Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
15
Completed
47
In Progress
21
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.NS2.01111 |
RPL10.Interior.NS2 - MES Skids - Set & Anchor Interconnects | NS2 - MES Skids | Complete | 04/01/26 | 04/07/26 | 30.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01080 |
RPL10.Interior.NS3 - OFE - WBS Summary | OFE | Active | 04/01/26 | 12/07/26 | 215.0 | 206.2 |
|
67.5 |
RPL10.INT.NS3.02480 |
RPL10.Interior.NS3 - OFE - MES Skids - Pre Set 30"" Piping | OFE | Active | 04/01/26 | 04/17/26 | 12.5 | 6.2 |
|
136.2 |
RPL10.INT.NS4.01080 |
RPL10.Interior.NS4 - OFE - WBS Summary | OFE | Active | 04/01/26 | 11/10/26 | 195.0 | 186.2 |
|
82.5 |
RPL10.INT.NS4.02425 |
RPL10.Interior.NS4 - OFE - MES Skids - Pre Set 30"" Piping | OFE | Active | 04/01/26 | 04/17/26 | 12.5 | 6.2 |
|
136.2 |
RPL10.INT.EF1.01090 |
RPL10.Interior.EF1 - Priority OH - Security | OverHead | Active | 04/02/26 | 04/15/26 | 2.5 | 3.8 |
|
170.0 |
RPL10.INT.EF1.01160 |
RPL10.Interior.EF1 - CFCI - WBS Summary | OFE | Active | 04/02/26 | 05/22/26 | 37.5 | 37.5 |
|
111.2 |
RPL10.INT.EF1.01190 |
RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 East | OFE | Active | 04/02/26 | 04/24/26 | 12.5 | 12.5 |
|
30.0 |
RPL10.INT.NS1.01720 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 2 | Active | 04/02/26 | 07/22/26 | 96.2 | 20.0 |
|
-8.8 |
RPL10.INT.NS1.02640 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 2 | Complete | 04/02/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.CBL.1160 |
RPL10.Conn BLDG - Install GS and Production Cabling - WBS Summary | Connectivity | Active | 04/06/26 | 07/27/32 | 1997.5 | 1991.2 |
|
0.0 |
RPL10.EY.NS1.01250 |
RPL10.EY.NS1 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Active | 04/06/26 | 04/17/26 | 12.5 | 6.2 |
|
30.0 |
RPL10.EY.NS1.01260 |
RPL10.EY.NS1 - Tie-ins - WBS Summary | Tie-ins | Active | 04/06/26 | 05/15/26 | 37.5 | 31.2 |
|
72.5 |
RPL10.INT.CTRC.01120 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Lowside OH and In-wall | Balance of Walls & OverHead | Active | 04/06/26 | 04/24/26 | 5.0 | 0.0 |
|
112.5 |
RPL10.INT.CTRC.01240 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & OverHead | Active | 04/06/26 | 04/24/26 | 8.8 | 0.0 |
|
112.5 |
RPL10.INT.CTRC.02480 |
RPL10.Interior.Center-Corridor - Priority - Hang Drywall (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 04/06/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06960 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (West Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 04/06/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01100 |
RPL10.Interior.EF2 - Priority OH - Electrical | OverHead | Complete | 04/06/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6240 |
RPL10.Interior.End-Corridor - Priority - QC Exterior Wall - Backing/In-Wall | Priority Walls & OverHead | Complete | 04/06/26 | 04/07/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01350 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (LV SIde) | LV Side Tie-ins | Complete | 04/06/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01380 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 5 SQ2.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 5 | Active | 04/06/26 | 06/25/26 | 72.5 | 66.2 |
|
38.8 |
RPL10.INT.NS1.02440 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (Mech Side Aisle) | OFE NS1 Control Fault Domain 6 | Active | 04/06/26 | 04/29/26 | 22.5 | 16.2 |
|
-1.2 |
RPL10.INT.NS2.01093 |
RPL10.Interior.NS2 - LV Skids and TopHat - Top Hat Busway | NS2 - LV Skids and TopHat | Active | 04/06/26 | 04/24/26 | 18.8 | 12.5 |
|
78.8 |
RPL10.INT.SSB.01320 |
RPL10.Interior.SSB - BoW - Hang Drywall (Remaining) | Balance of Walls and OverHead | Active | 04/06/26 | 04/16/26 | 3.8 | 0.0 |
|
72.5 |
RPL10.INT.SSB.07040 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Active | 04/06/26 | 04/14/26 | 8.0 | 2.5 |
|
151.2 |
RPL10.INT.SSBC.02380 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical Tie-Ins | Balance of Walls & OverHead | Active | 04/06/26 | 04/14/26 | 8.8 | 2.5 |
|
78.8 |
RPL10.INT.SSBC.02940 |
RPL10.Interior.SSB-Corridor - BoW - F/R/P Pads / Curbs | Balance of Walls & OverHead | Complete | 04/06/26 | 04/07/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01050 |
RPL10.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Active | 04/06/26 | 04/13/26 | 5.0 | 1.2 |
|
203.8 |
RPL10.WP2.01080 |
RPL10.Conn Int IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5275 LF - WBS Summary | Interior | Active | 04/06/26 | 12/28/26 | 230.0 | 223.8 |
|
297.5 |
RPL10.WP2.EF1.1000 |
RPL10.Conn GS.EF1 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Complete | 04/06/26 | 04/08/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.WP2.EF2.1000 |
RPL10.Conn GS.EF2 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Complete | 04/06/26 | 04/08/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01090 |
RPL10.EY.EF2 - Install RPL-3 FSP Deep Foundation ((TCCO est Release 27-Jul-26)) | Fiber Support Platform - RPL-3 | Active | 04/07/26 | 04/21/26 | 6.2 | 6.2 |
|
225.0 |
RPL10.INT.ENDC.6140 |
RPL10.Interior.End-Corridor - Priority - Install Drywall at IMP Exterior Wall | Priority Walls & OverHead | Complete | 04/07/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01880 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 1 | Active | 04/07/26 | 08/12/26 | 112.5 | 20.0 |
|
-11.2 |
RPL10.INT.NS1.02700 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 1 | Complete | 04/07/26 | 04/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01120 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS2 Control Fault Domain 6 | Active | 04/07/26 | 05/19/26 | 38.8 | 33.8 |
|
-15.0 |
RPL10.INT.NS2.02445 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle) | OFE NS2 Control Fault Domain 6 | Active | 04/07/26 | 04/13/26 | 6.2 | 1.2 |
|
-27.5 |
RPL10.INT.NS3.02000 |
RPL10.Interior.NS3 - Priority - Install Draft Curtains (#4 - 6 Days Each * 2 crew) | OverHead | Active | 04/07/26 | 04/21/26 | 15.0 | 8.8 |
|
118.8 |
RPL10.INT.NS4.02000 |
RPL10.Interior.NS4 - Priority - Install Draft Curtains (#4 - 6 Days Each* 2 crew) | OverHead | Active | 04/07/26 | 04/21/26 | 15.0 | 8.8 |
|
115.0 |
RPL10.EY.EF1.01090 |
RPL10.EY.EF1 - Install RPL-1 FSP Columns F/R/P | Fiber Support Platform - RPL-1 | Active | 04/08/26 | 04/14/26 | 6.2 | 2.5 |
|
203.8 |
RPL10.EY.EF2.01170 |
RPL10.EY.EF2 - Install RPL-5 FSP Deep Foundation (TCCO est Release 21-Oct-26) | Fiber Support Platform - RPL-5 | Active | 04/08/26 | 04/17/26 | 6.2 | 6.2 |
|
225.0 |
RPL10.EY.ENDC.01110 |
RPL10.EY.End - Install AHU (4) - CFCI | OFE | Active | 04/08/26 | 04/16/26 | 8.8 | 5.0 |
|
103.8 |
RPL10.EY.NS1.01240 |
RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX01 (04.08.26) | OFE | Active | 04/08/26 | 04/14/26 | 6.2 | 2.5 |
|
33.8 |
RPL10.EY.NS1.01270 |
RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX02 (04.08.26) | OFE | Active | 04/08/26 | 04/14/26 | 6.2 | 2.5 |
|
33.8 |
RPL10.INT.SSB.01120 |
RPL10.Interior.SSB - BoW - Tape Finish Paint (Finish Out) | Balance of Walls and OverHead | Active | 04/08/26 | 04/16/26 | 8.8 | 5.0 |
|
71.2 |
RPL10.INT.EF2.01160 |
RPL10.Interior.EF2 - CFCI - WBS Summary | OFE | Active | 04/09/26 | 06/05/26 | 66.2 | 48.8 |
|
117.5 |
RPL10.INT.EF2.01190 |
RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 East | OFE | Active | 04/09/26 | 05/14/26 | 25.0 | 30.0 |
|
18.8 |
RPL10.MCUP.LP1.1860 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #5 | Tie-Ins Electrical | Active | 04/09/26 | 04/17/26 | 8.8 | 6.2 |
|
22.5 |
RPL10.MCUP.LP1.1960 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #7 | Tie-Ins Electrical | Active | 04/09/26 | 04/21/26 | 11.2 | 8.8 |
|
20.0 |
RPL.10.D.X3720.XG |
RMUs/MV Skids Set (Loop 1) - RPL10 NS2 | Give Milestones (XREFs) | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3725.XG |
RMUs/MV Skids Set (Loop 2) - RPL10 NS2 | Give Milestones (XREFs) | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02500 |
RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Active | 04/10/26 | 04/16/26 | 6.2 | 5.0 |
|
110.0 |
RPL10.INT.CTRC.07020 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (West Side) | Priority Wall (P6) - Grid Line 10-16 | Active | 04/10/26 | 04/16/26 | 6.2 | 5.0 |
|
138.8 |
RPL10.INT.CTRC.07060 |
RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside OH and On-Wall | Balance of Walls & OverHead | Active | 04/10/26 | 04/16/26 | 6.2 | 5.0 |
|
110.0 |
RPL10.INT.ENDC.6360 |
RPL10.Interior.End-Corridor - Priority - Tape Finish Paint Exterior Wall | Priority Walls & OverHead | Active | 04/10/26 | 04/21/26 | 10.0 | 8.8 |
|
115.0 |
RPL10.INT.NS1.03180 |
RPL10.Interior.NS1 - OFE - MES Skids - Set Remaining 30"" Piping | OFE | Active | 04/10/26 | 04/20/26 | 12.5 | 7.5 |
|
138.8 |
RPL10.INT.NS2.03305 |
RPL10.Interior.NS2 - OFE - MES Skids - Set Remaining 30"" Piping | OFE | Active | 04/10/26 | 04/20/26 | 12.5 | 7.5 |
|
138.8 |
RPL10.MCUP.LP1.1720 |
RPL10.MCUP.Loop 1 - Tie-in EPMS #3 | Tie-Ins EPMS | Active | 04/10/26 | 04/20/26 | 7.5 | 7.5 |
|
22.5 |
RPL10.MCUP.LP1.1740 |
RPL10.MCUP.Loop 1 - Tie-in BMS #3 | Tie-Ins BMS | Active | 04/10/26 | 04/21/26 | 8.8 | 8.8 |
|
22.5 |
RPL10.MCUP.LP2.1440 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #2 | OFE | Active | 04/10/26 | 04/13/26 | 2.5 | 1.2 |
|
138.8 |
RPL10.MCUP.LP2.1460 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #4 | OFE | Active | 04/10/26 | 04/13/26 | 2.5 | 1.2 |
|
138.8 |
RPL10.STR.NS43.01160 |
RPL10.Structure.NS43 - SOG Sealant Cure | F/R/P | Complete | 04/10/26 | 04/10/26 | 1.2 | 0.0 |
|
0.0 |
DCC.B10.3010 |
[NWB] Production Gear Delivered [Network Suite] DR/EBB | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3015 |
[NWB] Production Gear Delivered [Network Suite] MA | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
446.2 |
DCC.B10.3020 |
[NWB] Production Gear Delivered [Network Suite] XSW | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
446.2 |
DCC.B10.3025 |
[NWB] Production Gear Delivered [NWS1] Front End (SSW & FSW) | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3027 |
[NWB] Production Gear Delivered [NWS1] Back End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3035 |
[NWB] Production Gear Delivered [NWS2] Front End (SSW & FSW) | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3037 |
[NWB] Production Gear Delivered [NWS2] Back End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3045 |
[NWB] Production Gear Delivered [NWS3] Front End (SSW & FSW) | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3047 |
[NWB] Production Gear Delivered [NWS3] Back End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3055 |
[NWB] Production Gear Delivered [NWS4] Front End (SSW & FSW) | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3057 |
[NWB] Production Gear Delivered [NWS4] Back End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3165 |
[NWB] PortMaps Delivered : GS | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3170 |
[NWB] PortMaps Delivered : Elevations & Cabling | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3175 |
[NWB] PortMaps Delivered :Backbone | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3180 |
[NWB] PortMaps Delivered :Front End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3185 |
[NWB] PortMaps Delivered :Back End | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3300 |
[NWB] Cabling Start : OSP Pathways - Primary GS | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3410 |
[NWB] IBB1.1 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3420 |
[NWB] IBB1.2 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3430 |
[NWB] DCN 1 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3440 |
[NWB] CORP 1 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3450 |
[NWB] CORP OOB1 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3460 |
[NWB] Production Dark Fiber Path 1 - Circuit Delivered | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
DCC.B10.3707 |
[NWB] Cabling Start : General Services (GS) | Connectivity | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
ICM.B10.1805 |
[NWB] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE | Construction | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
JCL.C.1260 |
RPL10 - Cost Risk LOE-14 Cabling | Cost LOEs | Not Started | 04/13/26 | 05/13/26 | 28.8 | 28.8 |
|
217.5 |
JCL.C.1360 |
RPL10 - Cost Risk LOE-19 Connectivity Package 2 - GS Carrier SFZ | Cost LOEs | Not Started | 04/13/26 | 01/25/27 | 246.2 | 246.2 |
|
98.8 |
RPL.10.D.X1410.XR |
Ready for Fiber Support Platform Construction - AI 1 (TCCO est Release 09-Feb-26) | Connectivity (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
221.2 |
RPL.10.D.X3210.XR |
500kva Temp Power Skids Energized (First 10 MW or Gen) | Power (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
53.8 |
RPL.10.D.X4510.XR |
Storm Available for Roof Drain Tie-ins | Pad Ready (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
195.0 |
RPL.CM.D.C5500.XR |
Galaxy Road | Logistics - Onsite Receive XREF Milestones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
RPL.CM.D.C5620.XR |
Naboo Road | Logistics - Onsite Receive XREF Milestones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
1991.2 |
RPL.CM.D.N5605.XR |
LA 183 /Burn Road - Traffic Signal | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
152.5 |
RPL.CM.D.N5620.XR |
LA 183 /Wade - Traffic Signal | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
152.5 |
RPL.CM.D.N5630.XR |
LA 183 /Fortenberry - Traffic Signal | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
508.8 |
RPL.CM.D.N5650.XR |
I-20 / LA 583 Right Turn Lane | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
162.5 |
RPL.CM.D.N5655.XR |
US 80 Traffic Signals at LA 583, LA 183 and LA 609 | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
162.5 |
RPL.CM.D.N5665.XR |
Smalling Widening (LA 183 to Jaggers) | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
162.5 |