKIN.SSB - PSI Install Rework DenseDeck & Peel & Stick (Grid 10-42 / 10-30) | Roofing Remediation 10-42 / 10-30 | Complete | 02/06/26 | 03/13/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01130 |
RPL10.Structure.EF12 - SOG F/R/P Pour #17 -01/22 & #18 -01/24) - Grid lines 10-14/10-10 | F/R/P | Complete | 02/06/26 | 02/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01000 |
RPL10.EY.SSB - Install F/R/P Equipment Pads | Foundations | Complete | 02/09/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01010 |
RPL10.EY.SSB - Install Foundations - WBS Summary | Foundations | Complete | 02/09/26 | 02/20/26 | 13.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01460 |
RPL10.EY.SSB - Set LD Strip Walls/ Backfill /Grade | Loading Dock | Complete | 02/09/26 | 02/10/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01340 |
RPL10.Interior.Center-Corridor - Priority - F/R/P Pads | Priority Walls & OverHead | Complete | 02/09/26 | 02/11/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01050 |
RPL10.Interior.NS1 - Priority - Install FA / Linear heat detection | OverHead | Complete | 02/09/26 | 02/27/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03480 |
RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - Hang Drywall & Tape Float Paint (02.17.26) | Balance of Walls & OverHead | Complete | 02/09/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1500 |
RPL10.MCUP.Loop 1 - Set mCUPs #5 (1 per 5 days) | OFE | Complete | 02/09/26 | 02/13/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.E.01040 |
RPL10.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin | East | Complete | 02/09/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01010 |
RPL10.SKIN.NS43 - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | NS4 & NS3 | Active | 02/09/26 | 01/27/27 | 302.5 | 173.8 |
|
77.5 |
RPL10.SKN.NS43.01080 |
RPL10.SKIN.NS43 - Install Roof System - WBS Summary | Roofing | Complete | 02/09/26 | 03/30/26 | 48.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01090 |
RPL10.SKIN.NS43 - Install Roof System - DenseDeck & Peel & Stick | Roofing | Complete | 02/09/26 | 02/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01130 |
RPL10.SKIN.SSB - Install Roof System - Final Roof (Grid 10-42 / 10-30) | Roofing | Complete | 02/09/26 | 03/13/26 | 13.8 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01030 |
RPL10.EY.EF1 - Cure (High Early Mix) | Foundations | Complete | 02/10/26 | 02/16/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01070 |
RPL10.EY.EF2 - Cure (High Early Mix) | Foundations | Complete | 02/10/26 | 02/16/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01040 |
RPL10.EY.NS3 - Install Tent Final Grading | Tent and Temp Conditions | Complete | 02/10/26 | 02/11/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01480 |
RPL10.EY.SSB - Install LD F/R/P Temp Paving | Loading Dock | Complete | 02/10/26 | 02/11/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06840 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Tape, Float and Paint (West Side) (02.17.26) | Priority Wall (P3) - Grid Line 10-25 | Complete | 02/10/26 | 02/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01030 |
RPL10.Interior.EF2 - Priority OH - Install Fire Sprinkler | OverHead | Complete | 02/10/26 | 02/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2280 |
RPL10.MCUP.Loop 2 - Set mCup #4 - Dry Coolers (6) (4 per week) | OFE | Complete | 02/10/26 | 02/11/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2380 |
RPL10.MCUP.Loop 2 - Set mCup #8 Facility water piping rack | OFE | Complete | 02/10/26 | 02/17/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.01300 |
RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Structural Framing & EJ | Expansion Joint Delay Event | Complete | 02/10/26 | 02/11/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01100 |
RPL10.SKIN.SSB - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ | Roofing | Complete | 02/10/26 | 02/11/26 | 2.5 | 0.0 |
|
0.0 |
ICM.B10.1865 |
[NWB] Delivery of MDF - GS.MDF Module (First Delivery) - RPL10 | Construction | Complete | 02/11/26 | 02/11/26 | 0.0 | 0.0 |
|
0.0 |
NW.1240 |
Dry Cooler 230 Ton Crane Movement 03 - Finish | 230 Ton Crane (Dry Cooler) | Complete | 02/11/26 | 02/11/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01090 |
RPL10.EY.SSB - Install GS.IDF Hut (1x GS.IDF) NX05 (02.11.26) | OFE | Complete | 02/11/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01100 |
RPL10.EY.SSB - OFE - WBS Summary | OFE | Complete | 02/11/26 | 03/27/26 | 47.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07420 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall MEP Backing/In-Wall Rough Ins (EF1 & EF2) | EF Perimeter Walls | Complete | 02/11/26 | 03/04/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01710 |
RPL10.Interior.EF2 - Priority OH - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall | OverHead | Complete | 02/11/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01140 |
RPL10.Structure.EF12 - Zone SOG Cure | F/R/P | Complete | 02/11/26 | 02/13/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01300 |
RPL10.Structure.NS12 - PSI SOG F/R/P with Plumbing/Slab Remediation Grid lines 10-24/10-25 &10-36/37 | F/R/P | Complete | 02/11/26 | 02/20/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01100 |
RPL10.Structure.NS43 - SOG F/R/P (Pour #19 -01/27 & #20 -01/29) - Grid lines 10-10/10-07 | F/R/P | Complete | 02/11/26 | 02/13/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01110 |
RPL10.Structure.NS43 - SOG F/R/P - WBS Summary | F/R/P | Complete | 02/11/26 | 04/10/26 | 51.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01080 |
RPL10.EY.NS2 - Tent SOG Cure | Tent and Temp Conditions | Complete | 02/12/26 | 02/16/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01150 |
RPL10.Interior.SSB - BoW - Frame Remaining Balance Of Walls | Balance of Walls and OverHead | Complete | 02/12/26 | 03/11/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01090 |
RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF NS1) (02.12.26) | OFE | Complete | 02/12/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01140 |
RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF NS2) (02.12.26) | OFE | Complete | 02/12/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03640 |
RPL10.Interior.SSB-Corridor - Priority - Priority Soffit Hang Drywall, Tape Finish Paint (All Soffit)- New*** | Priority Walls & OverHead | Complete | 02/12/26 | 03/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03700 |
RPL10.Interior.SSB-Corridor - Priority - QC - P2 Wall - Backing/Wall | Priority Wall (P2) - Grid Line 10-38 | Complete | 02/12/26 | 02/13/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1240 |
RPL10.MCUP.Loop 2 - Set MTRs (4 per day) | OFE | Complete | 02/12/26 | 02/19/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.SKN.01320 |
RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Dry In EJ | Expansion Joint Delay Event | Complete | 02/12/26 | 02/12/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01140 |
RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-10/10-01(9) (with temp closures for openings) | North | Complete | 02/12/26 | 02/13/26 | 2.5 | 0.0 |
|
0.0 |