Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
88
Completed
12
In Progress
88
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.EY.NS4.01050 RPL10.EY.NS4 - Install Tent F/R/P SOG (30k Mock Up) Tent and Temp Conditions Complete 02/23/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01060 RPL10.Interior.NS12 - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Complete 02/23/26 02/24/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01090 RPL10.Interior.NS12 - Temp Conditions - Install Early Temp Conditions Temp Conditions Complete 02/23/26 02/24/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01110 RPL10.Interior.NS1 - Priority - Install Electrical **to clarify scope OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01160 RPL10.Interior.NS1 - OFE - WBS Summary OFE Active 02/23/26 08/12/26 150.0 107.5
0%
38.8
RPL10.INT.NS1.02380 RPL10.Interior.NS1 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 02/23/26 03/09/26 12.5 0.0
100%
0.0
RPL10.INT.NS2.01010 RPL10.Interior.NS2 - Priority - Install Duct OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01080 RPL10.Interior.NS2 - OFE - WBS Summary OFE Active 02/23/26 09/03/26 170.0 127.5
0%
18.8
RPL10.INT.NS2.02330 RPL10.Interior.NS2 - Priority - Exterior Wall Tape, Float and Paint NS2 (sanding off hours) *02/23 OverHead Complete 02/23/26 02/27/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.02425 RPL10.Interior.NS2 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 02/23/26 03/09/26 12.5 0.0
100%
0.0
RPL10.INT.NS3.01980 RPL10.Interior.NS3 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/23/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.02300 RPL10.Interior.NS3 - Priority - Install IMP Exterior In-Wall Rough-Ins OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01980 RPL10.Interior.NS4 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/23/26 03/23/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1280 RPL10.MCUP.Loop 2 - Set mCUPs #2 (1 per 5 days) OFE Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.STR.NS12.01180 RPL10.Structure.NS1 - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
GCD.RPL10.5945 Temporary Conditioning Achieved in NS1 Construction Milestones Complete 02/24/26 02/24/26 0.0 0.0
100%
0.0
RPL10.CFCI.5700 RPL10 - Submittal Rvw/App'l - Glass / Frames (Awaiting Substitiute Approval) Glass & Glazing (Alum. Entrances & Curtainwall) Active 02/24/26 04/13/26 1.2 1.2
0%
125.0
RPL10.INT.CTRC.01010 RPL10.Interior.Center-Corridor - Priority - Install Duct (LOE) Priority Walls & OverHead Complete 02/24/26 03/27/26 18.8 0.0
100%
0.0
RPL10.INT.CTRC.01011 RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) Priority Walls & OverHead Complete 02/24/26 03/10/26 12.5 0.0
100%
0.0
RPL10.SKN.EF12.01090 RPL10.SKIN.EF12 - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ Roofing Complete 02/24/26 02/25/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.01012 RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) Priority Walls & OverHead Complete 02/25/26 03/24/26 12.5 0.0
100%
0.0
RPL10.INT.SSB.01260 RPL10.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls and OverHead Active 02/25/26 04/15/26 8.8 3.8
0%
72.5
RPL10.EY.NS4.01060 RPL10.EY.NS4 - Tent SOG Cure Tent and Temp Conditions Complete 02/26/26 02/27/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.06820 RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall (East Side) Priority Wall (P3) - Grid Line 10-25 Complete 02/26/26 03/02/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP2.2580 RPL10.MCUP.Loop 2 - F/R/P Pad for GS.IDF NX10 Foundations Complete 02/26/26 02/27/26 3.8 0.0
100%
0.0
NW.1040 MCUP 600 Ton Crane Movement 2 600 Ton Crane (MCUP) Complete 02/27/26 02/27/26 0.0 0.0
100%
0.0
RPL.10.D.X3860.XG Ready for MV Cable Pull NS 2 (Loop 1) Give Milestones (XREFs) Complete 02/27/26 02/27/26 0.0 0.0
100%
0.0
RPL.10.D.X3865.XG Ready for MV Cable Pull NS 2 (Loop 2) Give Milestones (XREFs) Complete 02/27/26 02/27/26 0.0 0.0
100%
0.0
RPL.10.D.X3880.XG Ready for MV Cable Pull NS 3 (Loop 1) Give Milestones (XREFs) Complete 02/27/26 02/27/26 0.0 0.0
100%
0.0
RPL.10.D.X3885.XG Ready for MV Cable Pull NS 3 (Loop 2) Give Milestones (XREFs) Complete 02/27/26 02/27/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.06860 RPL10.Interior.Center-Corridor - Priority - P3 Wall Tape, Float and Paint (East Side) Priority Wall (P3) - Grid Line 10-25 Complete 02/27/26 03/09/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06920 RPL10.Interior.Center-Corridor - Priority - P6 Wall MEP In-Wall Rough Ins Priority Wall (P6) - Grid Line 10-16 Complete 02/27/26 03/09/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06940 RPL10.Interior.Center-Corridor - Priority - P6 Wall Backing Priority Wall (P6) - Grid Line 10-16 Complete 02/27/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS4.02110 RPL10.Interior.NS4 - Priority - Install Plumbing / Mechanical Piping OverHead Complete 02/27/26 03/13/26 3.8 0.0
100%
0.0
RPL10.SKN.W.01000 RPL10.SKIN.West - Install IMP Flashing,Panels & Caulking - Grid lines 10A/10F(10) (with temp closures for openings) West Complete 02/27/26 03/02/26 3.8 0.0
100%
0.0
RPL10.SKN.W.01010 RPL10.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary West Complete 02/27/26 03/11/26 13.8 0.0
100%
0.0
RPL10.STR.NS12.01160 RPL10.Structure.NS1 - SOG Sealant Cure F/R/P Complete 02/28/26 02/28/26 1.2 0.0
100%
0.0
GCD.RPL10.1390 IMP Complete - RPL10 Construction Milestones Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
GCD.RPL10.1700 Start LV Electrical Skid Set-In-Place - RPL10 Construction Milestones Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
GCD.RPL10.1826 Delivery of RMU - (First Delivery) - RPL10 - NS12 Construction Milestones Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
ICM.B10.1825 [NWB] Delivery of MVS - Medium Voltage Switches (First Delivery) Construction Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
ICM.B10.1850 [NWB] Delivery of NES - Network Electrical Room Skid (First Delivery) - RPL10 Construction Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
NW.1800 IMP Crane #1 Movement 09 IMP Crane #1 Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
RPL10.EY.EF2.01560 RPL10.EY.EF2 - Install F/R/P Remaining Equipment Pads (IDF/CRAH/CRAC) Foundations Complete 03/02/26 03/03/26 10.0 0.0
100%
0.0
RPL10.EY.NS1.01140 RPL10.EY.NS1 - Install Tent Electrical Panels Tent and Temp Conditions Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01150 RPL10.EY.NS1 - Install Tent Heating and Cooling Equipment Tent and Temp Conditions Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01170 RPL10.EY.NS1 - Install Tent Fit-out Tent and Temp Conditions Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01190 RPL10.EY.NS1 - Install Tent Mechanical Tie-ins Tent and Temp Conditions Complete 03/02/26 03/09/26 7.5 0.0
100%
0.0
RPL10.INT.CTRC.07520 RPL10.Interior.Center-Corridor - Priority - P6 Hang Drywall Tape, Float and Paint (for IDFs) (03.05.26) Priority Wall (P6) - Grid Line 10-16 Complete 03/02/26 03/05/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01140 RPL10.Interior.NS1 - OFE - LV Skids and TopHat - Set / Place / Anchor (03.04.26) OFE Complete 03/02/26 03/23/26 25.0 0.0
100%
0.0
RPL10.INT.NS4.02420 RPL10.Interior.NS4 - Priority - Install Temp Doors Frame Hardware OverHead Complete 03/02/26 03/04/26 3.8 0.0
100%
0.0
RPL10.MCUP.LP1.1420 RPL10.MCUP.Loop 1 - Tie-in Electrical (LOE) Tie-Ins Electrical Active 03/02/26 05/08/26 51.2 25.0
0%
17.5
RPL10.MCUP.LP1.1480 RPL10.MCUP.Loop 1 - Tie-in Electrical #1 Tie-Ins Electrical Active 03/02/26 04/17/26 11.2 6.2
0%
22.5
RPL10.MCUP.LP2.1300 RPL10.MCUP.Loop 2 - Set mCUPs #4 (1 per 5 days) OFE Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.SKN.NS12.01120 RPL10.SKIN.NS12 - Install Roof System - Final Roof (Grid 10-30 / 10-20) Roofing Complete 03/02/26 03/18/26 11.2 0.0
100%
0.0
RPL10.SKN.S.01160 RPL10.SKIN - Install Comeback Leave out IMP Flashing,Panels & Caulking (EF Area/FSP) IMP System Complete 03/02/26 03/03/26 5.0 0.0
100%
0.0
RPL10.STR.NS12.01320 RPL10.Structure.NS2 - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.STR.SSB.01230 RPL10.Structure.SSB - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL10.WA.OFE.01000 RPL10.WA - FDN to OFE Weather Allowance Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0
RPL10.INT.SSBC.04060 RPL10.Interior.SSB-Corridor - BoW - Hang Drywall Tape Finish Paint (GS MDF Electrical Room) BoW Balance of Walls & OverHead Complete 03/03/26 03/06/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.04080 RPL10.Interior.SSB-Corridor - Priority - OFE Waterproofing Protection Layer Delay Priority Walls & OverHead Complete 03/03/26 03/09/26 10.0 0.0
100%
0.0
RPL10.EY.EF2.01580 RPL10.EY.EF2 - Cure for Remaining Equipment Pads (High Early Mix) Foundations Complete 03/04/26 03/06/26 8.8 0.0
100%
0.0
RPL10.EY.NS1.01180 RPL10.EY.NS1 - Install Tent Electrical Tie-ins Tent and Temp Conditions Complete 03/04/26 03/06/26 3.8 0.0
100%
0.0
RPL10.INT.ENDC.01000 RPL10.Interior.End-Corridor - Install Priority Walls and OverHead- WBS Summary Priority Walls & OverHead Active 03/04/26 05/05/26 55.0 21.2
0%
197.5
RPL10.INT.ENDC.01020 RPL10.Interior.End-Corridor - Install Priority OH, Walls, Fitout and Build Back - WBS Summary End Corridor Active 03/04/26 02/22/27 303.8 270.0
0%
72.5
RPL10.INT.ENDC.6320 RPL10.Interior.End-Corridor - Priority - Frame Priority Soffit and Hang Drywall Priority Walls & OverHead Complete 03/04/26 03/10/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07460 RPL10.Interior.Center-Corridor - Priority - Install Remaining Supplemental Steel (Exterior Walls) Priority Walls & OverHead Complete 03/05/26 03/27/26 12.5 0.0
100%
0.0
RPL10.INT.SSB.01080 RPL10.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall *Lowside Separate Activity Balance of Walls and OverHead Active 03/05/26 04/13/26 6.2 1.2
0%
75.0
RPL10.INT.SSB.01740 RPL10.Interior.SSB - Loading Dock and Storage - Install VAV's/ Duct Branches Loading Dock and Storage Complete 03/05/26 03/20/26 12.5 0.0
100%
0.0
FR01.1000 FR01: PSI HAC Delays - NS1 - LV Side Aisle - Issue Identification & Notification FR01: NS1 LV Side Aisle HAC Delays Complete 03/06/26 03/06/26 1.2 0.0
100%
0.0
FR01.1100 FR01: PSI HAC Delays - NS2 - LV Side Aisle - Issue Identification & Notification FR02: NS2 LV Side Aisle HAC Delays Complete 03/06/26 03/06/26 1.2 0.0
100%
0.0
NW.1080 MCUP 600 Ton Crane Movement 4 (If Needed) 600 Ton Crane (MCUP) Complete 03/06/26 03/06/26 0.0 0.0
100%
0.0
RPL10.EY.ENDC.01090 RPL10.EY.End - Install GS.IDF Hut (1x GS.IDF) NX10 (05.29.26) OFE Complete 03/06/26 03/12/26 6.2 0.0
100%
0.0
RPL10.EY.ENDC.01100 RPL10.EY.End - OFE - WBS Summary OFE Active 03/06/26 04/16/26 36.2 5.0
0%
103.8
RPL10.INT.CTRC.01250 RPL10.Interior.Center-Corridor - OFE - NS4 (1x GS.IDF) N41 (03.06.26) OFE Complete 03/06/26 03/12/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01310 RPL10.Interior.Center-Corridor - OFE - NS3 (1x GS.IDF) N31 (03.06.26) OFE Complete 03/06/26 03/12/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.02440 RPL10.Interior.Center-Corridor - Priority - P4 Tape, Float and Paint (EF2 Wall Along Grid 10-D) (02.17.26) Priority Wall (P4) - Grid Line 10-D Complete 03/06/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.02460 RPL10.Interior.Center-Corridor - Priority - Frame Wall (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 03/06/26 03/11/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07440 RPL10.Interior.Center-Corridor - Priority - Install Remaining Supplemental Steel (Wing Walls) Priority Walls & OverHead Complete 03/06/26 03/27/26 7.5 0.0
100%
0.0
RPL10.INT.ENDC.6180 RPL10.Interior.End-Corridor - Priority - P7 Frame Remaining Wall Priority Wall (P7) - Grid Line 10-02 Complete 03/06/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02340 RPL10.Interior.NS2 - Priority - Install Electrical **to clarify scope *03/02 OverHead Complete 03/06/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01010 RPL10.Interior.NS4 - Priority - Install Duct OverHead Complete 03/06/26 03/27/26 18.8 0.0
100%
0.0
RPL10.MCUP.LP1.1700 RPL10.MCUP.Loop 1 - Tie-in Electrical #3 Tie-Ins Electrical Active 03/06/26 04/17/26 8.8 6.2
0%
22.5
RPL10.STR.SSB.01210 RPL10.Structure.SSB - SOG Sealant Cure F/R/P Complete 03/06/26 03/06/26 1.2 0.0
100%
0.0
RPL10.STR.NS12.01340 RPL10.Structure.NS2 - SOG Sealant Cure F/R/P Complete 03/07/26 03/07/26 1.2 0.0
100%
0.0
GCD.RPL10.1290 Interior fit-out Start RPL10 - NS43 Construction Milestones Complete 03/09/26 03/09/26 0.0 0.0
100%
0.0
RPL10.EY.ENDC.01060 RPL10.EY.End - Install F/R/P Equipment Pads Foundations Complete 03/09/26 03/12/26 12.5 0.0
100%
0.0
RPL10.EY.ENDC.01070 RPL10.EY.End - Install Foundations - WBS Summary Foundations Complete 03/09/26 03/19/26 12.5 0.0
100%
0.0
RPL10.EY.NS1.01160 RPL10.EY.NS1 - Install Tent Overhead Doors Tent and Temp Conditions Complete 03/09/26 03/10/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01220 RPL10.EY.NS1 - Install MV, RMUs & Electrical Panels (15) OFE Complete 03/09/26 03/25/26 25.0 0.0
100%
0.0
RPL10.EY.NS1.01230 RPL10.EY.NS1 - OFE - MV - WBS Summary OFE Active 03/09/26 04/14/26 32.5 2.5
0%
33.8
RPL10.EY.NS3.01070 RPL10.EY.NS3 - Install Tent F/R/P SOG (30k Mock Up) Tent and Temp Conditions Complete 03/09/26 03/13/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01810 RPL10.Interior.Center-Corridor - Priority - Install Backing Exterior Wall Priority Walls & OverHead Complete 03/09/26 03/13/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07480 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Hang Drywall (Outside) (EF1 & EF2) EF Perimeter Walls Complete 03/09/26 03/12/26 5.0 0.0
100%
0.0
RPL10.INT.EF1.01050 RPL10.Interior.EF1 - Priority OH - Install Vesda / FA / Linear Heat Detection OverHead Complete 03/09/26 03/11/26 3.8 0.0
100%
0.0
RPL10.INT.EF2.01050 RPL10.Interior.EF2 - Priority OH - Install Vesda / FA / Linear Heat Detection OverHead Complete 03/09/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01040 RPL10.Interior.End-Corridor - Priority - Install Temp Lighting (Show in Model) Priority Walls & OverHead Complete 03/09/26 03/10/26 3.8 0.0
100%
0.0
RPL10.INT.ENDC.6080 RPL10.Interior.End-Corridor - Priority - Install Layout Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & OverHead Complete 03/09/26 03/18/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.02420 RPL10.Interior.NS3 - Priority - Install Temp Doors Frame Hardware OverHead Complete 03/09/26 03/11/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.01070 RPL10.Interior.SSB - BoW - Doors Frame Balance of Walls and OverHead Complete 03/09/26 03/11/26 3.8 0.0
100%
0.0