Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
70
Completed
30
In Progress
75
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.CTRC.07580 RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall/Backing (Post Optical Splice) Priority Wall (P3) - Grid Line 10-25 Complete 03/19/26 03/25/26 2.5 0.0
100%
0.0
RPL10.INT.ENDC.6260 RPL10.Interior.End-Corridor - Priority - Install IMP Backing Exterior Wall Priority Walls & OverHead Complete 03/19/26 03/24/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.04300 RPL10.Interior.SSB - Priority - P5 QC - Backings/In-Wall Priority Wall (P5) - Grid Line 10-C Complete 03/19/26 03/19/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.04400 RPL10.Interior.SSB - BoW - Notify META for TV Installation & Conf Sound (+25d Install TV) Balance of Walls and OverHead Complete 03/19/26 03/19/26 0.0 0.0
100%
0.0
RPL10.INT.SSBC.02740 RPL10.Interior.SSB-Corridor - BoW - MEPF Frame Hard Lid Rough Ins/Close of Inspection Balance of Walls & OverHead Complete 03/19/26 03/19/26 1.2 0.0
100%
0.0
NW.1100 MCUP 600 Ton Crane Demobilization 600 Ton Crane (MCUP) Complete 03/20/26 03/20/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.01730 RPL10.Interior.Center-Corridor - Priority - Install Drywall at Exterior Wall Priority Walls & OverHead Complete 03/20/26 03/30/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.02390 RPL10.Interior.NS3 - Priority - Exterior Wall Tape, Float and Paint NS3 (sanding off hours) OverHead Complete 03/20/26 04/09/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.02330 RPL10.Interior.NS4 - Priority - Exterior Wall Tape, Float and Paint NS4 (sanding off hours) OverHead Complete 03/20/26 04/08/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.04260 RPL10.Interior.SSB - Priority - P5 Two Side Drywall Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 03/20/26 03/30/26 4.0 0.0
100%
0.0
RPL10.INT.SSB.07020 RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 03/20/26 04/02/26 8.0 0.0
100%
0.0
RPL10.STR.EF12.01160 RPL10.Structure.EF12 - SOG Sealant Cure F/R/P Complete 03/20/26 03/21/26 2.5 0.0
100%
0.0
FR01.1060 FR01: PSI HAC Delays - NS1 - LV Side Aisle - Third Delivery (4,5) (4/21/26 Saturday) FR01: NS1 LV Side Aisle HAC Delays Complete 03/23/26 03/23/26 1.2 0.0
100%
0.0
ICM.B10.1845 [NWB] Delivery of FSHAC - Hot Aisle Containment (First Delivery) - RPL10 Construction Complete 03/23/26 03/23/26 0.0 0.0
100%
0.0
JCL.C.1160 RPL10 - Cost Risk LOE-9 HAC Install Cost LOEs Active 03/23/26 12/07/26 206.2 206.2
0%
67.5
RPL10.EY.NS2.01220 RPL10.EY.NS2 - Install MV, RMUs & Electrical Panels (15) OFE Complete 03/23/26 04/10/26 25.0 0.0
100%
0.0
RPL10.EY.NS2.01230 RPL10.EY.NS2 - OFE - MV - WBS Summary OFE Active 03/23/26 05/05/26 38.8 12.5
0%
31.2
RPL10.EY.NS4.01090 RPL10.EY.NS4 - Install Tent Tent and Temp Conditions Active 03/23/26 04/20/26 25.0 7.5
0%
115.0
RPL10.EY.NS4.01170 RPL10.EY.NS4 - Install Tent Fit-out Tent and Temp Conditions Active 03/23/26 04/20/26 25.0 7.5
0%
123.8
RPL10.INT.CTRC.07140 RPL10.Interior.Center-Corridor - Priority - Install Hilti Steel for Cable Tray & Mech Piping Priority Walls & OverHead Active 03/23/26 04/13/26 12.5 1.2
100%
72.5
RPL10.INT.EF2.01610 RPL10.Interior.EF2 - Priority OH - Install Plumbing (*No Scope) OverHead Complete 03/23/26 03/23/26 2.5 0.0
100%
0.0
RPL10.INT.EF2.01650 RPL10.Interior.EF1 - Priority OH - Install Plumbing (*No Scope) OverHead Complete 03/23/26 03/23/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01210 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 6 Active 03/23/26 04/29/26 32.5 16.2
0%
-1.2
RPL10.INT.NS1.02400 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle) OFE NS1 Control Fault Domain 6 Complete 03/23/26 03/25/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01090 RPL10.Interior.NS2 - LV Skids and TopHat Tie-ins (LOE) NS2 - LV Skids and TopHat Active 03/23/26 04/24/26 37.5 12.5
0%
78.8
RPL10.INT.NS2.01091 RPL10.Interior.NS2 - LV Skids and TopHat - Set & Anchor Interconnects NS2 - LV Skids and TopHat Complete 03/23/26 03/27/26 22.5 0.0
100%
0.0
RPL10.INT.NS2.01092 RPL10.Interior.NS2 - LV Skids and TopHat - Maintenance and Reserve Busways NS2 - LV Skids and TopHat Active 03/23/26 04/16/26 18.8 5.0
0%
78.8
RPL10.INT.NS2.01100 RPL10.Interior.NS2 - Tie-ins - WBS Summary Tie-Ins Active 03/23/26 10/21/26 186.2 168.8
0%
83.8
RPL10.INT.SSBC.02300 RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N2.10) Balance of Walls & OverHead Complete 03/23/26 03/31/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP2.1400 RPL10.MCUP.Loop 2 - Tie-ins - WBS Summary Tie-ins Active 03/23/26 06/12/26 72.5 53.8
0%
130.0
RPL10.MCUP.LP2.1420 RPL10.MCUP.Loop 2 - Tie-in SD, DW *No Scope Tie-Ins Mechanical Complete 03/23/26 03/23/26 18.8 0.0
100%
0.0
RPL10.SKN.NS43.01110 RPL10.SKIN.NS43 - Install Roof System - Final Roof (Grid 10-10 / 10-01) Roofing Complete 03/24/26 03/30/26 11.2 0.0
100%
0.0
RPL.10.D.X3710.XG RMUs/MV Skids Set (Loop 1) - RPL10 NS1 Give Milestones (XREFs) Complete 03/25/26 03/25/26 0.0 0.0
100%
0.0
RPL.10.D.X3715.XG RMUs/MV Skids Set (Loop 2) - RPL10 NS1 Give Milestones (XREFs) Complete 03/25/26 03/25/26 0.0 0.0
100%
0.0
RPL10.EY.ENDC.01230 RPL10.EY.End - Install AHU Duct Stands & Ducts OFE Complete 03/25/26 04/07/26 12.5 0.0
100%
0.0
RPL10.INT.CTRC.07540 RPL10.Interior.Center-Corridor - Priority - Install Remaining Mechanical Valves & Piping (Highside OH space) Priority Walls & OverHead Complete 03/25/26 03/27/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.07680 RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (North Side) Priority Walls & OverHead Complete 03/25/26 03/27/26 3.8 0.0
100%
0.0
RPL10.SKN.NS43.01070 RPL10.SKIN.NS43 - Install Roof System - Exterior Wall Sheething Roofing Complete 03/25/26 03/30/26 3.8 0.0
100%
0.0
FR01.1080 FR01: PSI HAC Delays - NS1 - LV Side Aisle - Fourth Delivery (6,7,8,9) FR01: NS1 LV Side Aisle HAC Delays Complete 03/26/26 03/27/26 2.5 0.0
100%
0.0
RPL10.EY.NS1.01210 RPL10.EY.NS1 - HAC Prefab prior to install Tent and Temp Conditions Complete 03/26/26 03/27/26 7.5 0.0
100%
0.0
RPL10.EY.NS2.01160 RPL10.EY.NS2 - Install Tent Overhead Doors Tent and Temp Conditions Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07600 RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall, Tape, Float and Paint (Post Optical Splice) Priority Wall (P3) - Grid Line 10-25 Complete 03/26/26 04/03/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07700 RPL10.Interior.Center-Corridor - Priority - Exterior Wall Tape, Float and Paint Priority Walls & OverHead Active 03/26/26 04/15/26 6.2 3.8
0%
133.8
RPL10.INT.EF2.01670 RPL10.Interior.EF1 - Priority OH - Install Mechanical Piping (Drops On South EF wall for CRAH) OverHead Complete 03/26/26 04/06/26 2.5 0.0
100%
0.0
RPL10.INT.ENDC.6120 RPL10.Interior.End-Corridor - Priority - Install IMP Exterior MEP In-Wall Rough-Ins Priority Walls & OverHead Complete 03/26/26 03/31/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01183 RPL10.Interior.NS1 - LV Skids and TopHat - Top Hat Busway NS1 - LV Skids and TopHat Complete 03/26/26 03/27/26 18.8 0.0
100%
0.0
RPL10.INT.NS1.01320 RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 5 Active 03/26/26 05/18/26 46.2 20.0
0%
-1.2
RPL10.INT.NS1.02460 RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle) (upto 9) OFE NS1 Control Fault Domain 5 Complete 03/26/26 03/27/26 3.8 0.0
100%
0.0
RPL10.SKN.N.01020 RPL10.SKIN.North - Install IMP EJ - Grid lines 10-31/30 Expansion Joint Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.SKN.N.01040 RPL10.SKIN.North - Install IMP EJ - Grid lines 10-21/20 Expansion Joint Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.SKN.N.01060 RPL10.SKIN.North - Install IMP EJ - Grid lines 10-11/10 Expansion Joint Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01020 RPL10.SKIN.South - Install IMP EJ - Grid lines 10-31/30 Expansion Joint Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.SKN.SSB.01040 RPL10.SKIN.SSB - Install Louvers Glazing, Doors and Ext Devices Complete 03/26/26 03/27/26 6.2 0.0
100%
0.0
RPL10.STR.NS43.01180 RPL10.Structure.NS43 - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 03/26/26 04/10/26 6.2 0.0
100%
0.0
GCD.RPL10.1725 Start FSHAC set in place - RPL10 - NS12 Construction Milestones Complete 03/27/26 03/27/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01100 RPL10.EY.EF1 - Install RPL-2 FSP Deep Foundation (TCCO est Release 01-May-26) Fiber Support Platform - RPL-2 Complete 03/27/26 04/01/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01140 RPL10.EY.NS2 - Install Tent Electrical Panels Tent and Temp Conditions Complete 03/27/26 04/01/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01150 RPL10.EY.NS2 - Install Tent Heating and Cooling Equipment Tent and Temp Conditions Complete 03/27/26 04/01/26 6.2 0.0
100%
0.0
RPL10.EY.SSB.01120 RPL10.EY.SSB - Install AHU (4) - CFCI OFE Complete 03/27/26 03/27/26 8.8 0.0
100%
0.0
RPL10.INT.EF2.01630 RPL10.Interior.EF2 - Priority OH - Install Mechanical Piping (Drops On North EF wall for CRAH) OverHead Complete 03/27/26 04/07/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01440 RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 4 Active 03/27/26 06/09/26 63.8 20.0
0%
-3.8
RPL10.INT.NS1.02520 RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Row 10 OFE NS1 Control Fault Domain 4 Complete 03/27/26 03/27/26 1.2 0.0
100%
0.0
RPL10.INT.SSBC.02800 RPL10.Interior.SSB-Corridor - BoW - Hang Drywall BoW Balance of Walls & OverHead Complete 03/27/26 04/08/26 8.8 0.0
100%
0.0
RPL10.EY.NS2.01190 RPL10.EY.NS2 - Install Tent Mechanical Tie-ins Tent and Temp Conditions Complete 03/30/26 04/01/26 6.2 0.0
100%
0.0
RPL10.EY.NS3.01110 RPL10.EY.NS3 - Install Tent Tent and Temp Conditions Active 03/30/26 05/01/26 25.0 18.8
0%
101.2
RPL10.EY.NS3.01170 RPL10.EY.NS3 - Install Tent Fit-out Tent and Temp Conditions Active 03/30/26 05/01/26 25.0 18.8
0%
132.5
RPL10.EY.SSB.01170 RPL10.EY.SSB - Install Mechanical Duct Stands & Main Duct (include penetration detail) Tie-ins Active 03/30/26 04/20/26 18.8 7.5
0%
35.0
RPL10.EY.SSB.01180 RPL10.EY.SSB - Tie-ins - WBS Summary Tie-ins Active 03/30/26 08/18/26 123.8 112.5
0%
57.5
RPL10.INT.CTRC.01060 RPL10.Interior.Center-Corridor - Balance Of Walls - WBS Summary Balance of Walls & OverHead Active 03/30/26 07/08/26 87.5 76.2
0%
165.0
RPL10.INT.CTRC.01150 RPL10.Interior.Center-Corridor - BoW - Frame Balance Of Walls (Spoke Tech,Spoke Part, Bathroom, Fire Riser) Balance of Walls & OverHead Complete 03/30/26 04/03/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.07040 RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (East Side) Priority Wall (P6) - Grid Line 10-16 Complete 03/30/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07120 RPL10.Interior.Center-Corridor - BoW - Install Remaining Unistruts & Hangers Balance of Walls & OverHead Complete 03/30/26 04/09/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01100 RPL10.Interior.EF1 - Priority OH - Electrical OverHead Complete 03/30/26 04/06/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01440 RPL10.Interior.End-Corridor - Priority - Install Plumbing (Highside OH Space) Priority Walls & OverHead Active 03/30/26 04/13/26 12.5 1.2
100%
217.5
RPL10.INT.ENDC.6340 RPL10.Interior.End-Corridor - Priority - Tape, Float and Paint Priority Soffit, Fire Safing Both Sides Priority Walls & OverHead Complete 03/30/26 04/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01202 RPL10.Interior.NS1 - MES Skids - Final Piping Tie-Ins & Inspections NS1 - MES Skids Active 03/30/26 05/01/26 30.0 18.8
0%
62.5
RPL10.INT.NS1.01220 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Duct (LV SIde) LV Side Tie-ins Complete 03/30/26 03/30/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01250 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 1 SQ6.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 6 Active 03/30/26 06/08/26 61.2 50.0
0%
40.0
RPL10.INT.NS1.03160 RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Remaining (11-13) OFE NS1 Control Fault Domain 4 Complete 03/30/26 03/30/26 2.5 0.0
100%
0.0
RPL10.INT.SSBC.02840 RPL10.Interior.SSB-Corridor - BoW - QC BoW Backing/In-Wall Balance of Walls & OverHead Complete 03/30/26 04/02/26 5.0 0.0
100%
0.0
RPL10.SKN.EF12.01130 RPL10.SKIN.EF12 - Install Roof System - Install EJ Grid lines 10-11/10 Expansion Joint Complete 03/30/26 04/01/26 2.5 0.0
100%
0.0
RPL10.SKN.NS12.01130 RPL10.SKIN.NS12 - Install Roof System - Install EJ Grid lines 10-21/20 Expansion Joint Complete 03/30/26 04/01/26 2.5 0.0
100%
0.0
RPL10.SKN.S.01040 RPL10.SKIN.South - Install IMP EJ - Grid lines 10-21/20 Expansion Joint Complete 03/30/26 04/01/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01070 RPL10.SKIN.South - Install IMP EJ - Grid lines 10-11/10 Expansion Joint Complete 03/30/26 04/01/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01180 RPL10.EY.NS2 - Install Tent Electrical Tie-ins Tent and Temp Conditions Complete 03/31/26 04/01/26 3.8 0.0
100%
0.0
RPL10.INT.ENDC.6280 RPL10.Interior.End-Corridor - Priority - P7 Wall Hang Drywall (Both Sides) Priority Wall (P7) - Grid Line 10-02 Active 03/31/26 04/17/26 6.2 6.2
0%
153.8
RPL10.INT.NS1.01580 RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 3 Active 03/31/26 06/30/26 80.0 20.0
0%
-6.2
RPL10.INT.NS1.02580 RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle) OFE NS1 Control Fault Domain 3 Complete 03/31/26 04/01/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.03380 RPL10.Interior.SSB - BoW - QC Backings/In-Walls Balance of Walls and OverHead Complete 03/31/26 04/07/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02420 RPL10.Interior.SSB-Corridor - BoW - Tape Finish Paint BoW Balance of Walls & OverHead Active 03/31/26 04/16/26 6.2 5.0
0%
42.5
RPL10.MCUP.LP1.1820 RPL10.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Active 03/31/26 05/18/26 42.5 32.5
0%
488.8
RPL10.MCUP.LP1.1920 RPL10.MCUP.Loop 1 - Install Site Grading for Paving *Start 03/30 Hardscape and Landscape Active 03/31/26 04/20/26 18.8 7.5
0%
463.8
RPL10.SKN.SSB.01370 RPL10.SKIN.BLDG - RFI1103 Parapet Coping PVC Termication Incompatible material Skin Active 03/31/26 04/20/26 5.0 7.5
0%
343.8
RPL10.EY.EF2.01100 RPL10.EY.EF2 - Install FSP - WBS Summary Fiber Support Platform Active 04/01/26 02/01/27 261.2 252.5
0%
78.8
RPL10.EY.EF2.01790 RPL10.EY.EF2 - Trade Partner Mobilization from North to South Fiber Support Platform Complete 04/01/26 04/03/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01200 RPL10.EY.NS2 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/13/26) Tent and Temp Conditions Complete 04/01/26 04/03/26 7.5 0.0
100%
0.0
RPL10.INT.CTRC.07660 RPL10.Interior.Center-Corridor - BoW - Install EZ Path Balance of Walls & OverHead Complete 04/01/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6090 RPL10.Interior.End-Corridor - Priority - Install FA (Highside OH space) Priority Walls & OverHead Complete 04/01/26 04/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02420 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (HAC) OFE NS1 Control Fault Domain 6 Active 04/01/26 04/24/26 25.0 12.5
0%
-11.2
RPL10.INT.NS2.01110 RPL10.Interior.NS2 - MES Skids Tie-ins (LOE) NS2 - MES Skids Active 04/01/26 06/25/26 75.0 66.2
0%
157.5