Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
15
Completed
47
In Progress
21
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.NS2.01111 RPL10.Interior.NS2 - MES Skids - Set & Anchor Interconnects NS2 - MES Skids Complete 04/01/26 04/07/26 30.0 0.0
100%
0.0
RPL10.INT.NS3.01080 RPL10.Interior.NS3 - OFE - WBS Summary OFE Active 04/01/26 12/07/26 215.0 206.2
0%
67.5
RPL10.INT.NS3.02480 RPL10.Interior.NS3 - OFE - MES Skids - Pre Set 30"" Piping OFE Active 04/01/26 04/17/26 12.5 6.2
0%
136.2
RPL10.INT.NS4.01080 RPL10.Interior.NS4 - OFE - WBS Summary OFE Active 04/01/26 11/10/26 195.0 186.2
0%
82.5
RPL10.INT.NS4.02425 RPL10.Interior.NS4 - OFE - MES Skids - Pre Set 30"" Piping OFE Active 04/01/26 04/17/26 12.5 6.2
0%
136.2
RPL10.INT.EF1.01090 RPL10.Interior.EF1 - Priority OH - Security OverHead Active 04/02/26 04/15/26 2.5 3.8
0%
170.0
RPL10.INT.EF1.01160 RPL10.Interior.EF1 - CFCI - WBS Summary OFE Active 04/02/26 05/22/26 37.5 37.5
0%
111.2
RPL10.INT.EF1.01190 RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 East OFE Active 04/02/26 04/24/26 12.5 12.5
0%
30.0
RPL10.INT.NS1.01720 RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 2 Active 04/02/26 07/22/26 96.2 20.0
0%
-8.8
RPL10.INT.NS1.02640 RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle) OFE NS1 Control Fault Domain 2 Complete 04/02/26 04/06/26 5.0 0.0
100%
0.0
RPL10.CBL.1160 RPL10.Conn BLDG - Install GS and Production Cabling - WBS Summary Connectivity Active 04/06/26 07/27/32 1997.5 1991.2
0%
0.0
RPL10.EY.NS1.01250 RPL10.EY.NS1 - Install Electrical Tie-ins (include penetration detail) Tie-ins Active 04/06/26 04/17/26 12.5 6.2
0%
30.0
RPL10.EY.NS1.01260 RPL10.EY.NS1 - Tie-ins - WBS Summary Tie-ins Active 04/06/26 05/15/26 37.5 31.2
0%
72.5
RPL10.INT.CTRC.01120 RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Lowside OH and In-wall Balance of Walls & OverHead Active 04/06/26 04/24/26 5.0 0.0
0%
112.5
RPL10.INT.CTRC.01240 RPL10.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & OverHead Active 04/06/26 04/24/26 8.8 0.0
0%
112.5
RPL10.INT.CTRC.02480 RPL10.Interior.Center-Corridor - Priority - Hang Drywall (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06960 RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (West Side) Priority Wall (P6) - Grid Line 10-16 Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.EF2.01100 RPL10.Interior.EF2 - Priority OH - Electrical OverHead Complete 04/06/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6240 RPL10.Interior.End-Corridor - Priority - QC Exterior Wall - Backing/In-Wall Priority Walls & OverHead Complete 04/06/26 04/07/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01350 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (LV SIde) LV Side Tie-ins Complete 04/06/26 04/06/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01380 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 5 SQ2.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 5 Active 04/06/26 06/25/26 72.5 66.2
0%
38.8
RPL10.INT.NS1.02440 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (Mech Side Aisle) OFE NS1 Control Fault Domain 6 Active 04/06/26 04/29/26 22.5 16.2
0%
-1.2
RPL10.INT.NS2.01093 RPL10.Interior.NS2 - LV Skids and TopHat - Top Hat Busway NS2 - LV Skids and TopHat Active 04/06/26 04/24/26 18.8 12.5
0%
78.8
RPL10.INT.SSB.01320 RPL10.Interior.SSB - BoW - Hang Drywall (Remaining) Balance of Walls and OverHead Active 04/06/26 04/16/26 3.8 0.0
0%
72.5
RPL10.INT.SSB.07040 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Active 04/06/26 04/14/26 8.0 2.5
0%
151.2
RPL10.INT.SSBC.02380 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Tie-Ins Balance of Walls & OverHead Active 04/06/26 04/14/26 8.8 2.5
0%
78.8
RPL10.INT.SSBC.02940 RPL10.Interior.SSB-Corridor - BoW - F/R/P Pads / Curbs Balance of Walls & OverHead Complete 04/06/26 04/07/26 3.8 0.0
100%
0.0
RPL10.SKN.SSB.01050 RPL10.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Active 04/06/26 04/13/26 5.0 1.2
100%
203.8
RPL10.WP2.01080 RPL10.Conn Int IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5275 LF - WBS Summary Interior Active 04/06/26 12/28/26 230.0 223.8
0%
297.5
RPL10.WP2.EF1.1000 RPL10.Conn GS.EF1 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.WP2.EF2.1000 RPL10.Conn GS.EF2 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.EY.EF2.01090 RPL10.EY.EF2 - Install RPL-3 FSP Deep Foundation ((TCCO est Release 27-Jul-26)) Fiber Support Platform - RPL-3 Active 04/07/26 04/21/26 6.2 6.2
0%
225.0
RPL10.INT.ENDC.6140 RPL10.Interior.End-Corridor - Priority - Install Drywall at IMP Exterior Wall Priority Walls & OverHead Complete 04/07/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01880 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 1 Active 04/07/26 08/12/26 112.5 20.0
0%
-11.2
RPL10.INT.NS1.02700 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle) OFE NS1 Control Fault Domain 1 Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
RPL10.INT.NS2.01120 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 6 Active 04/07/26 05/19/26 38.8 33.8
0%
-15.0
RPL10.INT.NS2.02445 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle) OFE NS2 Control Fault Domain 6 Active 04/07/26 04/13/26 6.2 1.2
0%
-27.5
RPL10.INT.NS3.02000 RPL10.Interior.NS3 - Priority - Install Draft Curtains (#4 - 6 Days Each * 2 crew) OverHead Active 04/07/26 04/21/26 15.0 8.8
0%
118.8
RPL10.INT.NS4.02000 RPL10.Interior.NS4 - Priority - Install Draft Curtains (#4 - 6 Days Each* 2 crew) OverHead Active 04/07/26 04/21/26 15.0 8.8
0%
115.0
RPL10.EY.EF1.01090 RPL10.EY.EF1 - Install RPL-1 FSP Columns F/R/P Fiber Support Platform - RPL-1 Active 04/08/26 04/14/26 6.2 2.5
0%
203.8
RPL10.EY.EF2.01170 RPL10.EY.EF2 - Install RPL-5 FSP Deep Foundation (TCCO est Release 21-Oct-26) Fiber Support Platform - RPL-5 Active 04/08/26 04/17/26 6.2 6.2
0%
225.0
RPL10.EY.ENDC.01110 RPL10.EY.End - Install AHU (4) - CFCI OFE Active 04/08/26 04/16/26 8.8 5.0
0%
103.8
RPL10.EY.NS1.01240 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX01 (04.08.26) OFE Active 04/08/26 04/14/26 6.2 2.5
0%
33.8
RPL10.EY.NS1.01270 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX02 (04.08.26) OFE Active 04/08/26 04/14/26 6.2 2.5
0%
33.8
RPL10.INT.SSB.01120 RPL10.Interior.SSB - BoW - Tape Finish Paint (Finish Out) Balance of Walls and OverHead Active 04/08/26 04/16/26 8.8 5.0
0%
71.2
RPL10.INT.EF2.01160 RPL10.Interior.EF2 - CFCI - WBS Summary OFE Active 04/09/26 06/05/26 66.2 48.8
0%
117.5
RPL10.INT.EF2.01190 RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 East OFE Active 04/09/26 05/14/26 25.0 30.0
0%
18.8
RPL10.MCUP.LP1.1860 RPL10.MCUP.Loop 1 - Tie-in Electrical #5 Tie-Ins Electrical Active 04/09/26 04/17/26 8.8 6.2
0%
22.5
RPL10.MCUP.LP1.1960 RPL10.MCUP.Loop 1 - Tie-in Electrical #7 Tie-Ins Electrical Active 04/09/26 04/21/26 11.2 8.8
0%
20.0
RPL.10.D.X3720.XG RMUs/MV Skids Set (Loop 1) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL.10.D.X3725.XG RMUs/MV Skids Set (Loop 2) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.02500 RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Active 04/10/26 04/16/26 6.2 5.0
0%
110.0
RPL10.INT.CTRC.07020 RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (West Side) Priority Wall (P6) - Grid Line 10-16 Active 04/10/26 04/16/26 6.2 5.0
0%
138.8
RPL10.INT.CTRC.07060 RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside OH and On-Wall Balance of Walls & OverHead Active 04/10/26 04/16/26 6.2 5.0
0%
110.0
RPL10.INT.ENDC.6360 RPL10.Interior.End-Corridor - Priority - Tape Finish Paint Exterior Wall Priority Walls & OverHead Active 04/10/26 04/21/26 10.0 8.8
0%
115.0
RPL10.INT.NS1.03180 RPL10.Interior.NS1 - OFE - MES Skids - Set Remaining 30"" Piping OFE Active 04/10/26 04/20/26 12.5 7.5
100%
138.8
RPL10.INT.NS2.03305 RPL10.Interior.NS2 - OFE - MES Skids - Set Remaining 30"" Piping OFE Active 04/10/26 04/20/26 12.5 7.5
100%
138.8
RPL10.MCUP.LP1.1720 RPL10.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Active 04/10/26 04/20/26 7.5 7.5
0%
22.5
RPL10.MCUP.LP1.1740 RPL10.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Active 04/10/26 04/21/26 8.8 8.8
0%
22.5
RPL10.MCUP.LP2.1440 RPL10.MCUP.Loop 2 - Set Electrical Skids #2 OFE Active 04/10/26 04/13/26 2.5 1.2
0%
138.8
RPL10.MCUP.LP2.1460 RPL10.MCUP.Loop 2 - Set Electrical Skids #4 OFE Active 04/10/26 04/13/26 2.5 1.2
0%
138.8
RPL10.STR.NS43.01160 RPL10.Structure.NS43 - SOG Sealant Cure F/R/P Complete 04/10/26 04/10/26 1.2 0.0
100%
0.0
DCC.B10.3010 [NWB] Production Gear Delivered [Network Suite] DR/EBB Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3015 [NWB] Production Gear Delivered [Network Suite] MA Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
446.2
DCC.B10.3020 [NWB] Production Gear Delivered [Network Suite] XSW Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
446.2
DCC.B10.3025 [NWB] Production Gear Delivered [NWS1] Front End (SSW & FSW) Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3027 [NWB] Production Gear Delivered [NWS1] Back End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3035 [NWB] Production Gear Delivered [NWS2] Front End (SSW & FSW) Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3037 [NWB] Production Gear Delivered [NWS2] Back End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3045 [NWB] Production Gear Delivered [NWS3] Front End (SSW & FSW) Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3047 [NWB] Production Gear Delivered [NWS3] Back End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3055 [NWB] Production Gear Delivered [NWS4] Front End (SSW & FSW) Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3057 [NWB] Production Gear Delivered [NWS4] Back End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3165 [NWB] PortMaps Delivered : GS Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3170 [NWB] PortMaps Delivered : Elevations & Cabling Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3175 [NWB] PortMaps Delivered :Backbone Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3180 [NWB] PortMaps Delivered :Front End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3185 [NWB] PortMaps Delivered :Back End Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3300 [NWB] Cabling Start : OSP Pathways - Primary GS Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3410 [NWB] IBB1.1 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3420 [NWB] IBB1.2 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3430 [NWB] DCN 1 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3440 [NWB] CORP 1 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3450 [NWB] CORP OOB1 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3460 [NWB] Production Dark Fiber Path 1 - Circuit Delivered Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
DCC.B10.3707 [NWB] Cabling Start : General Services (GS) Connectivity Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
ICM.B10.1805 [NWB] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
JCL.C.1260 RPL10 - Cost Risk LOE-14 Cabling Cost LOEs Not Started 04/13/26 05/13/26 28.8 28.8
0%
217.5
JCL.C.1360 RPL10 - Cost Risk LOE-19 Connectivity Package 2 - GS Carrier SFZ Cost LOEs Not Started 04/13/26 01/25/27 246.2 246.2
0%
98.8
RPL.10.D.X1410.XR Ready for Fiber Support Platform Construction - AI 1 (TCCO est Release 09-Feb-26) Connectivity (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
221.2
RPL.10.D.X3210.XR 500kva Temp Power Skids Energized (First 10 MW or Gen) Power (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
53.8
RPL.10.D.X4510.XR Storm Available for Roof Drain Tie-ins Pad Ready (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
195.0
RPL.CM.D.C5500.XR Galaxy Road Logistics - Onsite Receive XREF Milestones Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
RPL.CM.D.C5620.XR Naboo Road Logistics - Onsite Receive XREF Milestones Not Started 04/13/26 04/13/26 0.0 0.0
0%
1991.2
RPL.CM.D.N5605.XR LA 183 /Burn Road - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
152.5
RPL.CM.D.N5620.XR LA 183 /Wade - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
152.5
RPL.CM.D.N5630.XR LA 183 /Fortenberry - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
508.8
RPL.CM.D.N5650.XR I-20 / LA 583 Right Turn Lane Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
162.5
RPL.CM.D.N5655.XR US 80 Traffic Signals at LA 583, LA 183 and LA 609 Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
162.5
RPL.CM.D.N5665.XR Smalling Widening (LA 183 to Jaggers) Logistics - Off-Site Receive XREF Milsetones Not Started 04/13/26 04/13/26 0.0 0.0
0%
162.5