Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
94
Completed
6
In Progress
94
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.STR.NS43.01060 RPL10.Structure.NS43 - Adjust Drains\Clean Outs\Stubups and Grounding wire Prep Complete 02/02/26 02/06/26 6.2 0.0
100%
0.0
RPL10.STR.NS43.01070 RPL10.Structure.NS43 - Install Remaining UG and Subgrade Prep - WBS Summary Prep Complete 02/02/26 02/20/26 8.8 0.0
100%
0.0
GCD.RPL10.1280 Interior fit-out Start RPL10 - NS12 Construction Milestones Complete 02/03/26 02/03/26 0.0 0.0
100%
0.0
NW.2120 Weather Event #9 - 02/03/26 Project Impacts Complete 02/03/26 02/03/26 1.2 0.0
100%
0.0
RPL10.INT.NS1.01010 RPL10.Interior.NS1 - Priority - Install Duct OverHead Complete 02/03/26 02/20/26 18.8 0.0
100%
0.0
RPL10.INT.NS1.02080 RPL10.Interior.NS1 - Priority - Install Plumbing/Mechanical Piping OverHead Complete 02/03/26 02/09/26 3.8 0.0
100%
0.0
NW.1060 MCUP 600 Ton Crane Movement 3 600 Ton Crane (MCUP) Complete 02/04/26 02/04/26 0.0 0.0
100%
0.0
RPL10.EY.NS1.01110 RPL10.EY.NS1 - Install Tent Tent and Temp Conditions Complete 02/04/26 03/06/26 25.0 0.0
100%
0.0
RPL10.EY.NS2.01015 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 9-15 (Grid 10-32/10-42) (12'' Larger For Tolerance) Foundations Complete 02/04/26 02/06/26 20.0 0.0
100%
0.0
RPL10.EY.NS2.01040 RPL10.EY.NS2 - Install Tent Final Grading Tent and Temp Conditions Complete 02/04/26 02/05/26 2.5 0.0
100%
0.0
RPL10.EY.NS4.01000 RPL10.EY.NS4 - Install Shallow Tent UG Tent and Temp Conditions Complete 02/04/26 02/05/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.01750 RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint Priority Soffit, Fire Safing Both Sides (All CC & EF) Priority Walls & OverHead Complete 02/04/26 03/13/26 18.8 0.0
100%
0.0
RPL10.INT.CTRC.06800 RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall (West Side) Priority Wall (P3) - Grid Line 10-25 Complete 02/04/26 02/13/26 5.0 0.0
100%
0.0
RPL10.INT.EF1.01010 RPL10.Interior.EF1 - Priority OH - WBS Summary OverHead Active 02/04/26 05/29/26 102.5 42.5
0%
136.2
RPL10.INT.EF1.01020 RPL10.Interior.EF1 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary EF1 Active 02/04/26 07/24/26 151.2 91.2
0%
158.8
RPL10.INT.EF1.01040 RPL10.Interior.EF1 - Priority OH - Install Temp Lighting OverHead Complete 02/04/26 02/05/26 3.8 0.0
100%
0.0
RPL10.INT.NS1.02360 RPL10.Interior.NS1 - Priority - Install Drywall at Exterior Wall OverHead Complete 02/04/26 02/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.03140 RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (Post WI#09) OverHead Complete 02/04/26 02/27/26 15.0 0.0
100%
0.0
RPL10.INT.NS2.02360 RPL10.Interior.NS2 - Priority - Install Security OverHead Complete 02/04/26 02/05/26 2.5 0.0
100%
0.0
RPL10.INT.NS2.03265 RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (Post WI#09) OverHead Complete 02/04/26 02/27/26 15.0 0.0
100%
0.0
RPL10.INT.SSB.04120 RPL10.Interior.SSB - Priority - P5 Frame Remaining Wall (South) Priority Wall (P5) - Grid Line 10-C Complete 02/04/26 02/06/26 3.0 0.0
100%
0.0
RPL10.INT.SSBC.01080 RPL10.Interior.SSB-Corridor - BoW - Install Doors Frame Balance of Walls & OverHead Complete 02/04/26 02/06/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.03500 RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - MEP In-Wall Balance of Walls & OverHead Complete 02/04/26 02/06/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.04040 RPL10.Interior.SSB-Corridor - Priority - Install Cementitious Spray to Deck - (Post WI#09) Priority Walls & OverHead Complete 02/04/26 02/06/26 25.0 0.0
100%
0.0
RPL10.MCUP.LP1.1380 RPL10.MCUP.Loop 1 - Set mCUPs #3 (1 per 5 days) OFE Complete 02/04/26 02/09/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1340 RPL10.MCUP.Loop 2 - Remaining Electrical F/R/P Pads 4 (12'' larger) Foundations Complete 02/04/26 02/27/26 17.5 0.0
100%
0.0
RPL10.MCUP.LP2.2340 RPL10.MCUP.Loop 2 - Set mCup #4 Facility water piping rack OFE Complete 02/04/26 02/05/26 15.0 0.0
100%
0.0
RPL10.MCUP.LP2.2540 RPL10.MCUP.Loop 2 - F/R/P Pads (12'' larger) (Post WI#09) Foundations Complete 02/04/26 02/27/26 25.0 0.0
100%
0.0
RPL10.SKN.01360 RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Install Bent Plate & Gusset Plates (Post WI#09) Expansion Joint Delay Event Complete 02/04/26 02/09/26 1.2 0.0
100%
0.0
RPL10.SKN.N.01240 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10(7) (Post WI#09) North Complete 02/04/26 02/09/26 2.5 0.0
100%
0.0
RPL10.STR.NS43.01080 RPL10.Structure.NS43 - Install AB final grade and Vapor Barrier Prep Complete 02/04/26 02/20/26 6.2 0.0
100%
0.0
RPL10.EY.NS4.01040 RPL10.EY.NS4 - Install Final Grading Tent and Temp Conditions Complete 02/05/26 02/06/26 2.5 0.0
100%
0.0
RPL10.EY.SSB.01440 RPL10.EY.SSB - Dig Walls Loading Dock Complete 02/05/26 02/06/26 5.0 0.0
100%
0.0
RPL10.INT.EF1.01030 RPL10.Interior.EF1 - Priority OH - Install Fire Sprinkler OverHead Complete 02/05/26 02/12/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01730 RPL10.Interior.EF1 - Priority OH - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/05/26 03/09/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01120 RPL10.Interior.NS1 - Priority - Install Security OverHead Complete 02/05/26 02/06/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01170 RPL10.Interior.NS1 - Priority - Install Fire Life Safety (Sprinkler Drops) OverHead Complete 02/05/26 02/11/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.02820 RPL10.Interior.SSB-Corridor - BoW - Install Backing BoW Balance of Walls & OverHead Complete 02/05/26 02/19/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.03660 RPL10.Interior.SSB-Corridor - BoW - Install Remaining Unistruts & Hangers Balance of Walls & OverHead Complete 02/05/26 02/13/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1360 RPL10.MCUP.Loop 1 - Set Electrical Skids #1 OFE Complete 02/05/26 02/05/26 1.2 0.0
100%
0.0
RPL10.MCUP.LP2.2360 RPL10.MCUP.Loop 2 - Set mCup #6 Facility water piping rack OFE Complete 02/05/26 02/06/26 12.5 0.0
100%
0.0
RPL10.STR.NS43.01090 RPL10.Structure.NS43 - Asphalt Emulsion and Wrap Steel Columns Prep Complete 02/05/26 02/20/26 3.8 0.0
100%
0.0
ICM.B10.1750 [NWB] Room Ready for GS.MDF Module Placement - RPL10 Construction Complete 02/06/26 02/06/26 0.0 0.0
100%
0.0
NW.1220 Dry Cooler 230 Ton Crane Movement 03 - Start 230 Ton Crane (Dry Cooler) Complete 02/06/26 02/06/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01540 RPL10.EY.EF1 - Install F/R/P Remaining Equipment Pads for GSB & IDF Huts Foundations Complete 02/06/26 02/09/26 2.5 0.0
100%
0.0
RPL10.EY.EF2.01730 RPL10.EY.EF2 - Install F/R/P Remaining Equipment Pads for GSB Foundations Complete 02/06/26 02/09/26 2.5 0.0
100%
0.0
RPL10.EY.NS2.01050 RPL10.EY.NS2 - Install Tent F/R/P SOG (30k Mock Up) Tent and Temp Conditions Complete 02/06/26 02/11/26 6.2 0.0
100%
0.0
RPL10.EY.NS3.01000 RPL10.EY.NS3 - Install Shallow Tent UG Tent and Temp Conditions Complete 02/06/26 02/09/26 3.8 0.0
100%
0.0
RPL10.EY.SSB.01230 RPL10.EY.SSB - Install LD F/R/P Loading Dock Walls Loading Dock Complete 02/06/26 02/09/26 10.0 0.0
100%
0.0
RPL10.INT.CTRC.01050 RPL10.Interior.Center-Corridor - Priority - Frame Perimeter Remaining Walls (EF1 & EF2) EF Perimeter Walls Complete 02/06/26 02/17/26 10.0 0.0
100%
0.0
RPL10.INT.CTRC.02380 RPL10.Interior.Center-Corridor - Priority - P4 Frame Remaining Wall (EF2 Wall Along Grid 10-D) Priority Wall (P4) - Grid Line 10-D Complete 02/06/26 02/12/26 6.2 0.0
100%
0.0
RPL10.INT.EF2.01010 RPL10.Interior.EF2 - Install Priority OH - WBS Summary OverHead Active 02/06/26 06/11/26 108.8 50.0
0%
136.2
RPL10.INT.EF2.01020 RPL10.Interior.EF2 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary EF2 Active 02/06/26 08/11/26 161.2 106.2
0%
156.2
RPL10.INT.EF2.01040 RPL10.Interior.EF2 - Priority OH - Install Temp Lighting OverHead Complete 02/06/26 02/10/26 3.8 0.0
100%
0.0
RPL10.INT.EF2.01070 RPL10.Interior.EF2 - Priority - WBS Summary OverHead Active 02/06/26 06/11/26 108.8 50.0
0%
136.2
RPL10.MCUP.LP1.1520 RPL10.MCUP.Loop 1 - Set Electrical Skids #3 OFE Complete 02/06/26 02/06/26 1.2 0.0
100%
0.0
RPL10.MCUP.LP2.1220 RPL10.MCUP.Loop 2 - Set mCup #2 - Dry Coolers (6) (4 per week) OFE Complete 02/06/26 02/09/26 7.5 0.0
100%
0.0
RPL10.SKN.SSB.01350 RPL10.SKIN.SSB - PSI Install Rework DenseDeck & Peel & Stick (Grid 10-42 / 10-30) Roofing Remediation 10-42 / 10-30 Complete 02/06/26 03/13/26 10.0 0.0
100%
0.0
RPL10.STR.EF12.01130 RPL10.Structure.EF12 - SOG F/R/P Pour #17 -01/22 & #18 -01/24) - Grid lines 10-14/10-10 F/R/P Complete 02/06/26 02/10/26 3.8 0.0
100%
0.0
RPL10.EY.SSB.01000 RPL10.EY.SSB - Install F/R/P Equipment Pads Foundations Complete 02/09/26 02/13/26 6.2 0.0
100%
0.0
RPL10.EY.SSB.01010 RPL10.EY.SSB - Install Foundations - WBS Summary Foundations Complete 02/09/26 02/20/26 13.8 0.0
100%
0.0
RPL10.EY.SSB.01460 RPL10.EY.SSB - Set LD Strip Walls/ Backfill /Grade Loading Dock Complete 02/09/26 02/10/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01340 RPL10.Interior.Center-Corridor - Priority - F/R/P Pads Priority Walls & OverHead Complete 02/09/26 02/11/26 3.8 0.0
100%
0.0
RPL10.INT.NS1.01050 RPL10.Interior.NS1 - Priority - Install FA / Linear heat detection OverHead Complete 02/09/26 02/27/26 2.5 0.0
100%
0.0
RPL10.INT.SSBC.03480 RPL10.Interior.SSB-Corridor - Priority - SSB Electrical Room - Hang Drywall & Tape Float Paint (02.17.26) Balance of Walls & OverHead Complete 02/09/26 02/13/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1500 RPL10.MCUP.Loop 1 - Set mCUPs #5 (1 per 5 days) OFE Complete 02/09/26 02/13/26 2.5 0.0
100%
0.0
RPL10.SKN.E.01040 RPL10.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin East Complete 02/09/26 02/13/26 6.2 0.0
100%
0.0
RPL10.SKN.NS43.01010 RPL10.SKIN.NS43 - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary NS4 & NS3 Active 02/09/26 01/27/27 302.5 173.8
0%
77.5
RPL10.SKN.NS43.01080 RPL10.SKIN.NS43 - Install Roof System - WBS Summary Roofing Complete 02/09/26 03/30/26 48.8 0.0
100%
0.0
RPL10.SKN.NS43.01090 RPL10.SKIN.NS43 - Install Roof System - DenseDeck & Peel & Stick Roofing Complete 02/09/26 02/24/26 6.2 0.0
100%
0.0
RPL10.SKN.SSB.01130 RPL10.SKIN.SSB - Install Roof System - Final Roof (Grid 10-42 / 10-30) Roofing Complete 02/09/26 03/13/26 13.8 0.0
100%
0.0
RPL10.EY.EF1.01030 RPL10.EY.EF1 - Cure (High Early Mix) Foundations Complete 02/10/26 02/16/26 8.8 0.0
100%
0.0
RPL10.EY.EF2.01070 RPL10.EY.EF2 - Cure (High Early Mix) Foundations Complete 02/10/26 02/16/26 8.8 0.0
100%
0.0
RPL10.EY.NS3.01040 RPL10.EY.NS3 - Install Tent Final Grading Tent and Temp Conditions Complete 02/10/26 02/11/26 2.5 0.0
100%
0.0
RPL10.EY.SSB.01480 RPL10.EY.SSB - Install LD F/R/P Temp Paving Loading Dock Complete 02/10/26 02/11/26 10.0 0.0
100%
0.0
RPL10.INT.CTRC.06840 RPL10.Interior.Center-Corridor - Priority - P3 Wall Tape, Float and Paint (West Side) (02.17.26) Priority Wall (P3) - Grid Line 10-25 Complete 02/10/26 02/18/26 6.2 0.0
100%
0.0
RPL10.INT.EF2.01030 RPL10.Interior.EF2 - Priority OH - Install Fire Sprinkler OverHead Complete 02/10/26 02/12/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.2280 RPL10.MCUP.Loop 2 - Set mCup #4 - Dry Coolers (6) (4 per week) OFE Complete 02/10/26 02/11/26 7.5 0.0
100%
0.0
RPL10.MCUP.LP2.2380 RPL10.MCUP.Loop 2 - Set mCup #8 Facility water piping rack OFE Complete 02/10/26 02/17/26 12.5 0.0
100%
0.0
RPL10.SKN.01300 RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Structural Framing & EJ Expansion Joint Delay Event Complete 02/10/26 02/11/26 2.5 0.0
100%
0.0
RPL10.SKN.SSB.01100 RPL10.SKIN.SSB - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ Roofing Complete 02/10/26 02/11/26 2.5 0.0
100%
0.0
ICM.B10.1865 [NWB] Delivery of MDF - GS.MDF Module (First Delivery) - RPL10 Construction Complete 02/11/26 02/11/26 0.0 0.0
100%
0.0
NW.1240 Dry Cooler 230 Ton Crane Movement 03 - Finish 230 Ton Crane (Dry Cooler) Complete 02/11/26 02/11/26 0.0 0.0
100%
0.0
RPL10.EY.SSB.01090 RPL10.EY.SSB - Install GS.IDF Hut (1x GS.IDF) NX05 (02.11.26) OFE Complete 02/11/26 02/13/26 6.2 0.0
100%
0.0
RPL10.EY.SSB.01100 RPL10.EY.SSB - OFE - WBS Summary OFE Complete 02/11/26 03/27/26 47.5 0.0
100%
0.0
RPL10.INT.CTRC.07420 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall MEP Backing/In-Wall Rough Ins (EF1 & EF2) EF Perimeter Walls Complete 02/11/26 03/04/26 6.2 0.0
100%
0.0
RPL10.INT.EF2.01710 RPL10.Interior.EF2 - Priority OH - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/11/26 03/09/26 6.2 0.0
100%
0.0
RPL10.STR.EF12.01140 RPL10.Structure.EF12 - Zone SOG Cure F/R/P Complete 02/11/26 02/13/26 8.8 0.0
100%
0.0
RPL10.STR.NS12.01300 RPL10.Structure.NS12 - PSI SOG F/R/P with Plumbing/Slab Remediation Grid lines 10-24/10-25 &10-36/37 F/R/P Complete 02/11/26 02/20/26 3.8 0.0
100%
0.0
RPL10.STR.NS43.01100 RPL10.Structure.NS43 - SOG F/R/P (Pour #19 -01/27 & #20 -01/29) - Grid lines 10-10/10-07 F/R/P Complete 02/11/26 02/13/26 3.8 0.0
100%
0.0
RPL10.STR.NS43.01110 RPL10.Structure.NS43 - SOG F/R/P - WBS Summary F/R/P Complete 02/11/26 04/10/26 51.2 0.0
100%
0.0
RPL10.EY.NS2.01080 RPL10.EY.NS2 - Tent SOG Cure Tent and Temp Conditions Complete 02/12/26 02/16/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.01150 RPL10.Interior.SSB - BoW - Frame Remaining Balance Of Walls Balance of Walls and OverHead Complete 02/12/26 03/11/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.01090 RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF NS1) (02.12.26) OFE Complete 02/12/26 02/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01140 RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF NS2) (02.12.26) OFE Complete 02/12/26 02/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03640 RPL10.Interior.SSB-Corridor - Priority - Priority Soffit Hang Drywall, Tape Finish Paint (All Soffit)- New*** Priority Walls & OverHead Complete 02/12/26 03/13/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03700 RPL10.Interior.SSB-Corridor - Priority - QC - P2 Wall - Backing/Wall Priority Wall (P2) - Grid Line 10-38 Complete 02/12/26 02/13/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.1240 RPL10.MCUP.Loop 2 - Set MTRs (4 per day) OFE Complete 02/12/26 02/19/26 7.5 0.0
100%
0.0
RPL10.SKN.01320 RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Dry In EJ Expansion Joint Delay Event Complete 02/12/26 02/12/26 1.2 0.0
100%
0.0
RPL10.SKN.N.01140 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-10/10-01(9) (with temp closures for openings) North Complete 02/12/26 02/13/26 2.5 0.0
100%
0.0