Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
3
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.SSB.01420 RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock Loading Dock and Storage Not Started 04/15/26 04/23/26 8.8 8.8
0%
151.2
JCL.C.1420 RPL10 - Cost Risk LOE-19 Connectivity Package 4A - Front End Network Cost LOEs Not Started 04/16/26 04/23/27 320.0 320.0
0%
37.5
RPL.GF.D.N0520.XG Ready for Mortenson to Test CAV1 to GS.EF1 Give Milestones (XREFs) Not Started 04/16/26 04/16/26 0.0 0.0
0%
1986.2
RPL.GF.D.N0530.XG Ready for Mortenson to Test CAV4 to EF1F Give Milestones (XREFs) Not Started 04/16/26 04/16/26 0.0 0.0
0%
1986.2
RPL10.EY.NS4.01180 RPL10.EY.NS4 - Install Tent Electrical Tie-ins Tent and Temp Conditions Not Started 04/16/26 04/20/26 3.8 3.8
0%
116.2
RPL10.INT.EF2.01090 RPL10.Interior.EF2 - Priority OH - Security OverHead Not Started 04/16/26 04/17/26 2.5 2.5
0%
178.8
RPL10.INT.NS1.01145 RPL10.Interior.NS1 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Not Started 04/16/26 04/22/26 6.2 6.2
0%
40.0
RPL10.INT.NS1.01610 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 04/16/26 04/21/26 5.0 5.0
0%
106.2
RPL10.INT.NS1.02070 RPL10.Interior.NS1 - OFE - Ancillary Skids - Set / Place / Anchor (04.01.26) OFE Not Started 04/16/26 04/21/26 5.0 5.0
0%
40.0
RPL10.INT.NS2.01065 RPL10.Interior.NS2 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Not Started 04/16/26 04/22/26 6.2 6.2
0%
40.0
RPL10.INT.NS2.01112 RPL10.Interior.NS2 - MES Skids - Final Piping Tie-Ins & Inspections NS2 - MES Skids Not Started 04/16/26 05/19/26 30.0 30.0
0%
47.5
RPL10.INT.NS2.02020 RPL10.Interior.NS2 - OFE - Ancillary Skids - Set / Place / Anchor (04.01.26) OFE Not Started 04/16/26 04/21/26 5.0 5.0
0%
31.2
RPL10.INT.SSB.01290 RPL10.Interior.SSB - BoW - Frame Hard Lid Balance of Walls and OverHead Not Started 04/16/26 04/22/26 6.2 6.2
0%
113.8
RPL10.INT.SSBC.03460 RPL10.Interior.Center-Corridor - BoW - Bed Tape Paint (OFE Room Closing) Balance of Walls & OverHead Not Started 04/16/26 04/24/26 8.8 8.8
0%
137.5
RPL10.MCUP.LP1.1900 RPL10.MCUP.Loop 1 - Tie-in EPMS #7 Tie-Ins EPMS Not Started 04/16/26 04/24/26 8.8 8.8
0%
17.5
RPL10.MCUP.LP1.1940 RPL10.MCUP.Loop 1 - Tie-in BMS #7 Tie-Ins BMS Not Started 04/16/26 04/27/26 10.0 10.0
0%
17.5
RPL10.MCUP.LP2.1580 RPL10.MCUP.Loop 2 - Tie-in Mechanical (LOE) Tie-Ins Mechanical Not Started 04/16/26 05/14/26 26.2 26.2
0%
142.5
RPL10.MCUP.LP2.1600 RPL10.MCUP.Loop 2 - Tie-in Mechanical #2 WBS Summary Tie-in Mechanical #2 Not Started 04/16/26 04/30/26 13.8 13.8
0%
138.8
RPL10.MCUP.LP2.1920 RPL10.MCUP.Loop 2 - Tie-in Mechanical #6 WBS Summary Tie-in Mechanical #6 Not Started 04/16/26 04/28/26 11.2 11.2
0%
141.2
RPL10.MCUP.LP2.2600 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #2 Tie-in Mechanical #2 Not Started 04/16/26 04/20/26 3.8 3.8
0%
138.8
RPL10.MCUP.LP2.2680 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #6 Tie-in Mechanical #6 Not Started 04/16/26 04/20/26 3.8 3.8
0%
141.2
RPL10.OFCI.6940 OFCI - Delivery ROJ: FE Fiber for CFD NS2.6 (ROJ ) (RVCD ) NS2 Not Started 04/16/26 05/06/26 18.8 18.8
0%
71.2
RPL10.SSB.BB.1160 RPL10.Ext.Build Back.SSB - LO #5 - Install Waterproofing and Flashing Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/16/26 04/17/26 2.5 2.5
0%
161.2
RPL10.WP2.MDF1.1180 RPL10.Conn GSMDF1<>GSMDF2 - Pull, Splice, Terminate & Test Cabling Not Started 04/16/26 04/21/26 5.0 5.0
0%
97.5
RPL10.WP2.MDF1.1200 RPL10.Conn GSMDF1 - Install, Copper & WAPs Cabling Not Started 04/16/26 04/21/26 5.0 5.0
0%
512.5
RPL10.WP2.MDF1.1220 RPL10.Conn GSMDF1 - Includes Rack/ Stack/ Patch Network Not Started 04/16/26 04/21/26 5.0 5.0
0%
45.0
RPL10.WP2.MDF1.1260 RPL10.Conn GS.EF1 <> GS.MDF1 - Pull, Splice, Terminate & Test Cabling Not Started 04/16/26 04/21/26 5.0 5.0
0%
45.0
RPL10.WP2.MDF2.1180 RPL10.Conn GSMDF2 - Install, Copper & WAPs Cabling Not Started 04/16/26 04/21/26 5.0 5.0
0%
512.5
RPL10.WP2.MDF2.1220 RPL10.Conn GSMDF2 - Includes Rack/ Stack/ Patch Network Not Started 04/16/26 04/21/26 5.0 5.0
0%
45.0
RPL10.WP2.MDF2.1260 RPL10.Conn GS.EF2 <> GS.MDF2 - Pull, Splice, Terminate & Test Cabling Not Started 04/16/26 04/21/26 5.0 5.0
0%
45.0
RPL10.WP4.08400 RPL10.Conn 10GSMDF1 Pull/Install Fanout (MMC<>UPC) [PON] Pre ORv3 Rack Not Started 04/16/26 04/21/26 5.0 5.0
0%
187.5
RPL10.EY.ENDC.01120 RPL10.EY.End - Install Perm Paving Hardscape and Landscape Not Started 04/17/26 04/23/26 6.2 6.2
0%
453.8
RPL10.EY.ENDC.01130 RPL10.EY.End - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 04/17/26 05/14/26 25.0 25.0
0%
185.0
RPL10.EY.ENDC.01140 RPL10.EY.End - Install Mechanical Main (include penetration detail) Tie-ins Not Started 04/17/26 05/07/26 18.8 18.8
0%
276.2
RPL10.EY.ENDC.01150 RPL10.EY.End - Tie-ins - WBS Summary Tie-ins Not Started 04/17/26 06/12/26 50.0 50.0
0%
263.8
RPL10.EY.ENDC.01160 RPL10.EY.End - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 04/17/26 06/26/26 62.5 62.5
0%
453.8
RPL10.INT.CTRC.01210 RPL10.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights) Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
110.0
RPL10.INT.CTRC.01270 RPL10.Interior.Center-Corridor - OFE - Install UPS in Corridor (2x UPS) OFE Not Started 04/17/26 04/30/26 12.5 12.5
0%
142.5
RPL10.INT.CTRC.01590 RPL10.Interior.Center-Corridor - BoW - Install Electrical - NS3/NS4 UPS Gallery Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
133.8
RPL10.INT.CTRC.01610 RPL10.Interior.Center-Corridor - BoW - Install Electrical - Lighning Inverter Rooms (N1/N2) Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
133.8
RPL10.INT.CTRC.01630 RPL10.Interior.Center-Corridor - BoW - Install Refrigerant Piping Lowside OH on Supplemental Steel Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
110.0
RPL10.INT.CTRC.01910 RPL10.Interior.Center-Corridor - BoW - Install Backing (Both Side of Corridor Wall) Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
110.0
RPL10.INT.NS1.01630 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/17/26 04/22/26 5.0 5.0
0%
76.2
RPL10.INT.NS1.01660 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 3 SQ4.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 3 Not Started 04/17/26 08/14/26 105.0 105.0
0%
31.2
RPL10.INT.SSB.01720 RPL10.Interior.SSB - BoW - Install Refrigerant Piping Lowside OH (ERAD Room) Balance of Walls and OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
161.2
RPL10.INT.SSB.01840 RPL10.Interior.SSB - BoW - Install Split Systems/Humidifiers Balance of Walls and OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
221.2
RPL10.INT.SSB.02520 RPL10.Interior.SSB - BoW - ACT - Set Wall Angle Balance of Walls and OverHead Not Started 04/17/26 04/27/26 8.8 8.8
0%
71.2
RPL10.INT.SSB.02720 RPL10.Interior.SSB - BoW - Install Acoustic Baffle Ceiling Walls in specific rooms Balance of Walls and OverHead Not Started 04/17/26 04/27/26 8.8 8.8
0%
236.2
RPL10.INT.SSBC.02260 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Carrier MDF (10.N1.09) Balance of Walls & OverHead Not Started 04/17/26 04/27/26 8.8 8.8
0%
221.2
RPL10.INT.SSBC.02280 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Carrier MDF (10.N2.09) Balance of Walls & OverHead Not Started 04/17/26 04/27/26 8.8 8.8
0%
221.2
RPL10.INT.SSBC.02340 RPL10.Interior.SSB-Corridor - BoW - Shell Space Walls (micro plan for finishes) OBSOLETE Balance of Walls & OverHead Not Started 04/17/26 04/22/26 5.0 5.0
0%
66.2
RPL10.INT.SSBC.02600 RPL10.Interior.SSB-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
53.8
RPL10.INT.SSBC.02700 RPL10.Interior.SSB-Corridor - BoW - Install Split Systems/Humidifiers Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
70.0
RPL10.INT.SSBC.02920 RPL10.Interior.SSB-Corridor - BoW - Install Resinous Flooring in specific rooms Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
45.0
RPL10.INT.SSBC.02960 RPL10.Interior.SSB-Corridor - BoW - Electrical Trim Out Balance of Walls & OverHead Not Started 04/17/26 04/27/26 8.8 8.8
0%
42.5
RPL10.INT.SSBC.02980 RPL10.Interior.SSB-Corridor - BoW - Install Lights Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
63.8
RPL10.INT.SSBC.03600 RPL10.Interior.SSB-Corridor - Priority - Install Refrigerant Piping Lowside OH (Electrical Room, Inverter Room) Balance of Walls & OverHead Not Started 04/17/26 04/23/26 6.2 6.2
0%
63.8
RPL10.INT.SSBC.04120 RPL10.Interior.SSB-Corridor - BoW - Install Fire Alarm Panel Balance of Walls & OverHead Not Started 04/17/26 04/20/26 2.5 2.5
0%
73.8
RPL10.MCUP.LP2.1740 RPL10.MCUP.Loop 2 - Tie-in Electrical #4 Tie-Ins Electrical Not Started 04/17/26 04/27/26 8.8 8.8
0%
143.8
RPL10.MCUP.LP2.2660 RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #4 Tie-in Mechanical #4 Not Started 04/17/26 04/24/26 7.5 7.5
0%
143.8
RPL10.CTRC.BB.3275 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/20/26 04/21/26 2.5 2.5
0%
140.0
RPL10.EY.EF1.01660 RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Erect Shoring & Decking & F/R/P Fiber Support Platform - RPL-2 Not Started 04/20/26 04/24/26 6.2 6.2
0%
217.5
RPL10.EY.ENDC.01270 RPL10.Interior.End-Corridor - Install Temp Conditioning Return Duct (Inside) Priority Walls & OverHead Not Started 04/20/26 04/30/26 11.2 11.2
0%
103.8
RPL10.EY.NS1.01280 RPL10.EY.NS1 - Install BMS Tie-ins Tie-ins Not Started 04/20/26 05/01/26 12.5 12.5
0%
30.0
RPL10.INT.CTRC.01230 RPL10.Interior.Center-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & OverHead Not Started 04/20/26 04/28/26 8.8 8.8
0%
145.0
RPL10.INT.EF1.01490 RPL10.Interior.EF1 - Tie-ins - EF1 West - WBS Summary West EF-1 Not Started 04/20/26 07/14/26 75.0 75.0
0%
168.8
RPL10.INT.EF1.01525 RPL10.Interior.EF1 - EF1 West - Install Wall Mounted Ladder Racks on Full Height EF Walls West EF-1 Not Started 04/20/26 04/24/26 6.2 6.2
0%
231.2
RPL10.INT.ENDC.6300 RPL10.Interior.End-Corridor - Priority - P7 Wall Tape Finish Paint (Both Sides) Priority Wall (P7) - Grid Line 10-02 Not Started 04/20/26 04/29/26 10.0 10.0
0%
153.8
RPL10.INT.NS1.01184 RPL10.Interior.NS1 - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Tie-ins NS1 - LV Skids and TopHat Not Started 04/20/26 05/08/26 18.8 18.8
0%
40.0
RPL10.INT.NS1.01260 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/20/26 05/15/26 25.0 25.0
0%
52.5
RPL10.INT.NS1.01270 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/20/26 05/15/26 25.0 25.0
0%
52.5
RPL10.INT.NS1.01280 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Set TWMS, UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 04/20/26 05/15/26 25.0 25.0
0%
38.8
RPL10.INT.NS2.01094 RPL10.Interior.NS2 - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins NS2 - LV Skids and TopHat Not Started 04/20/26 05/08/26 18.8 18.8
0%
40.0
RPL10.INT.NS2.01350 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 4 Not Started 04/20/26 07/01/26 65.0 65.0
0%
-20.0
RPL10.INT.NS2.02565 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle) - Row 10 OFE NS2 Control Fault Domain 4 Not Started 04/20/26 04/20/26 1.2 1.2
0%
-27.5
RPL10.INT.NS3.02360 RPL10.Interior.NS3 - Priority - Install Security OverHead Not Started 04/20/26 04/21/26 2.5 2.5
0%
153.8
RPL10.INT.NS4.02360 RPL10.Interior.NS4 - Priority - Install Security OverHead Not Started 04/20/26 04/21/26 2.5 2.5
0%
133.8
RPL10.INT.SSB.01130 RPL10.Interior.SSB - BoW - Paint (1st Coat) Balance of Walls and OverHead Not Started 04/20/26 04/22/26 3.8 3.8
0%
198.8
RPL10.SSB.BB.1180 RPL10.Ext.Build Back.SSB - LO #5 - Install IMP Exterior Panel Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/20/26 04/21/26 2.5 2.5
0%
161.2
RPL10.SSBC.BB.1340 RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Arch Finishes - Hang Drywall, Paint, Final Finishes Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Not Started 04/20/26 05/15/26 25.0 25.0
0%
183.8
RPL10.WP2.GSIDF.1180 RPL10.Conn GSIDFNE1 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 04/27/26 7.5 7.5
0%
161.2
RPL10.WP2.GSIDF.1340 RPL10.Conn GSIDFN13 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 04/24/26 6.2 6.2
0%
75.0
RPL10.WP2.GSIDF.1480 RPL10.Conn GSIDFN23 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 04/24/26 6.2 6.2
0%
78.8
RPL10.WP2.GSIDF.1560 RPL10.Conn GSIDFN41 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 05/01/26 12.5 12.5
0%
201.2
RPL10.WP2.GSIDF.1800 RPL10.Conn GSIDFN31 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 05/01/26 12.5 12.5
0%
213.8
RPL10.WP2.GSIDF.2840 RPL10.Conn GSIDFNX11 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 05/08/26 18.8 18.8
0%
28.8
RPL10.WP2.GSIDF.2920 RPL10.Conn GSIDFNX12 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 05/08/26 18.8 18.8
0%
28.8
RPL10.WP2.GSIDF.2980 RPL10.Conn GSIDFNX13 Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/20/26 04/27/26 7.5 7.5
0%
40.0
RPL10.CTRC.BB.2000 RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/21/26 04/22/26 2.5 2.5
0%
138.8
RPL10.EY.EF1.01640 RPL10.EY.EF1 - Install RPL-1 FSP Columns Cap Cure Fiber Support Platform - RPL-1 Not Started 04/21/26 05/02/26 15.0 15.0
0%
287.5
RPL10.INT.NS1.01740 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 04/21/26 04/24/26 5.0 5.0
0%
106.2
RPL10.INT.NS2.02465 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (HAC) OFE NS2 Control Fault Domain 6 Not Started 04/21/26 05/18/26 25.0 25.0
0%
-27.5
RPL10.INT.NS2.03285 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle) - Remaining (11-13) OFE NS2 Control Fault Domain 4 Not Started 04/21/26 04/23/26 3.8 3.8
0%
15.0
RPL10.INT.NS4.01070 RPL10.Interior.NS4 - OFE - MES Skids - Set / Place / Anchor OFE Not Started 04/21/26 05/18/26 25.0 25.0
0%
135.0
RPL10.MCUP.LP1.2500 RPL10.MCUP.Loop 1 - Install Bollards Hardscape and Landscape Not Started 04/21/26 05/04/26 12.5 12.5
0%
463.8
RPL10.MCUP.LP2.1780 RPL10.MCUP.Loop 2 - Tie-in EPMS #4 Tie-Ins EPMS Not Started 04/21/26 04/28/26 7.5 7.5
0%
143.8
RPL10.MCUP.LP2.1820 RPL10.MCUP.Loop 2 - Tie-in BMS #4 Tie-Ins BMS Not Started 04/21/26 04/29/26 8.8 8.8
0%
143.8
RPL10.MCUP.LP2.1900 RPL10.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Not Started 04/21/26 04/29/26 8.8 8.8
0%
141.2
RPL10.MCUP.LP2.2620 RPL10.MCUP.Loop 2 - Condenser WaterTie-in Mechanical #2 Tie-in Mechanical #2 Not Started 04/21/26 04/30/26 10.0 10.0
0%
138.8
RPL10.MCUP.LP2.2700 RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #6 Tie-in Mechanical #6 Not Started 04/21/26 04/28/26 7.5 7.5
0%
141.2