Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
81
Completed
19
In Progress
81
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
GCD.RPL10.5925 Temp Dry In SSB and NS12 Construction Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
NW.1260 Dry Cooler 230 Ton Crane Movement 04 - Start 230 Ton Crane (Dry Cooler) Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.10.D.X3850.XG Ready for MV Cable Pull NS 1 (Loop 1) Give Milestones (XREFs) Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.10.D.X3855.XG Ready for MV Cable Pull NS 1 (Loop 2) Give Milestones (XREFs) Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.CM.D.C5640.XR Ahsoka Road Logistics - Onsite Receive XREF Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.CM.D.C5680.XR This is the way Logistics - Onsite Receive XREF Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.CM.D.C5720.XR Ewok Way Logistics - Onsite Receive XREF Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.CM.D.C5745.XR Droid Drive Logistics - Onsite Receive XREF Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.CM.D.C5920.XR Wade East Logistics - Onsite Receive XREF Milestones Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL.GF.D.N0590.XG GS.IDF Hut Install Complete (11, 12, 13, 05) Give Milestones (XREFs) Complete 02/13/26 02/13/26 0.0 0.0
100%
0.0
RPL10.EY.SSB.01050 RPL10.EY.SSB - Foundation Cure (High Early Mix) Foundations Complete 02/13/26 02/20/26 8.8 0.0
100%
0.0
RPL10.EY.SSB.01520 RPL10.EY.SSB - Install Temp Condition Units and Temp Ducts OFE Complete 02/13/26 02/24/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.02400 RPL10.Interior.Center-Corridor - Priority - P4 MEP In-Wall/Backing (EF2 Wall Along Grid 10-D) Priority Wall (P4) - Grid Line 10-D Complete 02/13/26 02/23/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.03500 RPL10.Interior.SSB - Priority - P0 & P1 Wall Hang Drywall (East Sides) Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 02/13/26 03/12/26 7.5 0.0
100%
0.0
RPL10.INT.SSBC.02500 RPL10.Interior.SSB-Corridor - Priority - Install Exterior Wall MEP Surface Mounted Rough-Ins Priority Walls & OverHead Complete 02/13/26 02/17/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1640 RPL10.MCUP.Loop 1 - Set Electrical Skids #5 OFE Complete 02/13/26 02/13/26 1.2 0.0
100%
0.0
RPL10.MCUP.LP2.1180 RPL10.MCUP.Loop 2 - Cure for Pads Foundations Complete 02/13/26 03/04/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP2.1260 RPL10.MCUP.Loop 2 - Set mCup #6 - Dry Coolers (6) (4 per week) OFE Complete 02/13/26 02/17/26 7.5 0.0
100%
0.0
RPL10.SKN.NS12.01090 RPL10.SKIN.NS12 - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ Roofing Complete 02/13/26 02/16/26 2.5 0.0
100%
0.0
RPL10.EY.NS2.01130 RPL10.EY.NS2 - Cure (High Early Mix) Foundations Complete 02/15/26 02/21/26 8.8 0.0
100%
0.0
RPL10.EY.EF1.01120 RPL10.EY.EF1 - Install Electrical Panels (2) (GSB and LB Equipment) OFE Complete 02/16/26 02/16/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.01770 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Hang Drywall (Inside) (EF1 & EF2) EF Perimeter Walls Complete 02/16/26 02/19/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01890 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Inside) (EF1 & EF2) EF Perimeter Walls Complete 02/16/26 03/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.02320 RPL10.Interior.NS1 - Priority - Exterior Wall Tape, Float and Paint NS1 (sanding off hours) *02/16 OverHead Complete 02/16/26 02/23/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.02720 RPL10.Interior.SSB-Corridor - Priority - P2 Wall Hang Drywall (Both Sides) Priority Wall (P2) - Grid Line 10-38 Complete 02/16/26 02/19/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1620 RPL10.MCUP.Loop 1 - Set mCUPs #7 (1 per 5 days) OFE Complete 02/16/26 02/20/26 6.2 0.0
100%
0.0
RPL10.STR.NS43.01120 RPL10.Structure.NS43 - SOG F/R/P (Pour #21 -01/31 & #22 -02/03) - Grid lines 10-07/10-04 F/R/P Complete 02/16/26 02/17/26 2.5 0.0
100%
0.0
RPL10.STR.SSB.01030 RPL10.Structure.SSB - Install Storm Shelter F/R/P Deck Storm Shelter Complete 02/16/26 02/18/26 3.8 0.0
100%
0.0
ICM.B10.1840 [NWB] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Complete 02/17/26 02/17/26 0.0 0.0
100%
0.0
RPL.CM.D.C54X0.XR Logistics Area #10 - Complete Logistics - Area Turnovers XREF Milestones Complete 02/17/26 02/17/26 0.0 0.0
100%
0.0
RPL10.EY.EF2.01590 RPL10.EY.EF2 - Install Remaining Electrical Panels (2) (GSB and LB Equipment) OFE Complete 02/17/26 02/17/26 2.5 0.0
100%
0.0
RPL10.EY.NS2.01090 RPL10.EY.NS2 - Install Tent Tent and Temp Conditions Complete 02/17/26 03/30/26 26.2 0.0
100%
0.0
RPL10.INT.CTRC.01530 RPL10.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) Priority Walls & OverHead Complete 02/17/26 03/06/26 12.5 0.0
100%
0.0
RPL10.INT.CTRC.01550 RPL10.Interior.Center-Corridor - Priority - Install Mechanical Piping (Highside OH space) Priority Walls & OverHead Complete 02/17/26 03/09/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.02420 RPL10.Interior.Center-Corridor - Priority - P4 Hang Drywall (EF2 Wall Along Grid 10-D) Priority Wall (P4) - Grid Line 10-D Complete 02/17/26 03/05/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01100 RPL10.Interior.NS1 - Priority - Install Temp Doors Frame Hardware OverHead Complete 02/17/26 02/19/26 3.8 0.0
100%
0.0
RPL10.INT.NS3.01000 RPL10.Interior.NS3 - Priority - WBS Summary OverHead Active 02/17/26 04/21/26 53.8 8.8
0%
153.8
RPL10.INT.NS3.01020 RPL10.Interior.NS3 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS3 Active 02/17/26 01/26/27 291.2 247.5
0%
120.0
RPL10.INT.NS3.01030 RPL10.Interior.NS3 - Priority - Install Fire Sprinkler OverHead Complete 02/17/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01000 RPL10.Interior.NS4 - Priority - WBS Summary OverHead Active 02/17/26 04/21/26 57.5 8.8
0%
133.8
RPL10.INT.NS4.01020 RPL10.Interior.NS4 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS4 Active 02/17/26 01/06/27 278.8 231.2
0%
123.8
RPL10.INT.NS4.01030 RPL10.Interior.NS4 - Priority - Install Fire Sprinkler *(02/18) OverHead Complete 02/17/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01170 RPL10.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Active 02/17/26 07/29/26 142.5 92.5
0%
146.2
RPL10.INT.SSB.01510 RPL10.Interior.SSB - Loading Dock and Storage - Install Door Frames Loading Dock and Storage Complete 02/17/26 02/18/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02660 RPL10.Interior.SSB-Corridor - BoW - Frame Hard Lid Balance of Walls & OverHead Complete 02/17/26 02/23/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1400 RPL10.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Active 02/17/26 05/21/26 83.8 36.2
0%
17.5
RPL10.MCUP.LP1.1440 RPL10.MCUP.Loop 1 - Tie-in Mechanical (LOE) Tie-Ins Mechanical Active 02/17/26 04/27/26 40.0 13.8
0%
28.8
RPL10.MCUP.LP1.1460 RPL10.MCUP.Loop 1 - Tie-in Mechanical #1 WBS Summary Tie-in Mechanical #1 Active 02/17/26 04/15/26 13.8 3.8
0%
23.8
RPL10.MCUP.LP1.1760 RPL10.MCUP.Loop 1 - Tie-in Mechanical #3 WBS Summary Tie-in Mechanical #3 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP1.1880 RPL10.MCUP.Loop 1 - Tie-in Mechanical #5 WBS Summary Tie-in Mechanical #5 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP1.2580 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #1 Tie-in Mechanical #1 Active 02/17/26 04/15/26 13.8 3.8
0%
23.8
RPL10.MCUP.LP1.2600 RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #1 Tie-in Mechanical #1 Active 02/17/26 04/15/26 13.8 3.8
0%
23.8
RPL10.MCUP.LP1.2620 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #3 Tie-in Mechanical #3 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP1.2640 RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #3 Tie-in Mechanical #3 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP1.2660 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #5 Tie-in Mechanical #5 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP1.2680 RPL10.MCUP.Loop 1 - Condenser Tie-in Mechanical #5 Tie-in Mechanical #5 Active 02/17/26 04/15/26 11.2 3.8
0%
23.8
RPL10.MCUP.LP2.2300 RPL10.MCUP.Loop 2 - Set mCup #8 - Dry Coolers (6) (4 per week) OFE Complete 02/17/26 02/19/26 7.5 0.0
100%
0.0
RPL.10.D.X3870.XG Ready for MV Cable Pull NS 4 (Loop 1) Give Milestones (XREFs) Complete 02/18/26 02/18/26 0.0 0.0
100%
0.0
RPL.10.D.X3875.XG Ready for MV Cable Pull NS 4 (Loop 2) Give Milestones (XREFs) Complete 02/18/26 02/18/26 0.0 0.0
100%
0.0
RPL10.CFCI.7080 RPL10 - Submittal Rvw/App'l - Scuppers Fixed Louvers Complete 02/18/26 03/18/26 12.5 0.0
100%
0.0
RPL10.EY.NS2.01170 RPL10.EY.NS2 - Install Tent Fit-out Tent and Temp Conditions Complete 02/18/26 03/30/26 25.0 0.0
100%
0.0
RPL10.INT.CTRC.01200 RPL10.Interior.Center-Corridor - OFE - NS2 (1x GS.IDF) N23 (02.18.26) OFE Complete 02/18/26 02/24/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02420 RPL10.Interior.NS2 - Priority - Install Temp Doors Frame Hardware OverHead Complete 02/18/26 02/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.04200 RPL10.Interior.SSB - Priority - P5 Backing Remaining Wall Priority Wall (P5) - Grid Line 10-C Complete 02/18/26 02/25/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.06960 RPL10.Interior.SSB - BoW - Hang Drywall, Tape Float Paint (Early Work) Balance of Walls and OverHead Complete 02/18/26 03/13/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01060 RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) (02.18.26) OFE Complete 02/18/26 02/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.01100 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall Balance of Walls & OverHead Complete 02/18/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01120 RPL10.Interior.SSB-Corridor - BoW - Controls / EPMS / BMS OH and In-Wall Balance of Walls & OverHead Complete 02/18/26 03/09/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.01130 RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Lowside OH and In-Wall Balance of Walls & OverHead Complete 02/18/26 03/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02640 RPL10.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & OverHead Complete 02/18/26 03/09/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01140 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-10/10-1 (11) (with temp closures for openings) South Complete 02/18/26 02/27/26 5.0 0.0
100%
0.0
RPL10.STR.NS43.01130 RPL10.Structure.NS43 - SOG F/R/P (Pour #23 -02/05 & #24 -02/07) - Grid Lines 10-04/10-01 F/R/P Complete 02/18/26 02/20/26 5.0 0.0
100%
0.0
NW.1280 Dry Cooler 230 Ton Crane Movement 04 - Finish 230 Ton Crane (Dry Cooler) Complete 02/19/26 02/19/26 0.0 0.0
100%
0.0
RPL10.EY.NS3.01130 RPL10.EY.NS3 - Cure (High Early Mix) Foundations Complete 02/19/26 02/20/26 8.8 0.0
100%
0.0
RPL10.EY.NS4.01120 RPL10.EY.NS4 - Cure (High Early Mix) Foundations Complete 02/19/26 02/20/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.01130 RPL10.Interior.Center-Corridor - OFE - NS1 (1x GS.IDF) N13 (02.18.26) OFE Complete 02/19/26 02/25/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.02300 RPL10.Interior.NS4 - Priority - Install IMP Exterior In-Wall Rough-Ins OverHead Complete 02/19/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.04140 RPL10.Interior.SSB - Priority - P5 MEP Remaining Wall In-wall Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 02/27/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.04220 RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (South) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 03/09/26 4.0 0.0
100%
0.0
RPL10.INT.SSB.06940 RPL10.Interior.SSB - Priority - P5 Frame Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 02/23/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.06980 RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 03/09/26 4.0 0.0
100%
0.0
RPL10.MCUP.LP1.1680 RPL10.MCUP.Loop 1 - Set Electrical Skids #7 OFE Complete 02/19/26 02/19/26 1.2 0.0
100%
0.0
NW.1300 Dry Cooler 230 Ton Crane Demobilization 230 Ton Crane (Dry Cooler) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X2110.XG Trestle Construction Ready - East - RPL10 Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X3750.XG RMUs/MV Skids Set - mCUP North Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X3890.XG Ready for MV Cable Pull mCUP North Loop (Loop#1) Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.01190 RPL10.Interior.Center-Corridor - OFE - EF1 (1x GS.IDF) NE1 (02.18.26) OFE Complete 02/20/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06880 RPL10.Interior.Center-Corridor - Priority - QC - P3 Wall - Backing/In-Wall Priority Wall (P3) - Grid Line 10-25 Complete 02/20/26 02/23/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.06900 RPL10.Interior.Center-Corridor - Priority - P6 Frame Remaining Wall Priority Wall (P6) - Grid Line 10-16 Complete 02/20/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01050 RPL10.Interior.NS2 - Priority - Install FA / Linear heat detection OverHead Complete 02/20/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02400 RPL10.Interior.NS2 - Priority - Install Fire Life Safety (Sprinkler Drops) OverHead Complete 02/20/26 03/09/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.01040 RPL10.Interior.NS3 - Priority - Install Temp Lighting OverHead Complete 02/20/26 03/06/26 3.8 0.0
100%
0.0
RPL10.INT.NS4.01040 RPL10.Interior.NS4 - Priority - Install Temp Lighting OverHead Complete 02/20/26 03/06/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.01110 RPL10.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-Wall Balance of Walls & OverHead Complete 02/20/26 03/09/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP1.2560 RPL10.MCUP.Loop 1 - Set Remaining Facility water piping rack with All Racks Welding OFE Active 02/20/26 04/15/26 2.5 3.8
0%
17.5
RPL10.MCUP.LP2.1380 RPL10.MCUP.Loop 2 - Cure for Remaining Electrical Pads Foundations Complete 02/20/26 03/04/26 8.8 0.0
100%
0.0
RPL10.STR.NS43.01140 RPL10.Structure.NS43 - Zone SOG Cure F/R/P Complete 02/20/26 02/26/26 8.8 0.0
100%
0.0
GCD.RPL10.3727 [RPL10] TC Ready: All General Services [RPL10-MDFs] TC Ready: General Services Complete 02/23/26 02/23/26 0.0 0.0
100%
0.0
RPL10.CFCI.4620 RPL10 - Prep / Submit for Review -Epoxy Flooring (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Active 02/23/26 04/13/26 25.0 1.2
0%
146.2
RPL10.CFCI.4810 RPL10 - Prep / Submit for Review - Specialities (CFCI) Div. 10 - Specialities Active 02/23/26 04/13/26 25.0 1.2
0%
113.8