Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
70
Completed
30
In Progress
75
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.CTRC.07580 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall/Backing (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/19/26 | 03/25/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6260 |
RPL10.Interior.End-Corridor - Priority - Install IMP Backing Exterior Wall | Priority Walls & OverHead | Complete | 03/19/26 | 03/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04300 |
RPL10.Interior.SSB - Priority - P5 QC - Backings/In-Wall | Priority Wall (P5) - Grid Line 10-C | Complete | 03/19/26 | 03/19/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04400 |
RPL10.Interior.SSB - BoW - Notify META for TV Installation & Conf Sound (+25d Install TV) | Balance of Walls and OverHead | Complete | 03/19/26 | 03/19/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02740 |
RPL10.Interior.SSB-Corridor - BoW - MEPF Frame Hard Lid Rough Ins/Close of Inspection | Balance of Walls & OverHead | Complete | 03/19/26 | 03/19/26 | 1.2 | 0.0 |
|
0.0 |
NW.1100 |
MCUP 600 Ton Crane Demobilization | 600 Ton Crane (MCUP) | Complete | 03/20/26 | 03/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01730 |
RPL10.Interior.Center-Corridor - Priority - Install Drywall at Exterior Wall | Priority Walls & OverHead | Complete | 03/20/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02390 |
RPL10.Interior.NS3 - Priority - Exterior Wall Tape, Float and Paint NS3 (sanding off hours) | OverHead | Complete | 03/20/26 | 04/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02330 |
RPL10.Interior.NS4 - Priority - Exterior Wall Tape, Float and Paint NS4 (sanding off hours) | OverHead | Complete | 03/20/26 | 04/08/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04260 |
RPL10.Interior.SSB - Priority - P5 Two Side Drywall Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/20/26 | 03/30/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.07020 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/20/26 | 04/02/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01160 |
RPL10.Structure.EF12 - SOG Sealant Cure | F/R/P | Complete | 03/20/26 | 03/21/26 | 2.5 | 0.0 |
|
0.0 |
FR01.1060 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Third Delivery (4,5) (4/21/26 Saturday) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/23/26 | 03/23/26 | 1.2 | 0.0 |
|
0.0 |
ICM.B10.1845 |
[NWB] Delivery of FSHAC - Hot Aisle Containment (First Delivery) - RPL10 | Construction | Complete | 03/23/26 | 03/23/26 | 0.0 | 0.0 |
|
0.0 |
JCL.C.1160 |
RPL10 - Cost Risk LOE-9 HAC Install | Cost LOEs | Active | 03/23/26 | 12/07/26 | 206.2 | 206.2 |
|
67.5 |
RPL10.EY.NS2.01220 |
RPL10.EY.NS2 - Install MV, RMUs & Electrical Panels (15) | OFE | Complete | 03/23/26 | 04/10/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01230 |
RPL10.EY.NS2 - OFE - MV - WBS Summary | OFE | Active | 03/23/26 | 05/05/26 | 38.8 | 12.5 |
|
31.2 |
RPL10.EY.NS4.01090 |
RPL10.EY.NS4 - Install Tent | Tent and Temp Conditions | Active | 03/23/26 | 04/20/26 | 25.0 | 7.5 |
|
115.0 |
RPL10.EY.NS4.01170 |
RPL10.EY.NS4 - Install Tent Fit-out | Tent and Temp Conditions | Active | 03/23/26 | 04/20/26 | 25.0 | 7.5 |
|
123.8 |
RPL10.INT.CTRC.07140 |
RPL10.Interior.Center-Corridor - Priority - Install Hilti Steel for Cable Tray & Mech Piping | Priority Walls & OverHead | Active | 03/23/26 | 04/13/26 | 12.5 | 1.2 |
|
72.5 |
RPL10.INT.EF2.01610 |
RPL10.Interior.EF2 - Priority OH - Install Plumbing (*No Scope) | OverHead | Complete | 03/23/26 | 03/23/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01650 |
RPL10.Interior.EF1 - Priority OH - Install Plumbing (*No Scope) | OverHead | Complete | 03/23/26 | 03/23/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01210 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 6 | Active | 03/23/26 | 04/29/26 | 32.5 | 16.2 |
|
-1.2 |
RPL10.INT.NS1.02400 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle) | OFE NS1 Control Fault Domain 6 | Complete | 03/23/26 | 03/25/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01090 |
RPL10.Interior.NS2 - LV Skids and TopHat Tie-ins (LOE) | NS2 - LV Skids and TopHat | Active | 03/23/26 | 04/24/26 | 37.5 | 12.5 |
|
78.8 |
RPL10.INT.NS2.01091 |
RPL10.Interior.NS2 - LV Skids and TopHat - Set & Anchor Interconnects | NS2 - LV Skids and TopHat | Complete | 03/23/26 | 03/27/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01092 |
RPL10.Interior.NS2 - LV Skids and TopHat - Maintenance and Reserve Busways | NS2 - LV Skids and TopHat | Active | 03/23/26 | 04/16/26 | 18.8 | 5.0 |
|
78.8 |
RPL10.INT.NS2.01100 |
RPL10.Interior.NS2 - Tie-ins - WBS Summary | Tie-Ins | Active | 03/23/26 | 10/21/26 | 186.2 | 168.8 |
|
83.8 |
RPL10.INT.SSBC.02300 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N2.10) | Balance of Walls & OverHead | Complete | 03/23/26 | 03/31/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1400 |
RPL10.MCUP.Loop 2 - Tie-ins - WBS Summary | Tie-ins | Active | 03/23/26 | 06/12/26 | 72.5 | 53.8 |
|
130.0 |
RPL10.MCUP.LP2.1420 |
RPL10.MCUP.Loop 2 - Tie-in SD, DW *No Scope | Tie-Ins Mechanical | Complete | 03/23/26 | 03/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01110 |
RPL10.SKIN.NS43 - Install Roof System - Final Roof (Grid 10-10 / 10-01) | Roofing | Complete | 03/24/26 | 03/30/26 | 11.2 | 0.0 |
|
0.0 |
RPL.10.D.X3710.XG |
RMUs/MV Skids Set (Loop 1) - RPL10 NS1 | Give Milestones (XREFs) | Complete | 03/25/26 | 03/25/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3715.XG |
RMUs/MV Skids Set (Loop 2) - RPL10 NS1 | Give Milestones (XREFs) | Complete | 03/25/26 | 03/25/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01230 |
RPL10.EY.End - Install AHU Duct Stands & Ducts | OFE | Complete | 03/25/26 | 04/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07540 |
RPL10.Interior.Center-Corridor - Priority - Install Remaining Mechanical Valves & Piping (Highside OH space) | Priority Walls & OverHead | Complete | 03/25/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07680 |
RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (North Side) | Priority Walls & OverHead | Complete | 03/25/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01070 |
RPL10.SKIN.NS43 - Install Roof System - Exterior Wall Sheething | Roofing | Complete | 03/25/26 | 03/30/26 | 3.8 | 0.0 |
|
0.0 |
FR01.1080 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Fourth Delivery (6,7,8,9) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/26/26 | 03/27/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01210 |
RPL10.EY.NS1 - HAC Prefab prior to install | Tent and Temp Conditions | Complete | 03/26/26 | 03/27/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01160 |
RPL10.EY.NS2 - Install Tent Overhead Doors | Tent and Temp Conditions | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07600 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall, Tape, Float and Paint (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/26/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07700 |
RPL10.Interior.Center-Corridor - Priority - Exterior Wall Tape, Float and Paint | Priority Walls & OverHead | Active | 03/26/26 | 04/15/26 | 6.2 | 3.8 |
|
133.8 |
RPL10.INT.EF2.01670 |
RPL10.Interior.EF1 - Priority OH - Install Mechanical Piping (Drops On South EF wall for CRAH) | OverHead | Complete | 03/26/26 | 04/06/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6120 |
RPL10.Interior.End-Corridor - Priority - Install IMP Exterior MEP In-Wall Rough-Ins | Priority Walls & OverHead | Complete | 03/26/26 | 03/31/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01183 |
RPL10.Interior.NS1 - LV Skids and TopHat - Top Hat Busway | NS1 - LV Skids and TopHat | Complete | 03/26/26 | 03/27/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01320 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 5 | Active | 03/26/26 | 05/18/26 | 46.2 | 20.0 |
|
-1.2 |
RPL10.INT.NS1.02460 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle) (upto 9) | OFE NS1 Control Fault Domain 5 | Complete | 03/26/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.N.01020 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-31/30 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01040 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-21/20 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01060 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-11/10 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01020 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-31/30 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01040 |
RPL10.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01180 |
RPL10.Structure.NS43 - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/26/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
GCD.RPL10.1725 |
Start FSHAC set in place - RPL10 - NS12 | Construction Milestones | Complete | 03/27/26 | 03/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01100 |
RPL10.EY.EF1 - Install RPL-2 FSP Deep Foundation (TCCO est Release 01-May-26) | Fiber Support Platform - RPL-2 | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01140 |
RPL10.EY.NS2 - Install Tent Electrical Panels | Tent and Temp Conditions | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01150 |
RPL10.EY.NS2 - Install Tent Heating and Cooling Equipment | Tent and Temp Conditions | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01120 |
RPL10.EY.SSB - Install AHU (4) - CFCI | OFE | Complete | 03/27/26 | 03/27/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01630 |
RPL10.Interior.EF2 - Priority OH - Install Mechanical Piping (Drops On North EF wall for CRAH) | OverHead | Complete | 03/27/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01440 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 4 | Active | 03/27/26 | 06/09/26 | 63.8 | 20.0 |
|
-3.8 |
RPL10.INT.NS1.02520 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Row 10 | OFE NS1 Control Fault Domain 4 | Complete | 03/27/26 | 03/27/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02800 |
RPL10.Interior.SSB-Corridor - BoW - Hang Drywall BoW | Balance of Walls & OverHead | Complete | 03/27/26 | 04/08/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01190 |
RPL10.EY.NS2 - Install Tent Mechanical Tie-ins | Tent and Temp Conditions | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01110 |
RPL10.EY.NS3 - Install Tent | Tent and Temp Conditions | Active | 03/30/26 | 05/01/26 | 25.0 | 18.8 |
|
101.2 |
RPL10.EY.NS3.01170 |
RPL10.EY.NS3 - Install Tent Fit-out | Tent and Temp Conditions | Active | 03/30/26 | 05/01/26 | 25.0 | 18.8 |
|
132.5 |
RPL10.EY.SSB.01170 |
RPL10.EY.SSB - Install Mechanical Duct Stands & Main Duct (include penetration detail) | Tie-ins | Active | 03/30/26 | 04/20/26 | 18.8 | 7.5 |
|
35.0 |
RPL10.EY.SSB.01180 |
RPL10.EY.SSB - Tie-ins - WBS Summary | Tie-ins | Active | 03/30/26 | 08/18/26 | 123.8 | 112.5 |
|
57.5 |
RPL10.INT.CTRC.01060 |
RPL10.Interior.Center-Corridor - Balance Of Walls - WBS Summary | Balance of Walls & OverHead | Active | 03/30/26 | 07/08/26 | 87.5 | 76.2 |
|
165.0 |
RPL10.INT.CTRC.01150 |
RPL10.Interior.Center-Corridor - BoW - Frame Balance Of Walls (Spoke Tech,Spoke Part, Bathroom, Fire Riser) | Balance of Walls & OverHead | Complete | 03/30/26 | 04/03/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07040 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (East Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/30/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07120 |
RPL10.Interior.Center-Corridor - BoW - Install Remaining Unistruts & Hangers | Balance of Walls & OverHead | Complete | 03/30/26 | 04/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01100 |
RPL10.Interior.EF1 - Priority OH - Electrical | OverHead | Complete | 03/30/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01440 |
RPL10.Interior.End-Corridor - Priority - Install Plumbing (Highside OH Space) | Priority Walls & OverHead | Active | 03/30/26 | 04/13/26 | 12.5 | 1.2 |
|
217.5 |
RPL10.INT.ENDC.6340 |
RPL10.Interior.End-Corridor - Priority - Tape, Float and Paint Priority Soffit, Fire Safing Both Sides | Priority Walls & OverHead | Complete | 03/30/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01202 |
RPL10.Interior.NS1 - MES Skids - Final Piping Tie-Ins & Inspections | NS1 - MES Skids | Active | 03/30/26 | 05/01/26 | 30.0 | 18.8 |
|
62.5 |
RPL10.INT.NS1.01220 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Duct (LV SIde) | LV Side Tie-ins | Complete | 03/30/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01250 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 1 SQ6.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 6 | Active | 03/30/26 | 06/08/26 | 61.2 | 50.0 |
|
40.0 |
RPL10.INT.NS1.03160 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Remaining (11-13) | OFE NS1 Control Fault Domain 4 | Complete | 03/30/26 | 03/30/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02840 |
RPL10.Interior.SSB-Corridor - BoW - QC BoW Backing/In-Wall | Balance of Walls & OverHead | Complete | 03/30/26 | 04/02/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01130 |
RPL10.SKIN.EF12 - Install Roof System - Install EJ Grid lines 10-11/10 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01130 |
RPL10.SKIN.NS12 - Install Roof System - Install EJ Grid lines 10-21/20 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.S.01040 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-21/20 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01070 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-11/10 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01180 |
RPL10.EY.NS2 - Install Tent Electrical Tie-ins | Tent and Temp Conditions | Complete | 03/31/26 | 04/01/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6280 |
RPL10.Interior.End-Corridor - Priority - P7 Wall Hang Drywall (Both Sides) | Priority Wall (P7) - Grid Line 10-02 | Active | 03/31/26 | 04/17/26 | 6.2 | 6.2 |
|
153.8 |
RPL10.INT.NS1.01580 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 3 | Active | 03/31/26 | 06/30/26 | 80.0 | 20.0 |
|
-6.2 |
RPL10.INT.NS1.02580 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 3 | Complete | 03/31/26 | 04/01/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03380 |
RPL10.Interior.SSB - BoW - QC Backings/In-Walls | Balance of Walls and OverHead | Complete | 03/31/26 | 04/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02420 |
RPL10.Interior.SSB-Corridor - BoW - Tape Finish Paint BoW | Balance of Walls & OverHead | Active | 03/31/26 | 04/16/26 | 6.2 | 5.0 |
|
42.5 |
RPL10.MCUP.LP1.1820 |
RPL10.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Active | 03/31/26 | 05/18/26 | 42.5 | 32.5 |
|
488.8 |
RPL10.MCUP.LP1.1920 |
RPL10.MCUP.Loop 1 - Install Site Grading for Paving *Start 03/30 | Hardscape and Landscape | Active | 03/31/26 | 04/20/26 | 18.8 | 7.5 |
|
463.8 |
RPL10.SKN.SSB.01370 |
RPL10.SKIN.BLDG - RFI1103 Parapet Coping PVC Termication Incompatible material | Skin | Active | 03/31/26 | 04/20/26 | 5.0 | 7.5 |
|
343.8 |
RPL10.EY.EF2.01100 |
RPL10.EY.EF2 - Install FSP - WBS Summary | Fiber Support Platform | Active | 04/01/26 | 02/01/27 | 261.2 | 252.5 |
|
78.8 |
RPL10.EY.EF2.01790 |
RPL10.EY.EF2 - Trade Partner Mobilization from North to South | Fiber Support Platform | Complete | 04/01/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01200 |
RPL10.EY.NS2 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/13/26) | Tent and Temp Conditions | Complete | 04/01/26 | 04/03/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07660 |
RPL10.Interior.Center-Corridor - BoW - Install EZ Path | Balance of Walls & OverHead | Complete | 04/01/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6090 |
RPL10.Interior.End-Corridor - Priority - Install FA (Highside OH space) | Priority Walls & OverHead | Complete | 04/01/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02420 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (HAC) | OFE NS1 Control Fault Domain 6 | Active | 04/01/26 | 04/24/26 | 25.0 | 12.5 |
|
-11.2 |
RPL10.INT.NS2.01110 |
RPL10.Interior.NS2 - MES Skids Tie-ins (LOE) | NS2 - MES Skids | Active | 04/01/26 | 06/25/26 | 75.0 | 66.2 |
|
157.5 |