Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
81
Completed
19
In Progress
81
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
GCD.RPL10.5925 |
Temp Dry In SSB and NS12 | Construction Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
NW.1260 |
Dry Cooler 230 Ton Crane Movement 04 - Start | 230 Ton Crane (Dry Cooler) | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3850.XG |
Ready for MV Cable Pull NS 1 (Loop 1) | Give Milestones (XREFs) | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3855.XG |
Ready for MV Cable Pull NS 1 (Loop 2) | Give Milestones (XREFs) | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5640.XR |
Ahsoka Road | Logistics - Onsite Receive XREF Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5680.XR |
This is the way | Logistics - Onsite Receive XREF Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5720.XR |
Ewok Way | Logistics - Onsite Receive XREF Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5745.XR |
Droid Drive | Logistics - Onsite Receive XREF Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5920.XR |
Wade East | Logistics - Onsite Receive XREF Milestones | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.N0590.XG |
GS.IDF Hut Install Complete (11, 12, 13, 05) | Give Milestones (XREFs) | Complete | 02/13/26 | 02/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01050 |
RPL10.EY.SSB - Foundation Cure (High Early Mix) | Foundations | Complete | 02/13/26 | 02/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01520 |
RPL10.EY.SSB - Install Temp Condition Units and Temp Ducts | OFE | Complete | 02/13/26 | 02/24/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02400 |
RPL10.Interior.Center-Corridor - Priority - P4 MEP In-Wall/Backing (EF2 Wall Along Grid 10-D) | Priority Wall (P4) - Grid Line 10-D | Complete | 02/13/26 | 02/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03500 |
RPL10.Interior.SSB - Priority - P0 & P1 Wall Hang Drywall (East Sides) | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 02/13/26 | 03/12/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02500 |
RPL10.Interior.SSB-Corridor - Priority - Install Exterior Wall MEP Surface Mounted Rough-Ins | Priority Walls & OverHead | Complete | 02/13/26 | 02/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1640 |
RPL10.MCUP.Loop 1 - Set Electrical Skids #5 | OFE | Complete | 02/13/26 | 02/13/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1180 |
RPL10.MCUP.Loop 2 - Cure for Pads | Foundations | Complete | 02/13/26 | 03/04/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1260 |
RPL10.MCUP.Loop 2 - Set mCup #6 - Dry Coolers (6) (4 per week) | OFE | Complete | 02/13/26 | 02/17/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01090 |
RPL10.SKIN.NS12 - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ | Roofing | Complete | 02/13/26 | 02/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01130 |
RPL10.EY.NS2 - Cure (High Early Mix) | Foundations | Complete | 02/15/26 | 02/21/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01120 |
RPL10.EY.EF1 - Install Electrical Panels (2) (GSB and LB Equipment) | OFE | Complete | 02/16/26 | 02/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01770 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Hang Drywall (Inside) (EF1 & EF2) | EF Perimeter Walls | Complete | 02/16/26 | 02/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01890 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Inside) (EF1 & EF2) | EF Perimeter Walls | Complete | 02/16/26 | 03/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02320 |
RPL10.Interior.NS1 - Priority - Exterior Wall Tape, Float and Paint NS1 (sanding off hours) *02/16 | OverHead | Complete | 02/16/26 | 02/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02720 |
RPL10.Interior.SSB-Corridor - Priority - P2 Wall Hang Drywall (Both Sides) | Priority Wall (P2) - Grid Line 10-38 | Complete | 02/16/26 | 02/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1620 |
RPL10.MCUP.Loop 1 - Set mCUPs #7 (1 per 5 days) | OFE | Complete | 02/16/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01120 |
RPL10.Structure.NS43 - SOG F/R/P (Pour #21 -01/31 & #22 -02/03) - Grid lines 10-07/10-04 | F/R/P | Complete | 02/16/26 | 02/17/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01030 |
RPL10.Structure.SSB - Install Storm Shelter F/R/P Deck | Storm Shelter | Complete | 02/16/26 | 02/18/26 | 3.8 | 0.0 |
|
0.0 |
ICM.B10.1840 |
[NWB] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) | Construction | Complete | 02/17/26 | 02/17/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C54X0.XR |
Logistics Area #10 - Complete | Logistics - Area Turnovers XREF Milestones | Complete | 02/17/26 | 02/17/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01590 |
RPL10.EY.EF2 - Install Remaining Electrical Panels (2) (GSB and LB Equipment) | OFE | Complete | 02/17/26 | 02/17/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01090 |
RPL10.EY.NS2 - Install Tent | Tent and Temp Conditions | Complete | 02/17/26 | 03/30/26 | 26.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01530 |
RPL10.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) | Priority Walls & OverHead | Complete | 02/17/26 | 03/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01550 |
RPL10.Interior.Center-Corridor - Priority - Install Mechanical Piping (Highside OH space) | Priority Walls & OverHead | Complete | 02/17/26 | 03/09/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02420 |
RPL10.Interior.Center-Corridor - Priority - P4 Hang Drywall (EF2 Wall Along Grid 10-D) | Priority Wall (P4) - Grid Line 10-D | Complete | 02/17/26 | 03/05/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01100 |
RPL10.Interior.NS1 - Priority - Install Temp Doors Frame Hardware | OverHead | Complete | 02/17/26 | 02/19/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01000 |
RPL10.Interior.NS3 - Priority - WBS Summary | OverHead | Active | 02/17/26 | 04/21/26 | 53.8 | 8.8 |
|
153.8 |
RPL10.INT.NS3.01020 |
RPL10.Interior.NS3 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | NS3 | Active | 02/17/26 | 01/26/27 | 291.2 | 247.5 |
|
120.0 |
RPL10.INT.NS3.01030 |
RPL10.Interior.NS3 - Priority - Install Fire Sprinkler | OverHead | Complete | 02/17/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01000 |
RPL10.Interior.NS4 - Priority - WBS Summary | OverHead | Active | 02/17/26 | 04/21/26 | 57.5 | 8.8 |
|
133.8 |
RPL10.INT.NS4.01020 |
RPL10.Interior.NS4 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | NS4 | Active | 02/17/26 | 01/06/27 | 278.8 | 231.2 |
|
123.8 |
RPL10.INT.NS4.01030 |
RPL10.Interior.NS4 - Priority - Install Fire Sprinkler *(02/18) | OverHead | Complete | 02/17/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01170 |
RPL10.Interior.SSB - Loading Dock and Storage - WBS Summary | Loading Dock and Storage | Active | 02/17/26 | 07/29/26 | 142.5 | 92.5 |
|
146.2 |
RPL10.INT.SSB.01510 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Door Frames | Loading Dock and Storage | Complete | 02/17/26 | 02/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02660 |
RPL10.Interior.SSB-Corridor - BoW - Frame Hard Lid | Balance of Walls & OverHead | Complete | 02/17/26 | 02/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1400 |
RPL10.MCUP.Loop 1 - Tie-ins - WBS Summary | Tie-ins | Active | 02/17/26 | 05/21/26 | 83.8 | 36.2 |
|
17.5 |
RPL10.MCUP.LP1.1440 |
RPL10.MCUP.Loop 1 - Tie-in Mechanical (LOE) | Tie-Ins Mechanical | Active | 02/17/26 | 04/27/26 | 40.0 | 13.8 |
|
28.8 |
RPL10.MCUP.LP1.1460 |
RPL10.MCUP.Loop 1 - Tie-in Mechanical #1 WBS Summary | Tie-in Mechanical #1 | Active | 02/17/26 | 04/15/26 | 13.8 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.1760 |
RPL10.MCUP.Loop 1 - Tie-in Mechanical #3 WBS Summary | Tie-in Mechanical #3 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.1880 |
RPL10.MCUP.Loop 1 - Tie-in Mechanical #5 WBS Summary | Tie-in Mechanical #5 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2580 |
RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #1 | Tie-in Mechanical #1 | Active | 02/17/26 | 04/15/26 | 13.8 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2600 |
RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #1 | Tie-in Mechanical #1 | Active | 02/17/26 | 04/15/26 | 13.8 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2620 |
RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #3 | Tie-in Mechanical #3 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2640 |
RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #3 | Tie-in Mechanical #3 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2660 |
RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #5 | Tie-in Mechanical #5 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP1.2680 |
RPL10.MCUP.Loop 1 - Condenser Tie-in Mechanical #5 | Tie-in Mechanical #5 | Active | 02/17/26 | 04/15/26 | 11.2 | 3.8 |
|
23.8 |
RPL10.MCUP.LP2.2300 |
RPL10.MCUP.Loop 2 - Set mCup #8 - Dry Coolers (6) (4 per week) | OFE | Complete | 02/17/26 | 02/19/26 | 7.5 | 0.0 |
|
0.0 |
RPL.10.D.X3870.XG |
Ready for MV Cable Pull NS 4 (Loop 1) | Give Milestones (XREFs) | Complete | 02/18/26 | 02/18/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3875.XG |
Ready for MV Cable Pull NS 4 (Loop 2) | Give Milestones (XREFs) | Complete | 02/18/26 | 02/18/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.7080 |
RPL10 - Submittal Rvw/App'l - Scuppers | Fixed Louvers | Complete | 02/18/26 | 03/18/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01170 |
RPL10.EY.NS2 - Install Tent Fit-out | Tent and Temp Conditions | Complete | 02/18/26 | 03/30/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01200 |
RPL10.Interior.Center-Corridor - OFE - NS2 (1x GS.IDF) N23 (02.18.26) | OFE | Complete | 02/18/26 | 02/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02420 |
RPL10.Interior.NS2 - Priority - Install Temp Doors Frame Hardware | OverHead | Complete | 02/18/26 | 02/20/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04200 |
RPL10.Interior.SSB - Priority - P5 Backing Remaining Wall | Priority Wall (P5) - Grid Line 10-C | Complete | 02/18/26 | 02/25/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06960 |
RPL10.Interior.SSB - BoW - Hang Drywall, Tape Float Paint (Early Work) | Balance of Walls and OverHead | Complete | 02/18/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01060 |
RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) (02.18.26) | OFE | Complete | 02/18/26 | 02/20/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01100 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall | Balance of Walls & OverHead | Complete | 02/18/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01120 |
RPL10.Interior.SSB-Corridor - BoW - Controls / EPMS / BMS OH and In-Wall | Balance of Walls & OverHead | Complete | 02/18/26 | 03/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01130 |
RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Lowside OH and In-Wall | Balance of Walls & OverHead | Complete | 02/18/26 | 03/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02640 |
RPL10.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & OverHead | Complete | 02/18/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01140 |
RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-10/10-1 (11) (with temp closures for openings) | South | Complete | 02/18/26 | 02/27/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01130 |
RPL10.Structure.NS43 - SOG F/R/P (Pour #23 -02/05 & #24 -02/07) - Grid Lines 10-04/10-01 | F/R/P | Complete | 02/18/26 | 02/20/26 | 5.0 | 0.0 |
|
0.0 |
NW.1280 |
Dry Cooler 230 Ton Crane Movement 04 - Finish | 230 Ton Crane (Dry Cooler) | Complete | 02/19/26 | 02/19/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01130 |
RPL10.EY.NS3 - Cure (High Early Mix) | Foundations | Complete | 02/19/26 | 02/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01120 |
RPL10.EY.NS4 - Cure (High Early Mix) | Foundations | Complete | 02/19/26 | 02/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01130 |
RPL10.Interior.Center-Corridor - OFE - NS1 (1x GS.IDF) N13 (02.18.26) | OFE | Complete | 02/19/26 | 02/25/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02300 |
RPL10.Interior.NS4 - Priority - Install IMP Exterior In-Wall Rough-Ins | OverHead | Complete | 02/19/26 | 02/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04140 |
RPL10.Interior.SSB - Priority - P5 MEP Remaining Wall In-wall | Priority Wall (P5) - Grid Line 10-C | Complete | 02/19/26 | 02/27/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04220 |
RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 02/19/26 | 03/09/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06940 |
RPL10.Interior.SSB - Priority - P5 Frame Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 02/19/26 | 02/23/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06980 |
RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 02/19/26 | 03/09/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1680 |
RPL10.MCUP.Loop 1 - Set Electrical Skids #7 | OFE | Complete | 02/19/26 | 02/19/26 | 1.2 | 0.0 |
|
0.0 |
NW.1300 |
Dry Cooler 230 Ton Crane Demobilization | 230 Ton Crane (Dry Cooler) | Complete | 02/20/26 | 02/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X2110.XG |
Trestle Construction Ready - East - RPL10 | Give Milestones (XREFs) | Complete | 02/20/26 | 02/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3750.XG |
RMUs/MV Skids Set - mCUP North | Give Milestones (XREFs) | Complete | 02/20/26 | 02/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3890.XG |
Ready for MV Cable Pull mCUP North Loop (Loop#1) | Give Milestones (XREFs) | Complete | 02/20/26 | 02/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01190 |
RPL10.Interior.Center-Corridor - OFE - EF1 (1x GS.IDF) NE1 (02.18.26) | OFE | Complete | 02/20/26 | 02/26/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06880 |
RPL10.Interior.Center-Corridor - Priority - QC - P3 Wall - Backing/In-Wall | Priority Wall (P3) - Grid Line 10-25 | Complete | 02/20/26 | 02/23/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06900 |
RPL10.Interior.Center-Corridor - Priority - P6 Frame Remaining Wall | Priority Wall (P6) - Grid Line 10-16 | Complete | 02/20/26 | 02/26/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01050 |
RPL10.Interior.NS2 - Priority - Install FA / Linear heat detection | OverHead | Complete | 02/20/26 | 02/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02400 |
RPL10.Interior.NS2 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 02/20/26 | 03/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01040 |
RPL10.Interior.NS3 - Priority - Install Temp Lighting | OverHead | Complete | 02/20/26 | 03/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01040 |
RPL10.Interior.NS4 - Priority - Install Temp Lighting | OverHead | Complete | 02/20/26 | 03/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01110 |
RPL10.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-Wall | Balance of Walls & OverHead | Complete | 02/20/26 | 03/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2560 |
RPL10.MCUP.Loop 1 - Set Remaining Facility water piping rack with All Racks Welding | OFE | Active | 02/20/26 | 04/15/26 | 2.5 | 3.8 |
|
17.5 |
RPL10.MCUP.LP2.1380 |
RPL10.MCUP.Loop 2 - Cure for Remaining Electrical Pads | Foundations | Complete | 02/20/26 | 03/04/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01140 |
RPL10.Structure.NS43 - Zone SOG Cure | F/R/P | Complete | 02/20/26 | 02/26/26 | 8.8 | 0.0 |
|
0.0 |
GCD.RPL10.3727 |
[RPL10] TC Ready: All General Services [RPL10-MDFs] | TC Ready: General Services | Complete | 02/23/26 | 02/23/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4620 |
RPL10 - Prep / Submit for Review -Epoxy Flooring (Spec 09 67 23) | (CFCI) Div. 09 - Epoxy Flooring | Active | 02/23/26 | 04/13/26 | 25.0 | 1.2 |
|
146.2 |
RPL10.CFCI.4810 |
RPL10 - Prep / Submit for Review - Specialities | (CFCI) Div. 10 - Specialities | Active | 02/23/26 | 04/13/26 | 25.0 | 1.2 |
|
113.8 |