Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
83
Completed
17
In Progress
83
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.SSB.01800 RPL10.Interior.SSB - BoW - Install VAV's/ Duct Branches Balance of Walls and OverHead Active 03/09/26 04/13/26 8.8 1.2
0%
165.0
RPL10.INT.SSBC.02580 RPL10.Interior.SSB-Corridor - Priority - Install FA (Highside OH space) *No Scope Priority Walls & OverHead Complete 03/09/26 03/09/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03100 RPL10.Interior.SSB-Corridor - Priority - P2 Wall Tape Finish Paint Priority Wall (P2) - Grid Line 10-38 Complete 03/09/26 03/13/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1320 RPL10.MCUP.Loop 2 - Set mCUPs #6 (1 per 5 days) OFE Complete 03/09/26 03/13/26 6.2 0.0
100%
0.0
RPL10.SKN.NS43.01000 RPL10.SKIN.NS43 - Install Temp Doors Glazing, Doors and Ext Devices Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL10.SKN.NS43.01020 RPL10.SKIN.NS43 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Active 03/09/26 01/27/27 278.8 173.8
0%
77.5
RPL10.SKN.S.01100 RPL10.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin South Complete 03/09/26 03/11/26 12.5 0.0
100%
0.0
RPL10.SKN.W.01040 RPL10.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin West Complete 03/09/26 03/11/26 6.2 0.0
100%
0.0
ICM.B10.1855 [NWB] Delivery of MES - Multi Trade Rack (First Delivery) - RPL10 Construction Complete 03/10/26 03/10/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.01090 RPL10.Interior.Center-Corridor - OFE - NS1 (1x Optical Splice) (03.04.26) (Rev-03.09.26) OFE Active 03/10/26 04/15/26 12.5 3.8
0%
137.5
RPL10.INT.CTRC.07500 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Outside) (EF1 & EF2) EF Perimeter Walls Complete 03/10/26 03/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS4.02320 RPL10.Interior.NS4 - Priority - Install Drywall at Exterior Wall OverHead Complete 03/10/26 03/17/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01220 RPL10.Interior.SSB - BoW - Install Security Lowside OH and In-wall Balance of Walls and OverHead Complete 03/10/26 03/25/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.01240 RPL10.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls and OverHead Complete 03/10/26 03/30/26 18.8 0.0
100%
0.0
RPL10.INT.SSB.03480 RPL10.Interior.SSB - Priority - P0 & P1 Wall Tape Float Paint (East Sides) Priority Wall (P0&P1) - Grid Line 10-41/40 Complete 03/10/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.04240 RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (South) Priority Wall (P5) - Grid Line 10-C Complete 03/10/26 03/13/26 8.0 0.0
100%
0.0
RPL10.INT.SSB.04280 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (South) Priority Wall (P5) - Grid Line 10-C Complete 03/10/26 03/13/26 8.0 0.0
100%
0.0
RPL10.INT.SSBC.04100 RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall (Remaining Work) Priority Walls & OverHead Complete 03/10/26 03/13/26 6.2 0.0
100%
0.0
GCD.RPL10.1655 Start MES Installation - RPL10 Construction Milestones Complete 03/11/26 03/11/26 0.0 0.0
100%
0.0
RPL10.EY.EF2.01280 RPL10.EY.EF2 - Install Electrical Tie-ins (include penetration detail) Tie-ins Complete 03/11/26 04/06/26 18.8 0.0
100%
0.0
RPL10.EY.EF2.01290 RPL10.EY.EF2 - Tie-ins - WBS Summary Tie-ins Active 03/11/26 06/03/26 73.8 32.5
0%
176.2
RPL10.INT.CTRC.01830 RPL10.Interior.Center-Corridor - Priority - Install FA/ Linear Heat Detection (Highside OH space) Priority Walls & OverHead Complete 03/11/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07160 RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF1) EF Perimeter Walls Complete 03/11/26 03/16/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07620 RPL10.Interior.Center-Corridor - Priority - MEP In-Wall Rough Ins/Backing (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 03/11/26 03/20/26 5.0 0.0
100%
0.0
RPL10.INT.ENDC.6220 RPL10.Interior.End-Corridor - Priority - P7 Wall MEP In-Wall Rough Ins Priority Wall (P7) - Grid Line 10-02 Complete 03/11/26 03/17/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6380 RPL10.Interior.End-Corridor - Priority - P7 Wall Backing Priority Wall (P7) - Grid Line 10-02 Active 03/11/26 04/13/26 6.2 1.2
100%
153.8
RPL10.INT.NS1.01150 RPL10.Interior.NS1 - OFE - MES Skids - Set / Place / Anchor **03/12 OFE Complete 03/11/26 04/06/26 25.0 0.0
100%
0.0
RPL10.INT.NS3.02320 RPL10.Interior.NS3 - Priority - Install Drywall at Exterior Wall OverHead Complete 03/11/26 03/17/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01251 RPL10.Interior.SSB-Corridor - Install Electrical - SSB Electrical Room (10.S2.06) Balance of Walls & OverHead Complete 03/11/26 03/19/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.02240 RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N1.08) Balance of Walls & OverHead Complete 03/11/26 03/31/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.02620 RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Piping Lowside OH and In-Wall Balance of Walls & OverHead Complete 03/11/26 03/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.02680 RPL10.Interior.SSB-Corridor - BoW - Install VAV's Balance of Walls & OverHead Complete 03/11/26 03/30/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1360 RPL10.MCUP.Loop 2 - Set mCUPs #8 (1 per 5 days) OFE Complete 03/11/26 03/13/26 6.2 0.0
100%
0.0
RPL10.SKN.SSB.01140 RPL10.SKIN.SSB - Install Roof System - Install EJ Grid lines 10-31/30 Expansion Joint Complete 03/11/26 03/13/26 5.0 0.0
100%
0.0
FR01.1020 FR01: PSI HAC Delays - NS1 - LV Side Aisle - First Delivery (Benchmark) ((1)) FR01: NS1 LV Side Aisle HAC Delays Complete 03/12/26 03/12/26 1.2 0.0
100%
0.0
FR01.1040 FR01: PSI HAC Delays - NS1 - LV Side Aisle - Second Delivery (2,3) FR01: NS1 LV Side Aisle HAC Delays Complete 03/12/26 03/12/26 1.2 0.0
100%
0.0
FR01.1120 FR01: PSI HAC Delays - NS2 - LV Side Aisle - First Delivery (Row 1) FR02: NS2 LV Side Aisle HAC Delays Complete 03/12/26 04/07/26 2.5 0.0
100%
0.0
FR01.1140 FR01: PSI HAC Delays - NS2 - LV Side Aisle - Second Delivery (Row 2) FR02: NS2 LV Side Aisle HAC Delays Complete 03/12/26 04/07/26 1.2 0.0
100%
0.0
FR01.1160 FR01: PSI HAC Delays - NS2 - LV Side Aisle - Third Delivery (Row 3,4,5) FR02: NS2 LV Side Aisle HAC Delays Complete 03/12/26 04/09/26 1.2 0.0
100%
0.0
FR01.1180 FR01: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 6,7,8) FR02: NS2 LV Side Aisle HAC Delays Complete 03/12/26 04/10/26 2.5 0.0
100%
0.0
FR01.1200 FR01: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 9) FR02: NS2 LV Side Aisle HAC Delays Complete 03/12/26 04/10/26 2.5 0.0
100%
0.0
NW.2140 031226 - Non Weather Impact #3 - Power Outage Due to Severe Weather 031226 Project Impacts Complete 03/12/26 03/12/26 1.2 0.0
100%
0.0
RPL10.INT.NS4.01050 RPL10.Interior.NS4 - Priority - Install FA / Linear heat detection OverHead Complete 03/12/26 03/18/26 2.5 0.0
100%
0.0
RPL10.EY.EF1.01130 RPL10.EY.EF1 - Install UPS-CU (2) OFE Complete 03/13/26 03/13/26 3.8 0.0
100%
0.0
RPL10.EY.ENDC.01080 RPL10.EY.End - Cure (High Early Mix) Foundations Complete 03/13/26 03/19/26 8.8 0.0
100%
0.0
RPL10.EY.NS1.01200 RPL10.EY.NS1 - Tent Temp Conditioning Startup and Available (Including Acclimation) (02/23/26) Tent and Temp Conditions Complete 03/13/26 03/20/26 7.5 0.0
100%
0.0
RPL10.EY.NS3.01080 RPL10.EY.NS3 - Tent SOG Cure Tent and Temp Conditions Complete 03/13/26 03/20/26 8.8 0.0
100%
0.0
RPL10.INT.NS2.01070 RPL10.Interior.NS2 - OFE - MES Skids - Set / Place / Anchor OFE Complete 03/13/26 04/06/26 25.0 0.0
100%
0.0
RPL10.SKN.EF12.01120 RPL10.SKIN.EF12 - Install Roof System - Final Roof (Grid 10-20 / 10-10) Roofing Complete 03/13/26 03/27/26 15.0 0.0
100%
0.0
RPL10.STR.EF12.01180 RPL10.Structure.EF12 - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 03/13/26 03/19/26 6.2 0.0
100%
0.0
RPL.CM.D.C5520.XR Burn Road East Logistics - Onsite Receive XREF Milestones Complete 03/16/26 03/16/26 0.0 0.0
100%
0.0
RPL.CM.D.C5540.XR Chewy Court ( Around RPL10 & Admin) Logistics - Onsite Receive XREF Milestones Complete 03/16/26 03/16/26 0.0 0.0
100%
0.0
RPL.CM.D.C5840.XR R2 Road Logistics - Onsite Receive XREF Milestones Complete 03/16/26 03/16/26 0.0 0.0
100%
0.0
RPL.CM.D.C5860.XR D2 Pass Logistics - Onsite Receive XREF Milestones Complete 03/16/26 03/16/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01050 RPL10.EY.EF1 - Install Fiber Support Platform (FSP) - WBS Summary Fiber Support Platform Active 03/16/26 08/07/26 127.5 103.8
0%
215.0
RPL10.EY.EF1.01580 RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization Fiber Support Platform Complete 03/16/26 03/16/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01600 RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization & Setup Fiber Support Platform Complete 03/16/26 03/18/26 3.8 0.0
100%
0.0
RPL10.EY.EF2.01610 RPL10.EY.EF2 - Install Remaining UPS-CU (2) OFE Complete 03/16/26 03/16/26 3.8 0.0
100%
0.0
RPL10.EY.SSB.01540 RPL10.EY.SSB - Install AHU Duct Stands & Ducts OFE Complete 03/16/26 03/26/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.07560 RPL10.Interior.Center-Corridor - Priority - P3 Wall Frame Wall (Post Optical Splice) Priority Wall (P3) - Grid Line 10-25 Complete 03/16/26 03/18/26 2.5 0.0
100%
0.0
RPL10.INT.EF1.01000 RPL10.Interior.EF1 - Priority OH - Install Duct (Highside OH space) OverHead Complete 03/16/26 03/16/26 10.0 0.0
100%
0.0
RPL10.INT.EF1.01120 RPL10.Interior.EF1 - Priority OH - Fire Life Safety (Sprinkler Drops) OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.EF2.01000 RPL10.Interior.EF2 - Priority OH - Install Duct (Highside OH space) OverHead Complete 03/16/26 03/16/26 10.0 0.0
100%
0.0
RPL10.INT.EF2.01120 RPL10.Interior.EF2 - Priority OH - Fire Life Safety (Sprinkler Drops) OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01130 RPL10.Interior.NS1 - Priority - Install Controls / EPMS / BMS OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01180 RPL10.Interior.NS1 - LV Skids and TopHat Tie-ins (LOE) NS1 - LV Skids and TopHat Complete 03/16/26 03/27/26 32.5 0.0
100%
0.0
RPL10.INT.NS1.01181 RPL10.Interior.NS1 - LV Skids and TopHat - Set & Anchor Interconnects NS1 - LV Skids and TopHat Complete 03/16/26 03/25/26 22.5 0.0
100%
0.0
RPL10.INT.NS1.01182 RPL10.Interior.NS1 - LV Skids and TopHat - Maintenance and Reserve Busways NS1 - LV Skids and TopHat Complete 03/16/26 03/25/26 18.8 0.0
100%
0.0
RPL10.INT.NS1.01190 RPL10.Interior.NS1 - Tie-ins - WBS Summary Tie-Ins Active 03/16/26 09/11/26 160.0 133.8
0%
107.5
RPL10.INT.NS1.01200 RPL10.Interior.NS1 - MES Skids Tie-ins (LOE) NS1 - MES Skids Active 03/16/26 06/09/26 97.5 51.2
0%
161.2
RPL10.INT.NS1.01201 RPL10.Interior.NS1 - MES Skids - Set & Anchor Interconnects NS1 - MES Skids Complete 03/16/26 04/07/26 30.0 0.0
100%
0.0
RPL10.INT.NS2.02380 RPL10.Interior.NS2 - Priority - Install Controls / EPMS / BMS OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.01010 RPL10.Interior.NS3 - Priority - Install Duct OverHead Active 03/16/26 04/15/26 18.8 3.8
0%
115.0
RPL10.INT.NS3.01050 RPL10.Interior.NS3 - Priority - Install FA / Linear heat detection OverHead Complete 03/16/26 03/20/26 2.5 0.0
100%
0.0
RPL10.INT.NS3.02380 RPL10.Interior.NS3 - Priority - Install Controls / EPMS / BMS OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.02400 RPL10.Interior.NS3 - Priority - Install Fire Life Safety (Sprinkler Drops) OverHead Complete 03/16/26 04/06/26 5.0 0.0
100%
0.0
RPL10.INT.NS4.02380 RPL10.Interior.NS4 - Priority - Install Controls / EPMS / BMS OverHead Complete 03/16/26 03/16/26 5.0 0.0
100%
0.0
RPL10.INT.NS4.02400 RPL10.Interior.NS4 - Priority - Install Fire Life Safety (Sprinkler Drops) OverHead Complete 03/16/26 03/30/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.01100 RPL10.Interior.SSB - BoW - Install Controls / EPMS / BMS and In-wall Balance of Walls and OverHead Complete 03/16/26 03/19/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.03360 RPL10.Interior.SSB - BoW - Install Backings Balance of Walls and OverHead Complete 03/16/26 03/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.07000 RPL10.Interior.SSB - Priority - P5 MEP In-Wall Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 03/16/26 03/19/26 4.0 0.0
100%
0.0
RPL10.MCUP.LP1.1540 RPL10.MCUP.Loop 1 - Tie-in BMS (LOE) Tie-Ins BMS Active 03/16/26 05/08/26 50.0 25.0
0%
17.5
RPL10.MCUP.LP1.1560 RPL10.MCUP.Loop 1 - Tie-in BMS #1 Tie-Ins BMS Active 03/16/26 04/21/26 10.0 3.8
0%
22.5
RPL10.MCUP.LP1.1580 RPL10.MCUP.Loop 1 - Tie-in EPMS (LOE) Tie-Ins EPMS Active 03/16/26 05/08/26 50.0 25.0
0%
17.5
RPL10.MCUP.LP1.1600 RPL10.MCUP.Loop 1 - Tie-in EPMS #1 Tie-Ins EPMS Active 03/16/26 04/20/26 8.8 6.2
0%
22.5
RPL10.MCUP.LP1.1660 RPL10.MCUP.Loop 1 - Tie-in SD, DW **Confirm Scope Tie-Ins Mechanical Complete 03/16/26 03/17/26 15.0 0.0
100%
0.0
RPL10.SKN.EF12.01000 RPL10.SKIN.EF12 - Install Temp Doors Glazing, Doors and Ext Devices Complete 03/16/26 03/17/26 2.5 0.0
100%
0.0
RPL10.SKN.EF12.01020 RPL10.SKIN.EF12 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Active 03/16/26 07/24/26 115.0 22.5
0%
235.0
RPL10.INT.CTRC.01140 RPL10.Interior.Center-Corridor - OFE - NS2 (1x Optical Splice) (03.10.26) (Rev-03.16.26) OFE Active 03/17/26 04/15/26 12.5 3.8
0%
137.5
RPL10.INT.CTRC.07000 RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (East Side) Priority Wall (P6) - Grid Line 10-16 Complete 03/17/26 03/20/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07640 RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF2) EF Perimeter Walls Complete 03/17/26 03/18/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01030 RPL10.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH Space) Priority Walls & OverHead Complete 03/17/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01060 RPL10.Interior.NS2 - OFE - LV Skids and TopHat - Set / Place / Anchor (03.18.26) OFE Complete 03/17/26 03/30/26 25.0 0.0
100%
0.0
GCD.RPL10.1020 Weather tight SSB and NS12 Construction Milestones Complete 03/18/26 03/18/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.06980 RPL10.Interior.Center-Corridor - Priority - QC - P6 Wall - Backing/Wall Priority Wall (P6) - Grid Line 10-16 Complete 03/18/26 03/19/26 2.5 0.0
100%
0.0
RPL10.INT.SSB.06720 RPL10.Interior.SSB - BoW - Install Remaining Unistruts & Hangers Balance of Walls and OverHead Complete 03/18/26 03/30/26 6.2 0.0
100%
0.0
RPL10.CFCI.7060 RPL10 - Fabricate / Deliver - Scuppers, Awning over Doors Fixed Louvers Active 03/19/26 06/15/26 6.2 56.2
100%
125.0
RPL10.CFCI.7100 RPL10 - Fabricate / Deliver - Metal Canopy Fixed Louvers Active 03/19/26 06/15/26 6.2 56.2
100%
148.8
RPL10.EY.EF1.01040 RPL10.EY.EF1 - Install RPL-1 FSP Deep Foundation (TCCO est Release 09-Feb-26) Fiber Support Platform - RPL-1 Complete 03/19/26 03/27/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01710 RPL10.Interior.Center-Corridor - Priority - QC Exterior Wall - Backing/In-Wall Priority Walls & OverHead Complete 03/19/26 03/20/26 6.2 0.0
100%
0.0